Contract Supply, Inc. v. T.H. Marsh Constr. Co.

2020 Ohio 3922
Ohio Court of Appeals·Decided August 3, 2020·No. CA2019-11-193 CA2019-11-195·Published

Opinion

IN THE COURT OF APPEALS

TWELFTH APPELLATE DISTRICT OF OHIO BUTLER COUNTY

CONTRACT SUPPLY, INC., et al., : CASE NOS. CA2019-11-193 CA2019-11-195

Appellants, :

OPINION

: 8/3/2020 - vs -

:

T.H. MARSH CONSTRUCTION CO., : et al., :

Appellees.

CIVIL APPEAL FROM BUTLER COUNTY COURT OF COMMON PLEAS Case No. CV2019-05-0956

Strauss Troy Co., LPA, Brian J. O'Connell, Stephen E. Schilling, The Federal Reserve Building, 150 East Fourth Street, Cincinnati, Ohio 45202-4018, for appellant, Contract Supply, Inc.

Benjamin, Heather, Iaciofano & Bitter, Co., Bradford C. Weber, Patrick M. O'Neill, 300 Pike Street, Suite 500, Cincinnati, Ohio 45202, for appellant, Anyweather Roofing-Dayton, LLC

Roetzel & Andress, LPA, Morris L. Hawk, 1375 East Ninth Street, One Cleveland Center, 10th Floor, Cleveland, Ohio 44144, for appellee, T.H. Marsh Construction Co.

Isaac Wiles Burkholder & Teetor, LLC, Samuel M. Pipino, Patrick M. Pickett, Two Miranova Place, Suite 700, Columbus, Ohio 43215-1173, for appellee, F.A. Construction, LLC

Barnes & Thornburg LLP, Stephen L. Fink, 88 S. Harrison Street, Suite 600, Fort Wayne, Indiana 46802, for appellees, Senior Living Fairfield LLC dba Storypoint of Fairfield, American Buildings and Contractors Supply Co., Inc., and Butler County Port Authority

CA2019-11-195

U.S. Bank National Association, 13737 Noel Road, Suite 800, Dallas, Texas 75240, for appellee, U.S. Bank National Association

M. POWELL, P.J.

{¶ 1} Appellant, Contract Supply, Inc. ("CSI"), appeals a decision of the Butler County Court of Common Pleas granting the motions to dismiss of appellees, T.H. Marsh Construction Co. ("Marsh"), Senior Living Fairfield, LLC dba Storypoint of Fairfield ("Senior Living"), and the Butler County Port Authority (the "Port Authority").

{¶ 2} This case arose out of a payment dispute related to the construction of the StoryPoint Fairfield Senior Living Center in Fairfield, Ohio. The Port Authority owns the land on which the facility was built. Senior Living was the developer of the facility and now operates it. In October 2016, Senior Living entered into a contract with Marsh (the "Prime Contract") for Marsh to serve as the general contractor for the construction of the facility. Marsh entered into subcontracts with CSI to frame and erect the building and with Anyweather Roofing-Dayton, LLC ("Anyweather"), a successor-in-interest to Noble Roofing, Inc., to construct the roof.

{¶ 3} The subcontracts incorporated the Prime Contract by reference and generally provided that "[a]ny claim arising out of or related to this Subcontract shall be handled in accordance with the Prime Contract[.] All claims must be made by the Subcontractor to Contractor in the same manner as required by Contractor to Owner in the Prime Contract, including, but not limited to, the timing for such claim."

{¶ 4} The Prime Contract, in turn, provided that "[c]laims, disputes, or other matters in controversy arising out of or related to the Contract * * * shall be subject to mediation as a condition precedent to binding dispute resolution." The Prime Contract further provided that "any Claim subject to, but not resolved by, mediation * * * shall be settled by arbitration

CA2019-11-195

* * * or through litigation in the court having jurisdiction. The Owner at his sole discretion shall determine whether to arbitrate or litigate any disputes or claims." These two provisions will be herein referred to as the "dispute resolution clause."

{¶ 5} Senior Living terminated its Prime Contract with Marsh in June 2018 and assumed all of Marsh's rights and responsibilities under the contract. Senior Living notified CSI and Anyweather in July 2018 that it was exercising its right to take assignment of their respective subcontracts. On August 1, 2018, Senior Living terminated the subcontract with CSI. On August 29, 2018, CSI recorded a mechanic's lien for unpaid work in the amount of $356,922.23. Anyweather recorded a mechanic's lien for unpaid work and a separate lien on public funds in December 2018.

{¶ 6} On May 10, 2019, CSI filed a complaint against Senior Living, the Port Authority, Marsh, and other defendants who may claim an interest in the facility such as Anyweather. CSI's complaint sought to foreclose its mechanic's lien against all defendants, asserted claims for breach of contract and violation of the Prompt Payment Act against Marsh and Senior Living and unjust enrichment against Senior Living and the Port Authority, and asserted a claim under R.C. 1311.04(C). Anyweather filed an answer with cross-claims and counterclaims.

{¶ 7} Marsh moved to dismiss CSI's complaint and Anyweather's cross-claims under Civ.R. 12(B)(1), arguing that the common pleas court did not have subject-matter jurisdiction over the parties' dispute because CSI and Anyweather failed to satisfy the condition precedent in their respective subcontracts that they pursue alternative dispute resolution before commencing legal action. Senior Living and the Port Authority jointly moved to dismiss CSI's complaint and Anyweather's cross-claims for lack of subject matter jurisdiction under Civ.R. 12(B)(1) on the same ground. Alternatively, Senior Living and the

CA2019-11-195

Port Authority requested that the litigation be stayed pending arbitration.1

{¶ 8} In its response to the motions to dismiss, CSI argued, inter alia, that the proper remedy was to stay the matter pursuant to R.C. 2711.02(B) rather than dismiss it, and that its claim for foreclosure of its mechanic's lien was not arbitrable under R.C. 2711.01(B)(1) because it involved title to real estate.

{¶ 9} On October 31, 2019, the common pleas court granted the Civ.R. 12(B)(1)

motions to dismiss of Senior Living, the Port Authority, and Marsh. Construing CSI's filing of its mechanic's lien as a "legal act," the common pleas court held it did not have subject- matter jurisdiction under Civ.R.12(B)(1) because CSI failed to satisfy the condition precedent in the mandatory dispute resolution clause that it pursue alternative dispute resolution before commencing legal action. Regarding Marsh, the common pleas court further held that dismissal was appropriate because once Senior Living terminated the Prime Contract and assumed Marsh's rights and responsibilities under the subcontract with CSI, Marsh was relieved of its obligations to CSI. The common pleas court further found that CSI was not entitled to a stay of the proceedings because it was "in default in proceeding with arbitration" under R.C. 2711.02(B).

{¶ 10} CSI now appeals, raising one assignment of error:

{¶ 11} THE TRIAL COURT ERRED BY DISMISSING CSI'S COMPLAINT.

{¶ 12} CSI presents four issues for review. The first issue challenges the common pleas court's dismissal of CSI's claims against Senior Living, the Port Authority, and Marsh for lack of subject-matter jurisdiction by virtue of the dispute resolution clause. CSI argues that the common pleas court has subject-matter jurisdiction over CSI's claims pursuant to

1. Senior Living and Anyweather settled their claims in April 2020. On July 9, 2020, this court granted Anyweather's motion to dismiss its appeal. Contract Supply, Inc. v. T.H. Marsh Construction Co., 12th Dist. Butler Nos. CA2019-11-193 and CA2019-11-195 (July 9, 2020) (Entry Granting Appellant's Motion to Dismiss Appeal).

CA2019-11-195

R.C. 2305.01 and applicable caselaw. The second issue challenges the common pleas court's failure to stay the proceedings pursuant to R.C. 2711.02(B). The third issue challenges the common pleas court's dismissal of CSI's foreclosure claims for lack of subject-matter jurisdiction on the ground that the dispute resolution clause does not apply to such claims under R.C. 2711.01(B)(1). The fourth issue challenges the common pleas court's application of CSI's contractual obligations to defendants that were not parties to its subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Contract Supply, Inc. v. T.H. Marsh Constr. Co., 2020 Ohio 3922 (Ohio Ct. App. 2020).

2020 Ohio 3922 (Contract Supply, Inc. v. T.H. Marsh Constr. Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pappas v. Richmond Towers, L.L.C.
2011 Ohio 5249 (Ohio Court of Appeals, 2011)
Bank of Am., N.A. v. Kuchta (Slip Opinion)
2014 Ohio 4275 (Ohio Supreme Court, 2014)
Bank of Am. v. Telerico
2015 Ohio 4544 (Ohio Court of Appeals, 2015)
Minkin v. Ohio State Home Servs., Inc.
2016 Ohio 5804 (Ohio Court of Appeals, 2016)
Anglin v. Donohoo
2018 Ohio 4484 (Ohio Court of Appeals, 2018)
Digonno v. Hamilton
2019 Ohio 2273 (Ohio Court of Appeals, 2019)
Ford Motor Credit Co. v. Ryan
939 N.E.2d 891 (Ohio Court of Appeals, 2010)