Continental Gin Co. v. Sullivan

1915 OK 489, 150 P. 209, 48 Okla. 332, 1915 Okla. LEXIS 631
CourtSupreme Court of Oklahoma
DecidedJune 22, 1915
Docket4543
StatusPublished
Cited by20 cases

This text of 1915 OK 489 (Continental Gin Co. v. Sullivan) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Continental Gin Co. v. Sullivan, 1915 OK 489, 150 P. 209, 48 Okla. 332, 1915 Okla. LEXIS 631 (Okla. 1915).

Opinion

Opinion by

BRETT, C.

The plaintiff in error in this action was plaintiff below, and the parties will be referred to as plaintiff and defendant as they appeared in the lower court.

The plaintiff filed suit in the district court of Carter county against the defendant to recover a balance of $1,271.31, alleged to be due on certain notes given by defendant to plaintiff, and to foreclose a real estate mortgage securing same, and for a balance on an open account of $29.41.

Defendant answered by general denial, admitting the execution of the notes and mortgage, but pleaded as a defense that the notes were given as the purchase price of gin machinery soldi by plaintiff to defendant; that among other machinery purchased of the plaintiff was an automatic tramper used in connection with the press in baling cotton; that the price of the tramper was $150; that *334 the tramper was purchased under a warranty; that it was a. new device, and plaintiff contracted and agreed to furnish a competent man to install this particular piece of machinery, for whose services defendant was to pay $4 per day; that the man furnished to install the tramper was incompetent, and so constructed it that a certain steam pipe was placed directly, over the press, and leaked and- discharged water into the press, and caused water-packed bales to be turned out from plaintiff’s gin; that this steam, pipe was so concealed that defendant could not, and did not, discover it until he learned that his gin was turning ■ out water-packed bales; that the party sent to install the tramper delayed the defendant in starting his gin 12 days longer than was necessary, and that the rental value of the gin for that period was $10 per day; that he refunded as damages for water-packed bales to different parties $225; that the tramper failed -to do the work for which it, was purchased and installed;- that he so notified plaintiff, and tendered it back to plaintiff; that by reason of, his gin turning out water-packed bales his business fell off, and he was damaged thereby $1,000.

• Plaintiff for reply denied that it furnished an incompetent man to install the tramper, but said it furnished, at defendant’s request, a competent man for that purpose, and denied that by its negligence the tramper was so constructed as to turn out water-packed bales, alleging that, if defendant was damaged by reason of the steam emptying into, the bales, it was due to the negligence and incompetency of his employees whose negligence contributed directly to the damages, and that his employees should have discovered the leaking pipe by reasonable diligence; denied that the delay in starting the gin was due to the negligence of the. employee furnished by plaintiff; pleaded that the *335 machinery complained of by defendant was furnished by plaintiff under a written contract which Is, in. part as follows:

“This machinery is fully warranted to be ,of good material and well made, with proper management to perform what is claimed for it in our printed circulars. But, if upon a full and fair trial it should not satisfactorily -do its work, then immediate notice must be given Continental Gin Company, Birmingham, Ala., and to the' agent from whom it was purchased, and reasonable time-allowed-to send a competent man to remedy the defect, and- in. case the trouble be caused from a clearly defined original.defect in the machinery itself, then the Continental Gin Company will furnish the defective part without, charge,, defect in any part not to condemn the other parts. And if, on trial, the machine cannot be made to perform the work of a capacity for which it was sold as per this order, then the Continental Gin Company agrees to take said defective machinery back and refund so much of cash payment and notes as applies to the defective machinery. Any failure on the part of purchaser to comply with his contract releases this warranty entirely.”

—and pleaded that defendant failed to comply; with the provisions of this contract in giving notice arid making complaint, and for that reason plaintiff was released from its warranty.

A trial was had. The issues of fact were submitted to a jury under instructions by the court, which returned the following verdict:

“We, the jury impaneled in the above-entitled cause, do upon our oaths, find for the plaintiff, and fix the amount of its recovery at..........'„„$1,271.31
which amount is to be credited as follows, viz:
By amount demaged defendant..................$800.00
By return of the tramper............................ 150.00 950.00
Balance of. $321.31
*336 with .interest from the filing of this suit at the rate of 10 per cent, the plaintiff to cancel mortgage when the balance due is paid said plaintiff.”

Judgment was rendered on the verdict of the jury, from which the plaintiff appeals.

• Plaintiff insists on six propositions for reversal in its brief.

The first is to the effect that, since the tramper, which is the machinery complained of in defendant’s answer, was purchased' under a written contract, which provided for a certain notice in case it proved unsatisfactory, the defendant was bound to give the notice stipulated in that written contract, or he lost his rights. The position, as a general proposition, is correct, but has no application to the facts in this case. The defendant in the written contract above set put agreed to give immediate notice to the Continental Gin Company, Birmingham, Ala., and to the agent from whom he purchased, in case the machine was unsatisfactory, and that they should be allowed a reasonable time to send a competent man to remedy the defect, and if the machine could not be made to work satisfactorily, then plaintiff agreed to take it back and refund the purchase price, and it is further provided that the failure on the part of the purchaser to comply with this contract releases the warranty entirely. And plaintiff insists that, inasmuch as the defendant did not give the notice required by the contract, he has by the terms of the contract lost all rights. But the plaintiff is not in a position to insist upon the notice required by the written contract, and to complain because it was not given, for the reason that the evidence of both plaintiff and defendant shows that shortly after the installation of the tramper the defendant made some sort of complaint, and in response to this com *337 plaint the plaintiff sent a man to try to remedy the defect in the machinery, which under the holding of this court in Hale et al. v. Van Buren, Heck & Marvin Co., 24 Okla. 13, 103 Pac. 1026, and Port Huron Engine & Threshing Co. v. Ball, 30 Okla. 11, 118 Pac. 393, waived the notice specified in the contract. The plaintiff did not have to act upon a notice different from that specified in the contract, but, if it did act upon a notice different, it by so doing waived the notice provided, and cannot now be heard to complain that the defendant failed to give the notice required of him by the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Webster Drilling Co. v. Walker
286 F.2d 114 (Tenth Circuit, 1961)
Webster Drilling Company v. Walker
286 F.2d 114 (Tenth Circuit, 1961)
Williams v. Frey
1938 OK 280 (Supreme Court of Oklahoma, 1938)
Brockman v. Western Southern Life Ins. Co.
1936 OK 43 (Supreme Court of Oklahoma, 1936)
Hope v. Gordon
1935 OK 805 (Supreme Court of Oklahoma, 1935)
Citizens Nat. Bank of Orange, Va. v. Waugh
78 F.2d 325 (Fourth Circuit, 1935)
Geeslin v. Farney
1926 OK 953 (Supreme Court of Oklahoma, 1926)
Marlin v. Williams
1926 OK 358 (Supreme Court of Oklahoma, 1926)
Cunningham v. Spencer
1925 OK 553 (Supreme Court of Oklahoma, 1925)
Williams & Miller Gin Co. v. Baker Cotton Oil Co.
1925 OK 67 (Supreme Court of Oklahoma, 1925)
Kennedy v. Evans
1924 OK 377 (Supreme Court of Oklahoma, 1924)
Dill v. Johnston
1923 OK 952 (Supreme Court of Oklahoma, 1923)
Aetna Bldg. & Loan Ass'n v. McCarty
1920 OK 175 (Supreme Court of Oklahoma, 1920)
Moline Plow Co. v. Adair
1919 OK 184 (Supreme Court of Oklahoma, 1919)
Kerr v. McKinney
1918 OK 27 (Supreme Court of Oklahoma, 1918)
Emerson-Brantingham Implement Co. v. Ritter
1918 OK 43 (Supreme Court of Oklahoma, 1918)
Holland Banking Co. v. Dicks
1917 OK 573 (Supreme Court of Oklahoma, 1917)
First Nat. Bank of Stigler v. Howard
1916 OK 716 (Supreme Court of Oklahoma, 1916)
Futoransky v. Pope
1916 OK 542 (Supreme Court of Oklahoma, 1916)
Murray Co. v. Palmer
1916 OK 17 (Supreme Court of Oklahoma, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
1915 OK 489, 150 P. 209, 48 Okla. 332, 1915 Okla. LEXIS 631, Counsel Stack Legal Research, https://law.counselstack.com/opinion/continental-gin-co-v-sullivan-okla-1915.