Contractors Engineers International, Inc., D/B/A Trans-Vac Systems v. United States Department of Veterans Affairs

947 F.2d 1298, 37 Cont. Cas. Fed. 76,237, 1991 U.S. App. LEXIS 28431, 1991 WL 238261
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 4, 1991
Docket91-8177
StatusPublished
Cited by8 cases

This text of 947 F.2d 1298 (Contractors Engineers International, Inc., D/B/A Trans-Vac Systems v. United States Department of Veterans Affairs) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contractors Engineers International, Inc., D/B/A Trans-Vac Systems v. United States Department of Veterans Affairs, 947 F.2d 1298, 37 Cont. Cas. Fed. 76,237, 1991 U.S. App. LEXIS 28431, 1991 WL 238261 (5th Cir. 1991).

Opinion

PER CURIAM:

Plaintiff-Appellant Contractors Engineers International, Inc., which does business under the name of Trans-Vac Systems (Trans-Vac), appeals the district court’s dismissal of its suit against the Department of Veterans Affairs (the VA) for lack of standing. Trans-Vac argues that, contrary to the district court’s determination, the VA had sufficient direct and active control over subcontractor selection to satisfy the test for disappointed subcontractor standing set forth in Amdahl Corp. v. Baldrige. 1 Concluding that the district court did not err in finding that the VA did not have direct and active control over subcontractor selection, we affirm.

I. FACTS AND PROCEDURAL HISTORY

The George Hyman Construction Co. (Hyman) entered into a contract with the VA to construct a VA Medical Center in Baltimore, Maryland. Trans-Vac submitted a bid for a subcontract to install a pneumatic soiled linen and trash transport system and stationary refuse compaction system (the system) for the medical facility. Hyman did not select Trans-Vac, however, but gave the subcontract instead to AVAC Systems (AVAC), the wholly-owned subsidiary of a Swedish Company. 2 Trans-Vac complained to the VA that AVAC was not qualified under either (1) the quality assurance specifications for the system written by the VA because AVAC lacked personnel and experience, or (2) the Buy American Act because non-American materials would be used to install the system. After requesting and receiving assurances from Hyman that AVAC’s system complied with the Buy American Act and met the VA’s system specifications, the VA approved the subcontract with AVAC. Nothing in the record suggests that, prior to Trans-Vac’s complaint to the VA about AVAC, the VA did anything to influence subcontractor selection other than promulgating the system specifications.

Trans-Vac brought suit in district court, alleging that the VA’s approval of AVAC violated both the Buy American Act 3 and the Competition in Contracting Act. 4 Trans-Vac asked the district court for in-junctive, declaratory, and monetary relief. The VA moved for summary judgment on the grounds that, as a disappointed subcontractor, Trans-Vac lacked standing to sue the VA under either act. The district court granted the VA’s motion for summary judgment, agreeing that, under the criteria set forth in Amdahl, Trans-Vac did not have standing to sue the VA as a disappointed subcontractor. 5 The district court reasoned that Trans-Vac could have standing under Amdahl only if (1) Hyman, the prime contractor, acted as the VA’s de facto purchasing agent, or (2) the VA controlled or caused the rejection of the subcontractor. The district court determined, however, that Hyman had not acted as the VA’s purchasing agent because Hyman did *1300 not have the power to bind the VA’s credit, and because the mere fact that the VA issued specifications for subcontractors and requested assurances from the prime contractor that it selected a subcontractor who met the specifications does not establish a purchasing agency. 6

The district court also concluded that Trans-Vac could not prevail on the control criterion in Amdahl because the VA did not have direct and active participation in the selection of AVAC or the rejection of Trans-Vac. The court rejected Trans-Vac’s argument that the VA was an active participant in the actual selection of a subcontractor simply because the VA issued quality assurance specifications for subcontracts. 7 The district court reasoned that the VA’s system specifications amounted to “little more than a government request that the subcontractor be somewhat experienced and qualified.” The district court also rejected Trans-Vac’s claim that the VA’s control over subcontractor selection was evidenced when the VA sought and received assurances from the prime contractor that AVAC met the quality assurance specifications. Finally, the district court rejected Trans-Vac’s contention that the VA’s control over subcontractor selection through its system specifications was magnified because four or fewer companies compete in the pneumatic linen and trash transport system industry. 8

Trans-Vac appealed the issue of the VA’s control over subcontractor selection to this court.

II. ANALYSIS

The standing issue presented by this appeal is one of first impression for this circuit. In Amdahl, the district court for the District of Columbia articulated criteria for determining when a disappointed subcontractor has standing to challenge a government procurement action. The Amdahl criteria, which relate principally to the zone-of-interest prong of the test for standing, 9 adopted the factors for determining subcontractor standing identified by the United States Comptroller General in Optimum Systems. 10 Under the Amdahl criteria, a disappointed subcontractor could have standing to challenge an agency procurement action in any of the following limited circumstances:

(i) when the contractor acted as a purchasing agent of the government; (ii) where the government has caused or controlled the rejection or selection of a potential subcontractor; (iii) where agency bad faith or fraud in the approval of a subcontractor is demonstrated; (iv) where a contract was made “for” the *1301 government; or (v) where the agency is entitled to an advance decision. 11

To satisfy the “control” criterion in Amdahl, the government agency must be actively and directly involved in selecting or rejecting a particular subcontractor. As examples of fact patterns that constitute direct control, the Amdahl court noted several decisions cited in Optimum Systems. For example, a disappointed subcontractor has been found to have standing to sue when “[t]he government limited the subcontractor sources and exercised control over every aspect of procurements, such that the prime contractors were ‘mere conduits.’ ” 12 In another case, a disappointed subcontractor was found to have standing when the government “severely limited the prime contractor’s rights of selection of subcontractors and was instrumental in drafting the terms of the subcontract.” 13 In yet another case, a disappointed subcontractor had standing when “[t]he [gjovernment specifically recommended an award of a subcontract to a particular company.” 14

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Validata Chemical Services v. United States Department of Energy
169 F. Supp. 3d 69 (District of Columbia, 2016)
Flour Exchange Building Corp. v. State
524 N.W.2d 496 (Court of Appeals of Minnesota, 1994)
Amtech System Corp. v. Illinois State Toll Highway Authority
637 N.E.2d 619 (Appellate Court of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
947 F.2d 1298, 37 Cont. Cas. Fed. 76,237, 1991 U.S. App. LEXIS 28431, 1991 WL 238261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contractors-engineers-international-inc-dba-trans-vac-systems-v-ca5-1991.