Cooke v. Independent Telephone & Telegraph Construction Co.

68 A. 790, 77 N.J.L. 454, 48 Vroom 454, 1908 N.J. Sup. Ct. LEXIS 213
Supreme Court of New Jersey·Decided January 20, 1908·Published

Opinion

The opinion of the court was delivered by

PitNey, J.

Plaintiff, a civil engineer, recovered a verdict and judgment against the defendant company in an action upon contract, founded upon two separate claims, viz.—first, damages for defendant’s act in dismissing him without cause from its employment, after he had been engaged for a term not yet expired; and second, compensation for his services in preparing certain engineering plans for defendant’s use. The present writ of error brings that judgment under review.

The circumstances, as disclosed by the evidence returned with the bills of exceptions, were as follows : The construction company was building water works in Monmouth county for the Tintern Manor Water Company. A part of the works was a large dam, to be built across the valley of the Swimming river. The actual construction of this dam had been let to a [455] firm of subcontractors, Messrs. Flood & Sherrill, and the work was in progress under the supervision of a Mr. Jennyn, president of the construction company, Dr. Wentz, its secretary, and a Mr. Pratt, who was its superintendent and chief engineer. The proposed dam was a large affair, being eight hundred or one thousand feet long, about forty feet in height at the lowest part of the valley, and with a width of two hundred feet at the bottom where the height of the dam was the greatest. It was to be an earthen embankment, stiffened by a central wall of concrete masonry known as a “core wall,” some eight or ten feet in thickness, running through the middle of the embankment. By the original plan it was intended that the bottom of this core wall should rest upon hardpan; but in making the necessary excavation great difficulty was found in reaching hardpan, a substratum of soft mud being encountered that would have necessitated excavation to an additional depth of some forty feet. Up to this point the plaintiff had no connection with the work. His evidence tended to show that he was approached by Flood, one of the subcontractors, who asked plaintiff’s advice with regard to making a foundation for the core wall. Plaintiff suggested a foundation of piling, and at Flood’s request made a free-hand sketch to illustrate the manner of constructing it. Later in the same day Flood returned to the plaintiff and told him that Wentz liad asked him to request the plaintiff to make a scale drawing. Plaintiff made such a drawing, showing more in detail and with greater accuracy his plan, which included round piles to be driven into the mud, sheet piling to be placed between them, and concrete to be run in around the heads of the piles to make a foundation for the core wall. This scale drawing was submitted by Flood to Mr. Pratt and Dr. Wentz, and the latter two agreed between themselves that Cooke, the plaintiff, should be employed at $150 a month to superintend the setting of the foundation of piles substantially in accordance with his plan. The substance of this conclusion was communicated to the plaintiff by Flood, who, according to plaintiff’s testimony, said to him that “Dr. Wentz wanted him to ascertain if I couldn’t be retained to build that foundation, and that he had author[456] ized him to offer me at the rate of $150 a month to put in that dam until its completion.” What was said between Flood and the plaintiff might have been hearsay, except for the fact that the other evidence tended to show that Wentz and Pratt, as agents of the company, had authorized Flood to communicate with the plaintiff, and that they, after being apprised of the details of the conversations between Flood and the plaintiff, ratified what Flood said and did. The conversations referred to were admitted without objection, and it appeared in evidence that on the strength of what Flood said to the plaintiff the latter went to the scene of the work, saw Pratt, and told him what had been said between Flood and himself. Pratt confirmed what Flood had said, with the result that plaintiff was employed for the defendant company by Pratt and entered at once upon the work. He commenced work on October 10th, 1900, and continued until January 1st following, at which time there was a general stoppage of work, due to the fact that the construction company was short of funds, and the plaintiff was dismissed from the job.

The principal controversies at the trial were—first,'whether the plaintiff was employed under a term contract, or was employed generally and under such circumstances that he might be dismissed at will; and secondly, whether defendant company was liable to paj^ him for making the plan, or whether, on the other hand, this was furnished by him voluntarily, without understanding or agreement that lie should be compensated for it.

Free access — add to your briefcase to read the full text and ask questions with AI

Cooke v. Independent Telephone & Telegraph Construction Co., 68 A. 790, 77 N.J.L. 454, 48 Vroom 454, 1908 N.J. Sup. Ct. LEXIS 213 (N.J. 1908).

68 A. 790 (Cooke v. Independent Telephone & Telegraph Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.