Contractor's Supply of Waterbury, LLC v. Commissioner of Environmental Protection

925 A.2d 1071, 283 Conn. 86, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20168, 2007 Conn. LEXIS 283
CourtSupreme Court of Connecticut
DecidedJuly 10, 2007
DocketSC 17592
StatusPublished
Cited by14 cases

This text of 925 A.2d 1071 (Contractor's Supply of Waterbury, LLC v. Commissioner of Environmental Protection) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contractor's Supply of Waterbury, LLC v. Commissioner of Environmental Protection, 925 A.2d 1071, 283 Conn. 86, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20168, 2007 Conn. LEXIS 283 (Colo. 2007).

Opinion

Opinion

BORDEN, J.

The plaintiff in this declaratory judgment action, Contractor’s Supply of Waterbury, LLC, appeals from the judgment of the trial court rendered in favor of the defendant, the commissioner of environmental protection. The plaintiff contends on appeal that: (1) General Statutes (Rev. to 1999) § 22a-196 violates its right to equal protection and due process under the federal and state constitutions because the statute does not bear a rational relation to a legitimate state interest; and (2) the trial court improperly concluded that the defendant had not applied § 22a-196 retroactively to the plaintiff in violation of General Statutes § 55-3. 1 We *89 disagree, and, accordingly, we affirm the judgment of the trial court.

The plaintiff brought this action seeking a judgment declaring that application of § 22a-196 to the plaintiff violated its rights to equal protection and due process under both the federal and state constitutions and that the defendant improperly had applied the statute retroactively to the plaintiff. The trial court rendered judgment in favor of the defendant. This appeal followed. 2

The parties stipulated to the following relevant facts. On June 23, 1995, pursuant to General Statutes §§ 22a-186 and 22a-174, as well as §§ 22a-174-3 (a), (b), (c), (f) and (g), 22a-174-18, 22a-174-23 and 22a-174-24 of the Regulations of Connecticut State Agencies, the plaintiff applied to the defendant for a permit to construct a hot mix bituminous concrete plant (asphalt plant) at property owned by the plaintiff at 157 East Aurora Street in Waterbury. 3 On November 5, 1996, the defendant issued permit no. 151 to the plaintiff, which included both a permit to construct an asphalt plant at the site and a conditional permit to operate a plant, provided that all emission testing was to be completed and the results found acceptable by the defendant within twelve months after the issuance of the permit, after which time permit no. 151 would expire. The conditional permit to operate stated that the defendant would not issue the plaintiff a final permit to operate until those two conditions were met. At the time that the plaintiff obtained permit no. 151, the agency regulations required, in the event that the holder of such a permit proved unable to complete construction within the time *90 specified, that the holder apply for renewal of the permit at least 120 days prior to its expiration date. Regs., Conn. State Agencies § 22a-174-3 (d) (9). The defendant informed the plaintiff of the deadline for a renewal application in a letter dated November 5, 1996.

On October 27, 1997, after the deadline established by § 22a-174-3 (d) (9) of the Regulations of Connecticut State Agencies had passed, the plaintiff requested a one year extension of permit no. 151. By letter dated January 16, 1998, the plaintiff requested confirmation from the defendant that the permit to construct remained valid, and acknowledged in the letter that the permit to operate had expired. In response, the defendant confirmed that the permit to construct remained valid, and also confirmed that the conditional permit to operate had expired on November 4, 1996, because of the plaintiffs failure to complete emissions testing within one year from issuance of the permit. The defendant’s letter further informed the plaintiff that “[p]rior to commencement of operation, the [plaintiff] must obtain a [p]ermit to [o]perate . . . .”

Subsequently, on May 5, 1998, in response to concerns expressed by the federal Environmental Protection Agency (EPA) regarding the possible harmful effects of fugitive emissions from asphalt plants on public health and the environment, the legislature passed Public Acts 1998, No. 98-112, later codified at General Statutes (Rev. to 1999) § 22a-174 (n), which imposed a moratorium on the issuing of permits for asphalt plants until July 1, 2000. Based on the same concerns expressed by the EPA, on June 1, 1998, the legislature passed Public Acts 1998, No. 98-216, § 4, later codified at General Statutes (Rev. to 1999) § 22a-196, which provided in relevant part: “No asphalt batching or continuous mix facility shall be located in an area which is less than one-third of a mile in linear distance from any hospital, nursing home, school, area of critical *91 environmental concern, watercourse, or area occupied by residential housing. Such distance shall be measured from the outermost perimeter of such facility to the outermost point of such zones provided that any such facility in operation as of December 31, 1997, shall not be subject to the provisions of this section.” On the basis of the plaintiffs own representation that the proposed asphalt plant would be located only 400 feet from the Naugatuck River, the defendant concluded that the proposed location of the facility did not meet the requirements of § 22a-196 because it would have placed the facility less than one third of a mile away from the river. Therefore, on June 28, 2000, the defendant informed the plaintiff that the permit to construct and to operate had been tentatively denied.

Following a trial, the court dismissed the action for lack of subject matter jurisdiction, based on its conclusion that the action was not ripe because § 22a-174 (n) rendered the plaintiffs right to proceed with the permitting process speculative and the plaintiffs alleged injuries hypothetical. The plaintiff appealed from the judgment to the Appellate Court, but withdrew its appeal on July 7, 2004, because the legislature had adjourned without extending the moratorium in § 22a-174 (n) beyond the July 1, 2004 expiration date. 4 At the same time that the plaintiff withdrew its appeal, it filed an unopposed motion to open the judgment of dismissal, which the trial court granted on July 7, 2004. *92 In its subsequent memorandum of decision, the trial court rendered judgment for the defendant. 5

I

The plaintiff first claims that § 22a-196 violates its right to equal protection and due process under the federal and state constitutions because the statute does not bear a rational relation to a legitimate state interest. We disagree.

A

We turn first to the plaintiffs claim that § 22a-196 violates its right to equal protection under the federal constitution. “The constitutionality of a statute presents a question of law over which our review is plenary. ... It is well established that a validly enacted statute carries with it a strong presumption of constitutionality, [and that] those who challenge its constitutionality must sustain the heavy burden of proving its unconstitutionality beyond a reasonable doubt. . . . The court will indulge in every presumption in favor of the statute’s constitutionality .... Therefore, [w]hen a question of constitutionality is raised, courts must approach it with caution, examine it with care, and sustain the legislation unless its invalidity is clear.” (Citation omitted; internal quotation marks omitted.) State v. McKenzie-Adams, 281 Conn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Cole
347 Conn. 284 (Supreme Court of Connecticut, 2023)
State v. Kono
Supreme Court of Connecticut, 2017
State v. Santiago
Supreme Court of Connecticut, 2015
Doe v. Hartford Roman Catholic Diocesan Corp.
Supreme Court of Connecticut, 2015
Watrous v. Town of Preston
902 F. Supp. 2d 243 (D. Connecticut, 2012)
Pereira v. State Bd. of Educ.
37 A.3d 625 (Supreme Court of Connecticut, 2012)
Keane v. Fischetti
300 Conn. 395 (Supreme Court of Connecticut, 2011)
Dutkiewicz v. Dutkiewicz
957 A.2d 821 (Supreme Court of Connecticut, 2008)
Kerrigan v. Commissioner of Public Health
957 A.2d 407 (Supreme Court of Connecticut, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
925 A.2d 1071, 283 Conn. 86, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20168, 2007 Conn. LEXIS 283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contractors-supply-of-waterbury-llc-v-commissioner-of-environmental-conn-2007.