Copeland v. Ballard

210 P.3d 1197, 2009 Alas. LEXIS 85, 2009 WL 1813187
CourtAlaska Supreme Court
DecidedJune 26, 2009
DocketS-12648
StatusPublished
Cited by16 cases

This text of 210 P.3d 1197 (Copeland v. Ballard) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Copeland v. Ballard, 210 P.3d 1197, 2009 Alas. LEXIS 85, 2009 WL 1813187 (Ala. 2009).

Opinion

*1200 OPINION

WINFREE, Justice.

I. INTRODUCTION

Two Cordova residents intervened in the administrative appeal of an agency decision approving contingency plans for various oil shipping entities, but then were dismissed from the proceedings for failure to pay ree-ord costs. The intervenors appealed to the superior court, which affirmed the agency decision. Although the underlying proceedings have been completed and the appeal to this court is technically moot, due process questions raised by the intervenors fall within the public interest exception to mootness, and we address those issues.

We generally, but with some caveats, affirm the superior court's decision to uphold the agency's: (1) interpretation of its regulation allowing it to charge a copying fee for the initial production of the record; (2) interpretation of the term "pro rata" for purposes of charging for the compilation of the record; (3) advance payment requirement; and (4) timeliness in producing the record. But we reverse in part the decision of the superior court and hold that the agency's: (1) practice of denying litigants access to the agency record prior to its certification violates due process; and (2) dismissal of the intervenors from the administrative appeal was an abuse of ageney discretion.

II. FACTS AND PROCEEDINGS

Companies operating in many facets of the oil industry-shipment, exploration, production, or transfer-must submit oil discharge prevention and contingency plans to the State of Alaska, Department of Environmental Conservation (DEC) on a regular basis. 1 Contingency plans are "plans to prevent, contain, and clean up oil spills from oil tank vessels, offshore oil exploration or production facilities, and large oil terminal facilities." 2 DEC reviews and then approves contingency plans if they are consistent with statutory and regulatory requirements. 3

Tom Lakosh appealed DEC's approvals of three separate contingency plans for oil tankers and shipping entities operating in and around Valdez; the three appeals were consolidated into a single proceeding. Tom Copeland and Riki Ott moved to intervene in Lakosh's appeal of DEC's approval of the Trans-Alaska Pipeline System tanker discharge prevention and contingency plans ("TAPS Tanker C-Plan") but did not move to intervene in Lakosh's other two appeals of contingency plan approvals. 4 In June 2003 DEC Commissioner Ernesta Ballard granted the intervention motion, stating that Copeland and Ott "are now considered parties to the proceeding I granted to Mr. Lakosh on February 21, 2008," and that Lakosh, Copeland, and Ott each would be responsible for paying one-third of the record costs.

Copeland, Ott, Lakosh, and DEC negotiated the preparation and certification of the administrative record over the next nine months. DEC provided several different cost estimates for record preparation, ranging from $1,270 to $2,848. Negotiations eul-minated in a January 2004 order from the Commissioner that Copeland, Ott, and La-kosh must pay the record costs (choosing one of several options) by February 18, 2004, or face dismissal.

On February 10 Lakosh submitted payment for his share of the record costs. On February 12 Copeland and Ott submitted a letter to the Commissioner with questions and objections to the record preparation process. The Commissioner did not respond. On February 20 DEC's counsel gave Copeland and Ott notice of revised cost estimates for the record preparation.

The Commissioner dismissed Copeland and Ott from the appeal on March 2 for nonpayment. Copeland and Ott then requested *1201 reconsideration of the dismissal and submitted a check for their two-thirds portion of the February 20 estimated record preparation costs under one of the options set forth in the Commissioner's January 2004 order. The Commissioner returned the check and affirmed Copeland and Ott's dismissal from the appeal.

Copeland and Oft appealed to superior court, arguing that the Commissioner violated their due process rights when she dismissed them from the administrative appeal. The superior court concluded that Copeland and Ott's due process rights had not been violated and affirmed their dismissal from the administrative appeal proceeding. Copeland and Ott now appeal the superior court's decision and its award of attorney's fees and other costs to DEC.

Lakosh ultimately abandoned his appeal. The disputed contingency plans expired and DEC approved new contingency plans.

III. STANDARD OF REVIEW

In this case the superior court acted as an intermediate appellate court, and we therefore "independently review the merits of [the] administrative determination." 5 We review questions of mootness under the "independent judgment standard." 6 Dismissals of administrative appeals for failure to prosecute are generally reviewed under the abuse of discretion standard. 7 However we use our "independent judgment when reviewing a lower court's interpretation of statutes and other related legal questions, and when determining whether a party's procedural due process rights have been violated." 8

IV. DISCUSSION

Copeland and Ott claim that DEC violated the due process clause of the Alaska Constitution 9 by dismissing them from the administrative appeal. "[P)rocedural due process under the state constitution requires 'notice and opportunity for hearing appropriate to the nature of the case'" 10 Due process includes the right to a neutral and unbiased decision-maker who presides over proceedings that are fair and that have the appearance of fairness. 11 Copeland and Ott contend that DEC's actions were arbitrary, biased, and unfair, culminating in three specific due process violations: (1) arbitrary denial of access to the record and delay in preparation of the record; (2) arbitrary apportionment of the record costs; and (8) unconstitutional imposition of a litigation-ending sanction.

We first address whether Copeland and Ott's claims are, as DEC and the shipping companies argue, moot.

A. This Appeal Satisfies the Public Interest Exception to the Mootness Doctrine, and We Will Consider Its Merits.

We generally will not consider questions "where events have rendered the *1202 legal issue moot. 12 A claim is moot if it is no longer a "present, live controversy" or if the court system cannot provide the relief the claimant seeks. 13

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank Griswold v. City of Homer
556 P.3d 252 (Alaska Supreme Court, 2024)
Darrell N. v. Jolina N.
Alaska Supreme Court, 2020
Mitchell v. Mitchell
445 P.3d 660 (Alaska Supreme Court, 2019)
Eder v. M-K Rivers
382 P.3d 1137 (Alaska Supreme Court, 2016)
Alaska Community Action on Toxics v. Hartig
321 P.3d 360 (Alaska Supreme Court, 2014)
Mullins v. Local Boundary Commission
226 P.3d 1012 (Alaska Supreme Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
210 P.3d 1197, 2009 Alas. LEXIS 85, 2009 WL 1813187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/copeland-v-ballard-alaska-2009.