Continental Illinois National Bank & Trust Co. v. United States

65 F. Supp. 908, 106 Ct. Cl. 503, 1946 U.S. Ct. Cl. LEXIS 52
CourtUnited States Court of Claims
DecidedJune 3, 1946
DocketNo. 45187
StatusPublished

This text of 65 F. Supp. 908 (Continental Illinois National Bank & Trust Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Continental Illinois National Bank & Trust Co. v. United States, 65 F. Supp. 908, 106 Ct. Cl. 503, 1946 U.S. Ct. Cl. LEXIS 52 (cc 1946).

Opinion

Jones, Judge,

delivered the opinion of the court:

The N. P. Severin Company under contract with defendant constructed the Post Office and Court House at Minneapolis, Minnesota. The contract price was $2,118,900. Work was to be completed within 720 calendar days after notice to proceed, which was received by the contractor on July 21,1932. Due to delays and change orders the time for completion was extended 267 days.

The contract provided for the wrecking of certain old buildings on the site of the project and the construction of two large buildings of granite and limestone with structural steel framework. The main building was to contain the post office, court room and various office rooms; the other, known as the repair building, was to contain quarters for the repair of mail trucks, the heating plant and other mechanical devices.

The N. P. Severin Company was a partnership composed of Alfred N. and Nils P. Severin. Both partners died after the suit was filed and the plaintiff was duly authorized to continue to prosecute this suit and to receive any and all money and proceeds resulting therefrom.

The N. P. Severin Company will hereinafter be referred to as the contractor.

The plaintiff alleges that during the progress of the work the contractor was compelled, to incur increased costs and was damaged by four delays which were the fault of the defendant. These are divided into subheads as follows:

1. Caisson delays.
2. Eepair building change.
3. Tile change.
4. Rifle range change.

[536]*536 Caisson Delays

Both buildings were to be supported by concrete pillars placed in excavations made for that purpose. The specifications named tbe depths of such excavations, but stipulated that after such depths should be reached the construction engineer could require test borings to determine whether or not it was necessary to make the excavations deeper and provided that in such event additional compensation would be allowed.

The defendant ordered that 100 of the 136 excavations for caissons to support the main building be continued to greater depths than indicated on the drawings, and similar directions were given in connection with 24 of the 48 excavations for caissons in the repair building. Following other correspondence the defendant’s construction engineer, on April 18,1933, in a letter advised the contractor that payment for such additional work would be upon a cost plus basis with ten percent for overhead and ten percent for profit and liability insurance.

The contractor submitted a claim for additional work on the main building in the total sum of $19,59.5 and asked 42 days’ extension of time required for the performance of this work. It submitted a bill of $5,887 and asked 14 days’ extension of time in connection with the repair building.

On June 24, 1933, the defendant’s supervising architect took exception to certain items, including equipment rental, hoisting engineer service and field force expenses totaling $1,680. In commenting on these items such architect made the following statement:

These charges are based on an estimated 6 weeks’ delay in completion of the building, and as this delay is indefinite and undetermined it should be handled as a claim only when it has actually been established as to the number of days’ delay that the change in the foundation has occasioned.

He also took exception to the equipment rental prices submitted by the subcontractor for jackhammers, breakers, clam-shells and trucks, on the ground that these prices were in excess of the amount that had been paid for similar equipment on other projects.

[537]*537Considerable correspondence followed between tbe contractor and the supervising architect. Finally in the latter part of September 1933 Mr. Lund, defendant’s Assistant Chief Engineer and Estimator, visited the contractor’s office in Minneapolis and in a conference with the contractor’s superintendent, project manager, subcontractor and others went over the two bills submitted by the contractor for excavation work. '

Subsequent to this conference the contractor on September 29, 1933, wrote the Supervising Architect as follows:

On May 11th, 1933, we submitted to you claim in the sum of $19,595.00 for carrying down certain caissons to depths designated by the Construction Engineer which were greater than the depths called for in the contract drawings.
In accordance with conference with Mr. Lund of your Department, we hereby revise the amount of our claim to $17,813.00, and request an extension of 42 days to the contract time.
This claim covers the additional work in the caissons in the Main Building only. Change in caissons in Repair Building is being covered by a separate letter.

On the same date the contractor wrote an identical letter in connection with the repair building except that claim was reduced from $5,887 to $5,318 and an extension of time of 14 •days was requested.

On October 3, 1933, the Assistant Secretary of the Treasury wrote defendant’s construction engineer a letter authorizing the payment of $23,131 for the additional caisson work. The testimony is somewhat conflicting as to just what items were discussed at the conference in September 1933, but it was agreed by witnesses on both sides that temporary heating was not included and was to be left for later determination.

The plaintiff strongly insists that equipment rental, hoisting engineer service and field force expense were not included in the terms of the settlement and points to the letter of the Supervising Architect dated June 24, 1933, quoted above, as bearing out this interpretation. However, in view of the fact that the contractor in its letter of September 29, 1933, revised its'claim and the full amount of the revised claim was paid, and in the light of the further fact that [538]*538in filing its claim for extra payment the contractor confined such claim to the cost of the temporary heating which was concededly not within the terms of the settlement, we think plaintiff is not entitled to recover any additional amount for the other items indicated.

Repair Building Change

After the commencement of the contract work the defendant determined to make extensive changes in the repair building in order to afford additional storage space for handling-mail trucks, bags and other post office equipment. The changes affected the building from the foundation to the roof, including floor slabs, footings,. caissons, and the roof itself.

On January 30, 1933, the construction engineer advised the contractor’s superintendent to cease all activity that would be affected by the proposed additional construction in the repair building; that the architects were proceeding with the necessary drawings and that-extension of time and adjustment would be made in accordance with the contract. It was necessary to consult the Post Office Department and to submit the drawings for its approval and-then submit the drawings to the contractor for a proposal covering the work involved. On April 7, 1933, the contractor protested the delay that was being caused.

The necessary drawings were sent to.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
65 F. Supp. 908, 106 Ct. Cl. 503, 1946 U.S. Ct. Cl. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/continental-illinois-national-bank-trust-co-v-united-states-cc-1946.