Control Data Corp. v. State Purchasing Agent

2 Mass. Supp. 306
CourtMassachusetts Superior Court
DecidedFebruary 2, 1981
DocketCiv. A. No. 44393
StatusPublished

This text of 2 Mass. Supp. 306 (Control Data Corp. v. State Purchasing Agent) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Control Data Corp. v. State Purchasing Agent, 2 Mass. Supp. 306 (Mass. Ct. App. 1981).

Opinion

FINDINGS AND RULINGS

Introduction

MASON, J.

This is an action brought by plaintiff, Control Data Corporation, against the defendants State Purchasing Agent and State Lottery Commission (Commission) wherein plaintiff seeks declaratory and injunctive relief requiring defendants to evaluate plaintiff’s proposal submitted for the procurement of an OnLine Number Selection Lottery Processing System. The proposal was made in response to a Request for Proposal (RFP) issued by the Commission on July 25, 1980 with a contemplated contract award date of September 30, 1980. Alleging that the defendants failed to evaluate plaintiffs proposal in accordance with the terms of the RFP, plaintiff sought to enjoin the Commission from awarding the contract and was denied a preliminary injunctive relief. Upon the agreement of the parties, the case was assigned for trial and trial commenced on January 5, 1981. The contract award documents for the procurement were executed by the Commission and American Totálisator Co., Inc. (Am Tote) on the date that trial commenced.

Facts

Since May, 1978, the Commission has attempted to award a contract for an OnLine Number Selection Lottery Processing System. The first RFP resulted in a rejection of all bids. The Lottery then allowed rebids on the original RFP resulting in an award to Am Tote, which was subsequently challenged. This challenge was the subject of litigation in Datatrol, Inc. v. State Purchasing Agent, 1980 Mass. Adv. Sh. 299. In Datatrol, the Court held that the problem-oriented specifications of the RFP did not meet the requirements of the public bidding statute, G.L. c. 7, sec. 22. The third RFP was also challenged and it was again determined that the requirements of G.L. c. 7, sec. 22 were applicable and had not been satisfied. Datatrol, Inc. v. Massachusetts State Lottery Commission et al., 1980 Mass. Adv. Sh. 323. The plaintiff had not filed proposals in response to the first three RFPs, and had advised the Commonwealth that it was unable to bid due to the limiting nature of the invitations.

Prior to issuance of the fourth RFP, which is the subject of the instant litigation, prospective vendors, including plaintiff, were issued a preliminary copy of the RFP by the Commission with an invitation to comment on its provisions. In response to thát invitation, the plaintiff submitted a document in which it commented on several contractual terms, suggested alternative terms, discussed various characteristics of the Massachusetts game products and services, and offered modifications based on its experience with lottery systems in several other states. (Exhibit 4.)

[308]*308On July 25,1980, the Commission issued the fourth RFP, Requisition 1981-11, (Exh. 1) and delivered copies to four industry vendors, including the plaintiff. The, RFP contained specifications for the procurement of an on-line computer-controlled wagering system. The RFP stated that the system was to initially replace a portion of an off-line wagering system currently installed for the processing of the Massachusetts Lottery’s Daily Numbers Game and might eventually replace the entire system. (Exhibit 1, p. iv.)

Several provisions of . the fourth RFP differed from the prior invitations to bid. Although many of the specifications which had been previously left open were more precisely defined, there was a new provision which clearly encouraged bidders who could not meet all requirements to offer alternatives:

Requirements which can be met only partially should be stated with explanation and delivery. Requirements which cannot be met at all should also be stated along with reasons or alternatives which may be employed to obviate the requirement. ... As the procurement is a competitive bid among vendors with strengths in certain areas and liabilities in others, it may turn (>ut that a loss in proposal evaluation points in one category for one vendor may be made up in another category depending upon the bids of other suppliers. (Exhibit 1, pp. 8, 9.)

The RFP also' contained a provision entitled “Exceptions to Bid Specifica-tions,” wherein the Lottery reserved the option to accept bids containing exceptions or deviations from the system specifications “provided such exceptions or deviations will not substantially affect the system’s performance and it is in its best interest to do so.” (Exhibit 1, sec.9.18.)

Sec. 9.48 of the RFP stated that the Commonwealth intended that the award procedure result in an award based on the following factors: (1) quality of the system proposed, (2) satisfaction of the needs of the Commonwealth, and (3) price. It was also stated that each factor would receive the weight assigned it by operation of the award procedure. The section noted that G.L. c. 7, sec. 22 contained no low bidder requirement, that the Commonwealth did not intend to inject such a requirement into the award and that the State Purchasing Agent reserved the right to accept or reject any or all bids if it was deemed in the best interest of the Commonwealth.

In a provision that had not been included in the previous RFPs, Section 9.54 established a Technical Evaluation Committee (TEC) to review and approve the RFP and the specifications contained therein, and to evaluate the vendor proposals received. In evaluating the proposals, the TEC was required to develop a ranking of such proposals and submit a recommendation to the Executive Director of the Lottery.

The procedure to be followed by the TEfc in evaluating the proposals was specifically outlined in Section 9.55 which reads, in part:

Proposals received in response to this invitation to bid shall be evaluated in two major steps. First, technical proposals containing information on the vendor’s proposed system, delivery and capability of the company to support the system proposed will be evaluated utilizing a point evaluation system described in Paragraph 9.56 below. ... Each (representative or firm on the Committee) will arrive at a point score for each bidding vendor. At that point, a consensus of the four individual scores will be agreed upon by the four groups meeting together and then discussing the reasons for the scoring with each vendor then giving a final score. This procedure will be followed prior to the opening of volumes containing pricing information. After an agreed-upon scoring has been done on technical merits, then pricing proposals will be evaluated and scored again utilizing the point evaluation and a grand total scoring of vendor proposals arrived at. The vendor with the highest total point score shall then be recommended for award.

A complete description of the point eval[309]*309uation system is set forth in sec. 9.56, which identifies the four major criteria to be evaluated and assigns a point value to each. Out of a total of 1.00 points,’ 40 were assigned conformance to technical specifications, 40! to system costs, 10 to delivery and the remaining 10 to the criteria of experience, resources, financial stability, performance and contract terms. Further breakdowns within each criterion are also outlined.

A draftsman of the RFP testified that the purpose of the point evaluation procedure was to provide a mechanism for meaningful, manageable comparison of vendors’ bid proposals.

On August 26,1980, the plaintiff made a timely submission of a detailed bid proposal. Three other vendors also submitted proposals: Am Tote, Autotote Ltd. and Datatrol, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morse v. City of Boston
148 N.E. 813 (Massachusetts Supreme Judicial Court, 1925)
Sweezey v. Mayor of Malden
174 N.E. 269 (Massachusetts Supreme Judicial Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
2 Mass. Supp. 306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/control-data-corp-v-state-purchasing-agent-masssuperct-1981.