Continental Electrical Contractors, Inc. v. Cardinal Lighting Co.

8 Va. Cir. 126, 1985 Va. Cir. LEXIS 55
CourtFairfax County Circuit Court
DecidedJuly 18, 1985
DocketCase No. (Law) 66463
StatusPublished

This text of 8 Va. Cir. 126 (Continental Electrical Contractors, Inc. v. Cardinal Lighting Co.) is published on Counsel Stack Legal Research, covering Fairfax County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Continental Electrical Contractors, Inc. v. Cardinal Lighting Co., 8 Va. Cir. 126, 1985 Va. Cir. LEXIS 55 (Va. Super. Ct. 1985).

Opinion

By JUDGE THOMAS A. FORTKORT

The case at bar involves a dispute between an electrical contractor, Continental Electrical Contractors, Inc.', and an electrical fixture supplier, Cardinal Lighting Company, Inc.

Continental^ for at least seven years, has purchased fixtures for various jobs from Cardinal Lighting. The relationship between the parties, while financially beneficial, has not been harmonious. While other disputes have occurred, the central theme seems to have been Continental’s habit of paying late although still claiming the discount for timely payment. The amounts in Question were small compared to the volume of business between the parties but Continental’s failure to adhere to Cardinal’s payment schedules had become á major irritant to Cardinal.

This case revolves around two bids for electrical contracts secured by Continental; a job for the American Society of Personnel Administrators and a job for Days Inn Motel. On each job, Continental had received bids from Cardinal which Continental incorporated into a successful low bid for the contract. Cardinal refused to ship fixtures to Continental on a credit basis and Continental [127]*127later went to other suppliers to secure the fixtures for the two jobs.

Cardinal claims that Continental was not credit worthy and its refusal to ship fixtures was done to protect Cardinal from loss which Cardinal claims it was entitled to do under Section 8.2-609 of the Uniform Commercial Code.

Continental asserts that Cardinal's withdrawal of credit forced Continental to purchase fixtures from other suppliers at a cost of $24,947.71 over Cardinal's bid price and that it is entitled to collect for these additional costs under Section 8.2-712 of the Uniform Commercial Code.

An electrical sub-contractor begins a contract bid by submitting the job plans and specifications to various fixture suppliers. The supplier submits a bid to the electrical contractor close to the bid day, sometimes within hours of the bid deadline. The electrical contractor then uses the supply bid to formulate its overall bid. If the electrical contractor's bid is accepted, he notifies the supplier. The supplier guarantees its bid to the electrical contractor which the supplier made on bid day.

It is the custom and usage of the trade that supply bids are firm. The electrical contractor may ask the supplier to discount his bid by 5 to 10 percent, but the supplier cannot adjust his bid upward, once made on bid day. The supplier may offer substitution items of like quality which, presumably, the supplier can obtain at a lower price than the specified item. Nevertheless, if the owner or general contractor refuses to accept these substitutions, the supplier will perform at the agreed price. The custom is so strong that Cardinal officials could not recall a case where it had failed to honor its bid day price.

The supplier protects his price with the manufacturer by ordering the fixtures but requiring that the fixtures not be shipped until authorized by the supplier. The manufacturer agrees to hold his price for varying lengths of time which information is passed onto the electrical contractor as part of the supplier's bid. The supplier is required to pledge his line of credit for the items ordered but not shipped. While he may suffer no economic loss, his available credit with the manufacturer is reduced by each job order.

[128]*128In this case, bid day for the ASPA job was February 3, 1983, and the bid day for the Days Inn job was May 3, 1983.

A quotation form normally follows a successful bid and is a memorialization of the oral bid made by the supplier on the bid date. Quotation forms were submitted by Cardinal on April 20, 1983, for the ASPA job (Plaintiff’s Exhibit # 2) and on June 9, 1983, for the Days Inn Motel job (Plaintiff’s Exhibit # 3).

On May 9, 1983, Cardinal advised Continental that it would not ship any more fixtures on another job called the Fairlanes job unless Continental brought its account current. Thereafter, Cardinal wrote to Continental on May 31, 1983, specifying certain credit terms for the continuance of business between the firms.

Cardinal maintains that Continental’s failure to adhere to this agreement caused Cardinal to suspend Continental’s credit. The suspension of credit placed Continental in the position of having to pay cash for the fixtures or purchase them elsewhere. The custom and usage of the trade is to deal on a credit basis. Out of thousands of transactions, Cardinal officers could only recall one cash transaction.

Continental maintains that the May 31, 1983, agreement only applied to future jobs as evidenced by Mr. McAteer’s crossing out of the paragraph referring to past indebtedness. Continental further maintains that the sums claimed by Cardinal were inaccurate even after Cardinal removed several thousand dollars worth of charges in a subsequent June billing.

On or about June 9, 1983, Mr. McDonald advised Continental that Cardinal would not ship the fixtures for the two jobs. Continental had forwarded a rejection list from the ASPA job but did nothing on the Days Inn job.

There is evidence that Cardinal underbid the Days Inn job. Continental was told by McDonald that the bid was no good and would have to be revised upward. Continental claimed it was not notified in time to withdraw the Continental bid on the Days Inn job. The evidence in the case favors Continental’s position, that it was notified by Cardinal of Cardinal’s underbid after Continental had submitted its bid to the general contractor.

The Court, after reviewing all of the above evidence, makes the following findings of fact.

[129]*1291. A contract existed between the parties wherein Cardinal agreed to supply Continental at the bid day quoted prices, the fixtures for the ASPA and Days Inn jobs.

2. Cardinal never delivered the fixtures.

3. Continental never made a demand on Cardinal to deliver the fixtures after being notified of Cardinal’s suspension of Continental’s credit.

4. Cardinal suspended Continental’s credit on or about June 9, 1983.

5. Continental paid $24,9947 additional for the fixtures for these jobs less $8433 challenged by Cardinal nr $16,494.

6. The Court finds such purchases were made in good faith and without unreasonable delay.

7. The Court construes the agreement of May 31, 1983, to apply to future contracts between the parties and therefore finds that Continental did not breach that agreement with Cardinal. It is clear that McAteer did not intend to be bound by that amount alleged to be owed on May 31, 1983, and that he considered that amount in dispute. Additionally, on June 9, 1983, Cardinal adjusted that account and a later law suit gave Cardinal a substantially lesser amount than it asked. The lesser amount is not conclusive that Cardinal’s claim was erroneous but is evidence that Continental’s complaints about the amount due were well founded.

8. Continental had not paid its bills in the past in accordance with the credit policies of Cardinal.

9. Cardinal had underbid the Days Inn Motel contract with Continental.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cocoa Products Co. of America, Inc. v. Duche
158 S.E. 719 (Supreme Court of Virginia, 1931)
Corn Products Refining Co. v. Fasola
109 A. 505 (Supreme Court of New Jersey, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
8 Va. Cir. 126, 1985 Va. Cir. LEXIS 55, Counsel Stack Legal Research, https://law.counselstack.com/opinion/continental-electrical-contractors-inc-v-cardinal-lighting-co-vaccfairfax-1985.