Coolidge A L.L.C. v. City of Waukesha

CourtCourt of Appeals of Wisconsin
DecidedJune 24, 2020
Docket2018AP001441
StatusUnpublished

This text of Coolidge A L.L.C. v. City of Waukesha (Coolidge A L.L.C. v. City of Waukesha) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coolidge A L.L.C. v. City of Waukesha, (Wis. Ct. App. 2020).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. June 24, 2020 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2018AP1441 Cir. Ct. No. 2014CV2274

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT II

COOLIDGE A L.L.C. AND COOLIDGE B L.L.C.,

PLAINTIFFS-APPELLANTS,

V.

CITY OF WAUKESHA AND D.F. TOMASINI CONTRACTORS, INC.,

DEFENDANTS-THIRD-PARTY PLAINTIFFS-RESPONDENTS,

D.F. TOMASINI CONTRACTORS, INC., BITCO GENERAL INSURANCE P/K/A BITUMINOUS FIRE AND MARINE INSURANCE, ACUITY, A MUTUAL INSURANCE COMPANY AND STATE CONTRACTORS INC.,

THIRD-PARTY DEFENDANTS-RESPONDENTS.

APPEAL from orders of the circuit court for Waukesha County: JENNIFER R. DOROW, Judge. Affirmed. No. 2018AP1441

Before Neubauer, C.J., Gundrum and Seidl, JJ.

Per curiam opinions may not be cited in any court of this state as precedent

or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3).

¶1 PER CURIAM. Coolidge A L.L.C. and Coolidge B L.L.C. (hereinafter, collectively “Coolidge”) appeal from orders granting summary judgment in favor of the City of Waukesha and the City’s contractor, D.F. Tomasini Contractors, Inc., and dismissing the property damage claims brought by Coolidge arising from a public works project commissioned by the City and completed by Tomasini. For the reasons that follow, we affirm.

BACKGROUND

¶2 Coolidge owns an apartment building that was constructed on top of a landfill located near the intersection of Coolidge Avenue and Scott Avenue. The prior property owners had entered into a settlement agreement with the City to close the landfill. In exchange for not having to contribute financially to the cleanup of the landfill, the prior property owners agreed to release the City from “any property damage claims related to or arising from the Contamination or the condition of the Site or the Property.”

¶3 In 2013, the City began a public works project replacing the water and sewer mains that run down the middle of both avenues. Pursuant to its contract with the City, Tomasini dug up the streets, replaced the sewer and water pipes, and backfilled the trenches so that the streets could be repaved. Tomasini compacted the final layer of fill using a vibrating drum roller.

2 No. 2018AP1441

¶4 Coolidge filed suit alleging several causes of action, all premised on the notion that the construction work performed by Tomasini produced vibrations that caused the soil supporting the Coolidge property to differentially settle, which damaged the property and made it uninhabitable. Coolidge’s complaint alleged negligence against both the City and Tomasini. Coolidge alleged that the City acted negligently by failing to warn Tomasini about the condition of Coolidge’s building and failing to require Tomasini to protect the building. As to Tomasini, Coolidge alleged that it was negligent for failing to inspect Coolidge’s building, for using a vibratory roller to compact the fill, and for failing to monitor the vibrations caused by its compacting work. Coolidge brought three additional causes of action against the City: intentional nuisance; inverse condemnation; and indemnification.

¶5 The City and Tomasini filed motions for summary judgment on all claims. With regard to negligence, both respondents asserted that they were entitled to governmental immunity. The circuit court informed the parties it would first hear Coolidge’s negligence claims and determine whether the City and/or Tomasini were immune from suit.

¶6 In hearing Coolidge’s negligence claims, the circuit court examined the undisputed facts, assumed the existence of negligence, and ultimately determined that both the City and Tomasini were entitled to governmental immunity. With regard to the City, the court “reviewed hundreds of pages of documents showing the extensive detail and instruction that went into the planning and methodology of this project[,]” including:

For example, the City worked with three lead engineers on the project. The first did the underground work and created the underground specifications to be used; the second engineer reviewed the paving and roadwork conditions; and

3 No. 2018AP1441

the third engineer worked with the utility for the water work that was involved. All three of these engineers then had their work reviewed and approved by the City’s lead engineer—engineers—excuse me, singular, engineer. This shows a deliberative, contemplative process involved in arriving at the decisions made concerning this public works project.

The court stated that the City’s deliberative process “in determining the specifications and final construction documents demonstrate, without a doubt, that the City engaged in a quasi-legislative process which this Court will not second- guess.”

¶7 Turning to Tomasini, the circuit court found that the City’s well- considered specifications “became significantly more precise” through the process of requesting proposals, which culminated in Tomasini receiving the contract. The court concluded that Tomasini followed the City’s reasonably precise specifications and was entitled to governmental contractor immunity. The court granted summary judgment to the City and to Tomasini and dismissed Coolidge’s negligence claims.

¶8 At a subsequent hearing on Coolidge’s remaining claims, the circuit court granted summary judgment in favor of the City. The court determined that the settlement agreement between the City and the prior owners of the Coolidge property barred Coolidge’s intentional nuisance and inverse condemnation claims.1 The court went on to address both remaining claims on the merits and

1 Coolidge originally raised as an alternative claim that it was entitled to indemnification under the settlement agreement. The circuit court dismissed this claim, and Coolidge does not raise it on appeal. See Reiman Assocs., Inc. v. R/A Adver., Inc., 102 Wis. 2d 305, 306 n.1., 306 N.W.2d 292 (Ct. App. 1981) (issues not briefed are deemed abandoned).

4 No. 2018AP1441

concluded that even without considering the settlement agreement, the City was entitled to summary judgment.

DISCUSSION

The circuit court properly granted summary judgment in favor of the City on Coolidge’s negligence claim because the City was entitled to governmental immunity.

¶9 Coolidge maintains that both the City and Tomasini were negligent, and that neither is entitled to governmental immunity for their negligent acts. We review summary judgment decisions de novo, applying the same methodology as the circuit court. Palisades Collection LLC v. Kalal, 2010 WI App 38, ¶9, 324 Wis. 2d 180, 781 N.W.2d 503. Summary judgment “shall be rendered if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material facts and that the moving party is entitled to judgment as a matter of law.” WIS. STAT. § 802.08(2) (2017-18).2

¶10 WISCONSIN STAT. § 893.80(4) immunizes governmental subdivisions and their employees and agents from liability “for acts done in the exercise of legislative, quasi-legislative, judicial, or quasi-judicial functions.” The statute “confers broad immunity from suit” and has been interpreted to include “any act that involves the exercise of discretion and judgment.” Lodl v. Progressive N. Ins. Co., 2002 WI 71, ¶¶20-21, 253 Wis. 2d 323, 646 N.W.2d 314.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Showers Appraisals, LLC v. Musson Bros., Inc.
2013 WI 79 (Wisconsin Supreme Court, 2013)
Bostco LLC v. Milwaukee Metropolitan Sewerage District
2013 WI 78 (Wisconsin Supreme Court, 2013)
Estate of Brown v. Mathy Construction Co.
2008 WI App 114 (Court of Appeals of Wisconsin, 2008)
PALISADES COLLECTION LLC v. Kalal
2010 WI App 38 (Court of Appeals of Wisconsin, 2010)
Heuser Ex Rel. Jacobs v. Community Insurance
2009 WI App 151 (Court of Appeals of Wisconsin, 2009)
Vogel v. Grant-Lafayette Electric Cooperative
548 N.W.2d 829 (Wisconsin Supreme Court, 1996)
Zinn v. State
334 N.W.2d 67 (Wisconsin Supreme Court, 1983)
Sweet v. Berge
334 N.W.2d 559 (Court of Appeals of Wisconsin, 1983)
Lodl v. Progressive Northern Insurance
2002 WI 71 (Wisconsin Supreme Court, 2002)
Reiman Associates, Inc. v. R/A Advertising, Inc.
306 N.W.2d 292 (Court of Appeals of Wisconsin, 1981)
Estate of Lyons v. CNA Insurance Companies
558 N.W.2d 658 (Court of Appeals of Wisconsin, 1996)
Milwaukee Metropolitan Sewerage District v. City of Milwaukee
2005 WI 8 (Wisconsin Supreme Court, 2005)
Dr. Randall Melchert v. Pro Electric Contractors
2017 WI 30 (Wisconsin Supreme Court, 2017)
Bronfeld v. Pember Companies, Inc.
2010 WI App 150 (Court of Appeals of Wisconsin, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Coolidge A L.L.C. v. City of Waukesha, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coolidge-a-llc-v-city-of-waukesha-wisctapp-2020.