Continental Contracting Co. v. United States

94 Ct. Cl. 244, 1941 U.S. Ct. Cl. LEXIS 73, 1941 WL 4580
CourtUnited States Court of Claims
DecidedMay 5, 1941
DocketNo. 43163
StatusPublished

This text of 94 Ct. Cl. 244 (Continental Contracting Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Continental Contracting Co. v. United States, 94 Ct. Cl. 244, 1941 U.S. Ct. Cl. LEXIS 73, 1941 WL 4580 (cc 1941).

Opinion

Whaley, Chief Justice,

delivered the opinion of the court:

Plaintiff and defendant entered into a contract on October 17, 1938, under which plaintiff was to construct an extension to the then existing steam heating plant and install a new steam distribution system at the Naval Ammunition Depot, Fort Mifflin, Pa.

Plaintiff commenced the work but did not complete the project. With the extended time for completion, the work should have been completed on June 2, 1934, but the plaintiff continued its activities until July 21, 1934, when it withdrew its force and ceased working. After the plaintiff had left the site of the project, the contracting officer on August 1, 1934, acting under Article 9 of the contract, terminated plaintiff’s right to proceed with the work. This article provided as follows:

Art. 9. Delays — Damages.—If the contractor refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in article 1, or any extension thereof, or fails to complete said work within such time, [283]*283the Government, may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and the contractor and his sureties shall be liable to the Government for any excess cost occasioned the Government thereby. If the contractor’s right to proceed is so terminated, the Government may take possession of and utilize in completing the work such materials, appliances, and plant as may be on the site of the work and necessary therefor. If the Government does not terminate the right of the contractor to proceed, the contractor shall continue the work, in which event the actual damages for the delay will be impossible to determine and in lieu thereof the contractor shall pay to the Government as fixed, agreed, and liquidated damages for each calendar day of delay until the work is completed or accepted the amount as set forth in the specifications or accompanying papers and the contractor and his sureties shall be liable for the amount thereof: Provided, That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather or delays of subcontractors due to such causes: Provided further, That the contractor shall within 10 days from the beginning of any such delay notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay and extend the time for completing the work when in his judgment the findings of fact justify such an extension, and his findings of facts thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days, by the contractor to the head of the department concerned, whose decision on such appeal as to the facts of delay and the extension of time for completing the work shall be final and conclusive on the parties hereto.

It is the plaintiff’s contention that the defendant cancelled the contract and it brings suit for damages in the sum of $62,142.05, but the brief in its behalf covers items aggregat[284]*284ing $61,978.33 only, and these items will be considered in the order and amounts as they appear in the brief.

The first claim is for $8,325.00, which plaintiff alleges is a loss due to error in defendant’s plans, delay in defendant’s surveys, and delay in approving plaintiff’s plans and drawings. This being a construction contract, the specifications were necessarily accompanied by contract drawings, which are identified in the specifications. They were designated as for distribution trenches and piping, profiles, details, and boiler house equipment, plans, elevation and details and foundation plan in the central heating plant.

Article 25 of the General Provisions forming part of the specifications required marked duties in the furnishing of its drawings by the plaintiff. It provided as follows:

25. Special drawings.- — -Wherever required by the special specifications or otherwise considered by the Government necessary the contractor shall make special or detail drawings in amplification of the contract drawings or in furtherance of the specifications, before proceeding with the execution of the work. Such drawings shall be submitted to the officer in charge or Chief of the Bureau of Yards and Docks, as may be directed, in the form of blue prints, in duplicate, for consideration, correction, or approval. When approved, one set of these prints will be returned to the contractor so marked. When changes or corrections are necessary one set will be returned to the contractor so noted and he shall proceed as before with the submission of duplicate prints. When any drawing has been approved the contractor shall furnish the officer in charge with additional blue-print copies or with the tracing or an equivalent as regards the facility for printing. If a, tracing is submitted the Government will make such prints as it may require and will return the tracing to the contractor. On the completion of the work the contractor shall, if so directed, furnish the Government with one complete set of Vandyke prints, on cloth, of all approved drawings.. When the work of the contractor is of a nature originating with him, full general and detail drawings shall be furnished to the Government in the form of tracings, or the equivalent as regards facility for printing, which shall, upon approval, become the property of the Government, approved sets or prints being furnished to the contractor. The approval of [285]*285the general and detail drawings of the contractor will in all cases be of a general nature relating to their sufficiency and compliance with the intention of the contract, and shall not relieve the contractor from errors, discrepancies, or omissions therein contained, which shall be made good whenever found.
Specification 1-09 provided:
1.09. Drawmgs required of the contractor. — Before commencing the installation of any of this wort, the contractor shall submit for approval, and in accordance with the General Provisions, such drawings as may be required, including those showing boilers and boiler-room equipment; piping, structural and reinforcing steel details; ceiling and pipe supports; and special valves and traps.

It will be seen from the above provisions that plaintiff was to prepare and submit a substantial number of drawings. The findings disclose much passing back and forth of drawings with many corrections made by the defendant on plaintiff’s drawings. In fact, the Public Works Office found it in the interest of expediency to cast aside many of plaintiffs drawings and substitute many of its own. If delay occurred in this respect, it does not appear that defendant was responsible for it. The findings indicate no delay whatever by defendant’s officers in the disposition and prompt handling of these drawings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fireman's Fund Indemnity Co. v. United States
93 Ct. Cl. 138 (Court of Claims, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
94 Ct. Cl. 244, 1941 U.S. Ct. Cl. LEXIS 73, 1941 WL 4580, Counsel Stack Legal Research, https://law.counselstack.com/opinion/continental-contracting-co-v-united-states-cc-1941.