Cooley Corp. v. Champlain Valley Union High School District 15

477 A.2d 624, 144 Vt. 341, 1984 Vt. LEXIS 475
CourtSupreme Court of Vermont
DecidedApril 20, 1984
DocketNo. 83-150
StatusPublished
Cited by5 cases

This text of 477 A.2d 624 (Cooley Corp. v. Champlain Valley Union High School District 15) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cooley Corp. v. Champlain Valley Union High School District 15, 477 A.2d 624, 144 Vt. 341, 1984 Vt. LEXIS 475 (Vt. 1984).

Opinion

Underwood, J.

Plaintiff, a general contractor, sued the defendant school district for a claimed balance due under a written contract. After a bench trial the Chittenden Superior Court made findings of fact and conclusions of law and entered judgment for the defendant. Plaintiff appealed. Because the trial court failed to make a critical finding, we are compelled to reverse and remand.

Plaintiff and defendant entered into a contract under which the former would improve and construct athletic fields at Champlain Valley Union High School. The contract documents included a bid request, specifications for construction and a purchase order. The pertinent provisions of the contract included the following: (1) “The U.S. Soil Conservation Service indicates there are 1600 cu. yards of usable topsoil at the site of the proposed softball field, and will provide a guide to stripping. The remaining topsoil required for the project must be trucked in by Contractor as a part of the project;” and (2) “The topsoil shall be placed on the field areas to a compacted depth of four (4) inches. The topsoil shall be of such quality that will support vigorous, healthy plant growth and be free of stones, sticks, roots, clods or any other objectionable material . . . .” The total contract price was $36,680 of which defendant paid plaintiff $26,127 before this litigation resulted.

Prior to initiating the lawsuit, plaintiff submitted a written request for payment in the amount of $10,053. Plaintiff considered the job completed, except for final raking and removal of stones, sticks and other debris; plaintiff’s request for payment allowed defendant to retain $500 for this final cleanup. When defendant refused to tender the final payment, plaintiff sued for breach of contract. Defendant denied the material allegations and advanced an affirmative defense of breach of contract. At trial the parties primarily disputed the quality of the topsoil; the trial court found the quality met the contract specifications, and the finding is unchallenged. There was also some evidence of dispute over the quantity of the topsoil. The trial court found that “[t]o comply with the contract requirer [343]*343ment of 4 [inches of] topsoil on the playing field, the total amount of topsoil needed was 2700 square [sic] yards.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ALBERINO v. Balch
2008 VT 130 (Supreme Court of Vermont, 2008)
Waterbury Feed Company, LLC v. O'Neil
2006 VT 126 (Supreme Court of Vermont, 2006)
Waterbury Feed Co., LLC v. O'Neil
2006 VT 126 (Supreme Court of Vermont, 2006)
Kopelman v. Schwag
485 A.2d 1254 (Supreme Court of Vermont, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
477 A.2d 624, 144 Vt. 341, 1984 Vt. LEXIS 475, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cooley-corp-v-champlain-valley-union-high-school-district-15-vt-1984.