Contract Supply, Inc. v. T.H. Marsh Constr. Co.

2020 Ohio 3922
CourtOhio Court of Appeals
DecidedAugust 3, 2020
DocketCA2019-11-193 CA2019-11-195
StatusPublished

This text of 2020 Ohio 3922 (Contract Supply, Inc. v. T.H. Marsh Constr. Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contract Supply, Inc. v. T.H. Marsh Constr. Co., 2020 Ohio 3922 (Ohio Ct. App. 2020).

Opinion

[Cite as Contract Supply, Inc. v. T.H. Marsh Constr. Co., 2020-Ohio-3922.]

IN THE COURT OF APPEALS

TWELFTH APPELLATE DISTRICT OF OHIO

BUTLER COUNTY

CONTRACT SUPPLY, INC., et al., : CASE NOS. CA2019-11-193 CA2019-11-195 Appellants, : OPINION : 8/3/2020 - vs - :

T.H. MARSH CONSTRUCTION CO., : et al., : Appellees.

CIVIL APPEAL FROM BUTLER COUNTY COURT OF COMMON PLEAS Case No. CV2019-05-0956

Strauss Troy Co., LPA, Brian J. O'Connell, Stephen E. Schilling, The Federal Reserve Building, 150 East Fourth Street, Cincinnati, Ohio 45202-4018, for appellant, Contract Supply, Inc.

Benjamin, Heather, Iaciofano & Bitter, Co., Bradford C. Weber, Patrick M. O'Neill, 300 Pike Street, Suite 500, Cincinnati, Ohio 45202, for appellant, Anyweather Roofing-Dayton, LLC

Roetzel & Andress, LPA, Morris L. Hawk, 1375 East Ninth Street, One Cleveland Center, 10th Floor, Cleveland, Ohio 44144, for appellee, T.H. Marsh Construction Co.

Isaac Wiles Burkholder & Teetor, LLC, Samuel M. Pipino, Patrick M. Pickett, Two Miranova Place, Suite 700, Columbus, Ohio 43215-1173, for appellee, F.A. Construction, LLC

Barnes & Thornburg LLP, Stephen L. Fink, 88 S. Harrison Street, Suite 600, Fort Wayne, Indiana 46802, for appellees, Senior Living Fairfield LLC dba Storypoint of Fairfield, American Buildings and Contractors Supply Co., Inc., and Butler County Port Authority Butler CA2019-11-193 CA2019-11-195

U.S. Bank National Association, 13737 Noel Road, Suite 800, Dallas, Texas 75240, for appellee, U.S. Bank National Association

M. POWELL, P.J.

{¶ 1} Appellant, Contract Supply, Inc. ("CSI"), appeals a decision of the Butler

County Court of Common Pleas granting the motions to dismiss of appellees, T.H. Marsh

Construction Co. ("Marsh"), Senior Living Fairfield, LLC dba Storypoint of Fairfield ("Senior

Living"), and the Butler County Port Authority (the "Port Authority").

{¶ 2} This case arose out of a payment dispute related to the construction of the

StoryPoint Fairfield Senior Living Center in Fairfield, Ohio. The Port Authority owns the

land on which the facility was built. Senior Living was the developer of the facility and now

operates it. In October 2016, Senior Living entered into a contract with Marsh (the "Prime

Contract") for Marsh to serve as the general contractor for the construction of the facility.

Marsh entered into subcontracts with CSI to frame and erect the building and with

Anyweather Roofing-Dayton, LLC ("Anyweather"), a successor-in-interest to Noble Roofing,

Inc., to construct the roof.

{¶ 3} The subcontracts incorporated the Prime Contract by reference and generally

provided that "[a]ny claim arising out of or related to this Subcontract shall be handled in

accordance with the Prime Contract[.] All claims must be made by the Subcontractor to

Contractor in the same manner as required by Contractor to Owner in the Prime Contract,

including, but not limited to, the timing for such claim."

{¶ 4} The Prime Contract, in turn, provided that "[c]laims, disputes, or other matters

in controversy arising out of or related to the Contract * * * shall be subject to mediation as

a condition precedent to binding dispute resolution." The Prime Contract further provided

that "any Claim subject to, but not resolved by, mediation * * * shall be settled by arbitration

-2- Butler CA2019-11-193 CA2019-11-195

* * * or through litigation in the court having jurisdiction. The Owner at his sole discretion

shall determine whether to arbitrate or litigate any disputes or claims." These two provisions

will be herein referred to as the "dispute resolution clause."

{¶ 5} Senior Living terminated its Prime Contract with Marsh in June 2018 and

assumed all of Marsh's rights and responsibilities under the contract. Senior Living notified

CSI and Anyweather in July 2018 that it was exercising its right to take assignment of their

respective subcontracts. On August 1, 2018, Senior Living terminated the subcontract with

CSI. On August 29, 2018, CSI recorded a mechanic's lien for unpaid work in the amount

of $356,922.23. Anyweather recorded a mechanic's lien for unpaid work and a separate

lien on public funds in December 2018.

{¶ 6} On May 10, 2019, CSI filed a complaint against Senior Living, the Port

Authority, Marsh, and other defendants who may claim an interest in the facility such as

Anyweather. CSI's complaint sought to foreclose its mechanic's lien against all defendants,

asserted claims for breach of contract and violation of the Prompt Payment Act against

Marsh and Senior Living and unjust enrichment against Senior Living and the Port Authority,

and asserted a claim under R.C. 1311.04(C). Anyweather filed an answer with cross-claims

and counterclaims.

{¶ 7} Marsh moved to dismiss CSI's complaint and Anyweather's cross-claims

under Civ.R. 12(B)(1), arguing that the common pleas court did not have subject-matter

jurisdiction over the parties' dispute because CSI and Anyweather failed to satisfy the

condition precedent in their respective subcontracts that they pursue alternative dispute

resolution before commencing legal action. Senior Living and the Port Authority jointly

moved to dismiss CSI's complaint and Anyweather's cross-claims for lack of subject matter

jurisdiction under Civ.R. 12(B)(1) on the same ground. Alternatively, Senior Living and the

-3- Butler CA2019-11-193 CA2019-11-195

Port Authority requested that the litigation be stayed pending arbitration.1

{¶ 8} In its response to the motions to dismiss, CSI argued, inter alia, that the proper

remedy was to stay the matter pursuant to R.C. 2711.02(B) rather than dismiss it, and that

its claim for foreclosure of its mechanic's lien was not arbitrable under R.C. 2711.01(B)(1)

because it involved title to real estate.

{¶ 9} On October 31, 2019, the common pleas court granted the Civ.R. 12(B)(1)

motions to dismiss of Senior Living, the Port Authority, and Marsh. Construing CSI's filing

of its mechanic's lien as a "legal act," the common pleas court held it did not have subject-

matter jurisdiction under Civ.R.12(B)(1) because CSI failed to satisfy the condition

precedent in the mandatory dispute resolution clause that it pursue alternative dispute

resolution before commencing legal action. Regarding Marsh, the common pleas court

further held that dismissal was appropriate because once Senior Living terminated the

Prime Contract and assumed Marsh's rights and responsibilities under the subcontract with

CSI, Marsh was relieved of its obligations to CSI. The common pleas court further found

that CSI was not entitled to a stay of the proceedings because it was "in default in

proceeding with arbitration" under R.C. 2711.02(B).

{¶ 10} CSI now appeals, raising one assignment of error:

{¶ 11} THE TRIAL COURT ERRED BY DISMISSING CSI'S COMPLAINT.

{¶ 12} CSI presents four issues for review. The first issue challenges the common

pleas court's dismissal of CSI's claims against Senior Living, the Port Authority, and Marsh

for lack of subject-matter jurisdiction by virtue of the dispute resolution clause. CSI argues

that the common pleas court has subject-matter jurisdiction over CSI's claims pursuant to

1. Senior Living and Anyweather settled their claims in April 2020. On July 9, 2020, this court granted Anyweather's motion to dismiss its appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pappas v. Richmond Towers, L.L.C.
2011 Ohio 5249 (Ohio Court of Appeals, 2011)
Bank of Am., N.A. v. Kuchta (Slip Opinion)
2014 Ohio 4275 (Ohio Supreme Court, 2014)
Bank of Am. v. Telerico
2015 Ohio 4544 (Ohio Court of Appeals, 2015)
Minkin v. Ohio State Home Servs., Inc.
2016 Ohio 5804 (Ohio Court of Appeals, 2016)
Anglin v. Donohoo
2018 Ohio 4484 (Ohio Court of Appeals, 2018)
Digonno v. Hamilton
2019 Ohio 2273 (Ohio Court of Appeals, 2019)
Ford Motor Credit Co. v. Ryan
939 N.E.2d 891 (Ohio Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2020 Ohio 3922, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contract-supply-inc-v-th-marsh-constr-co-ohioctapp-2020.