Contreras v. Vannoy Heating & Air Conditioning, Inc.

892 P.2d 557, 270 Mont. 393, 52 State Rptr. 246, 1995 Mont. LEXIS 51
CourtMontana Supreme Court
DecidedMarch 30, 1995
Docket94-490
StatusPublished
Cited by5 cases

This text of 892 P.2d 557 (Contreras v. Vannoy Heating & Air Conditioning, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contreras v. Vannoy Heating & Air Conditioning, Inc., 892 P.2d 557, 270 Mont. 393, 52 State Rptr. 246, 1995 Mont. LEXIS 51 (Mo. 1995).

Opinion

JUSTICE WEBER

delivered the Opinion of the Court.

This is an appeal from a jury verdict in the Thirteenth Judicial District Court, Yellowstone County, finding for defendants. We affirm.

We consider the following issues on appeal:

I. Did the District Court err when it denied plaintiff’s motions for partial summary judgment and for directed verdict on the issue of liability?

II. Did the District Court improperly instruct the jury?

Brian Contreras (Contreras) worked for the City of Billings on June 30, 1987, when the explosion that is in controversy here occurred. Contreras was a fifteen year old and worked through the District Seven Human Resources Development Council, an agency that provides employment and training for underprivileged minors. Contreras worked as a maintenance trainee at the Parmly Library Building.

*397 On June 30, 1987, Contreras’s supervisor, James Southworth (Southworth), instructed Contreras to clean the boiler room situated on the fourth floor of the building. While cleaning the room with a backpack vacuum cleaner, Contreras hit a valve on a gas line, approximately six inches from the boiler. The valve fell off the gas line and natural gas began to leak out of the line.

Contreras ran after Southworth who immediately came to the boiler room and unsuccessfully attempted to stop the leak. A pilot light on the boiler ignited the gas and an explosion resulted, causing Contreras severe burns.

Contreras filed a complaint on June 20, 1990, against the City of Billings, Southworth, and a number of John Does. Southworth and the City of Billings were dismissed following their motion for summary judgment. Contreras then amended his complaint to add Vannoy Heating & Air Conditioning, Inc. (Vannoy) as a defendant. Vannoy had a contract with the library for the heating, ventilating and air conditioning system (HVAC) maintenance. Contreras alleged he would not have been injured had Vannoy inspected the valve as it was required to do.

Both parties filed cross motions for summary judgment which were denied on March 15,1994. Trial was held on April 18,19 and 20,1994, followed by both parties’ move for a directed verdict. Both were denied. On April 25, 1994, the jury found that Vannoy was not negligent. Contreras’ May 9, 1994, motion for a new trial was denied on May 25, 1994. Contreras appeals from the judgment entered for defendant Vannoy.

I.

Did the District Court err when it denied plaintiff’s motions for partial summary judgment and for directed verdict on the issue of liability?

Contreras argues that under its contract, Vannoy was responsible for all hand valves in the HVAC system and that the gas shut off valve was such a hand valve. Contreras also contends that no one from Vannoy ever inspected the valve; and because the contract specifically calls for inspection of the system of which the valve was a part, the court should have directed a verdict or granted partial summary judgment to Contreras.

Vannoy argues that the gas shut off valve was a nonmaintainable part of the system for which it had no responsibility under the contract. Vannoy further asserts that the contract is ambiguous *398 concerning the valve in question and the jury had the responsibility to decide whether Vannoy had a duty or not.

If there is any evidence that warrants submission to the jury, a directed verdict is inappropriate. Kearney v. KXLF Communications, Inc. (1994), 263 Mont. 407, 869 P.2d 772. A party is entitled to summary judgment only if no genuine issues of material fact exist and it is entitled to judgment as a matter of law. McDonald v. Anderson (1993), 261 Mont. 268, 862 P.2d 402. In order to prove any claim of negligence, a party has to show duty, breach of that duty, and resulting damage caused by the defendant. Lindey’s v. Goodover (1994), 264 Mont. 449, 872 P.2d 764.

The court denied summary judgment because it determined that genuine issues of material fact existed. Following the trial, the court denied both plaintiff’s and defendant’s motion for directed verdict.

In order for Contreras to be granted summary judgment or a directed verdict on the issue ofVannoy’s liability, he had to show that all evidence submitted proves that Vannoy had a duty to Contreras and that it breached that duty. Contreras argues that the existence of a legal duty is a question of law for the court. If there are issues of fact as to the presence or absence of a duty owed to the plaintiff, then the court must instruct the jury to make the initial fact determination, and then apply the correct standard as furnished by the court. Olson v. Kayser (1973), 161 Mont. 241, 505 P.2d 394.

The two parties presented facts demonstrating a controversy as to the existence of a duty owed to Contreras. To make a determination as to the presence of a duty, the jury had to decide whether the valve was a “hand valve” or a “nonmaintainable” part of HVAC or not a part of HVAC at all. Contreras argues that the valve was a hand valve and under the contract repair and maintenance of all hand valves was required. Contreras also referred to another part of the contract which required Vannoy to inspect the entire system and he contends the valve was a part of the system.

Vannoy introduced evidence which demonstrated that the valve was not a part of the HVAC system. Vannoy pointed out that if the valve was part of the piping and duct work on the boiler, then Vannoy was not responsible for inspection or maintenance. Witnesses Aron Schenk and Rod Putnam testified that the valve in question was not part of their responsibility under the contract between Vannoy and the City of Billings. Southworth testified that his maintenance staff worked on valves such as this and only called Vannoy when there was a problem. There is substantial evidence from which the jury could *399 have concluded that under its contract, Vannoy was not responsible for the valve.

In addition to employees of Vannoy, Vannoy presented evidence that the company responsible for the HVAC system before Vannoy took over the contract did not consider the valve as part of its responsibility to inspect or repair. Also, an engineer testified that it was possible to consider the valve as part of the piping and duct work for which Vannoy had no responsibility.

We conclude there were significant issues of material fact which precluded summary judgment. In a similar manner, there remained significant issues of fact as to the presence or absence of a duty owed to Contreras which precluded a directed verdict.

Depending on which set of facts the jury believed, a different duty would ensue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

St. Paul Companies v. Construction Management Co.
96 F. Supp. 2d 1094 (D. Montana, 2000)
Lombardo v. Heisler
Montana Supreme Court, 1995
State v. Weldy
902 P.2d 1 (Montana Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
892 P.2d 557, 270 Mont. 393, 52 State Rptr. 246, 1995 Mont. LEXIS 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contreras-v-vannoy-heating-air-conditioning-inc-mont-1995.