Continental Casualty Company v. The United States

786 F.2d 1120, 9 Cl. Ct. 1120, 1986 U.S. App. LEXIS 20030
Court of Appeals for the Federal Circuit·Decided March 17, 1986·No. Appeal 85-2650·Published

Opinion

DAVIS, Circuit Judge.

In this action (coming to us from the United States Claims Court) appellant Continental Casualty Company (Continental) challenges the denial by the Small Business Administration (SBA) of Continental’s claim for reimbursement with respect to eight surety bond guarantee agreements that the SBA entered into with Continental. On cross-motions for summary judgment, the Claims Court held that the guarantees had been excluded by Congress — because the underlying transaction exceeded $1,000,000 — from the SBA’s authority to guarantee, and therefore that Continental could not recover. We affirm.

I.

Because this case was decided below on motions for summary judgment, we consider only those facts that are undisputed or indisputable. On November 8, 1979, the City of Los Angeles (City), California, issued a single request for bids for the construction and delivery of ten heavy-duty pumper fire trucks. A few weeks later, on November 23, 1979, the City issued an addendum to the initial bid request advising prospective bidders that it was increasing the quantity of trucks requested from ten to eleven. The award was subsequently made to Seagrave Fire Apparatus, Inc. *1121 (Seagrave). Seagrave’s total bid (which covered only ten trucks), including tax, was $1,105,58o. 1

Appellee contends that the City and Seagrave first executed a single contract on March 14, 1980 for eleven trucks and later modified the transaction so that eleven “separate contracts” existed for each of the trucks. We do not decide whether or not this was so. 2 But it is undoubted that, in their entirety, the contracts provided that the City was to make a $828,000 advance payment on the eleven trucks to Seagrave to cover the full price of seven of the trucks purchased under contracts later bonded by appellant and a portion of the eighth truck purchased under a contract also subsequently bonded by Continental. Interest was to run at 14% per annum and would pay for the unpaid balance of the contract price for the eighth truck and a portion of the contract price for the ninth. The balance of the cost of the contract for the ninth truck as well as the contract price for the tenth and eleventh trucks was due on delivery.

On May 2, 1980, Continental issued eight performance bonds (one for each of the first eight contracts or trucks) 3 and in June 1980 Continental executed eight SBA Surety Bond Guarantee Agreements for each of Continental’s eight performance bonds. Under the Guarantee Agreements, the SBA underwrote up to 90% of Continental’s losses on the eight performance bonds. Continental, as surety, issued the bonds on behalf of Seagrave, as principal, to the City, as obligee.

After Continental issued its bonds, and after the SBA executed its guarantees, FWD Corp., the parent company of Seagrave, filed for bankruptcy. Seagrave thereafter defaulted on all eleven truck contracts with Los Angeles. Seagrave then advised the City that it could construct the eight trucks bonded by Continental only if an additional payment of $828,-000 was made. In response, Los Angeles made a demand on Continental for the additional payment pursuant to the performance bonds. Continental made payment to Los Angeles and then sought reimbursement for 90% of its losses from the SBA pursuant to the guarantees. 4

The SBA refused to pay. The agency denied liability, in part because it “determined that there was one contract in excess of $1,000,000 and, therefore, the SBA had no authority to guarantee any bonds in connection with the contract (Small Business Investment Act, Section 411(e)(2)).” 5 Upon reconsideration, the SBA upheld its earlier denial of Continental’s claims.

On June 25, 1984, Continental filed suit in the Claims Court for the total amount of the guarantees said to be due it. The only issue before the Claims Court was whether the $1,000,000 contractual limit established by 15 U.S.C. § 694b(e)(2), supra n. 5, was exceeded. Granting the Government’s mo *1122 tion for summary judgment, the court declared that the case involved two central issues. First, whether in fact there was one contract or eleven separate contracts. Second, assuming arguendo that separate contracts existed, whether these contracts must be aggregated to determine whether the $1,000,000 ceiling imposed by 15 U.S.C. § 694b(e)(2) was exceeded. Both issues were resolved against appellant and in favor of the United States.

II.

On the view we take of this case, there is no disputed factual issue calling for a trial. 6 The case turns wholly on the primary issue of the proper construction of the federal statute {see supra n. 5) denying SBA power to guarantee where “the total contract amount” exceeds $1,000,000, and secondarily on the question whether that limit was breached on the undisputed and indisputable facts. 7 We therefore assume arguendo Continental’s version of the disputable facts, including that (1) separate contracts were made between the City and Seagrave, (2) Continental separately guaranteed those contracts, and (3) the SBA knew (before it made its guarantees) the form and structure of the arrangement. On the basis of those facts, the problem is what is the proper application of the statutory limit.

The SBA is authorized by 15 U.S.C. § 694b(a) to guarantee a surety against loss due to the “breach of the terms of a ... performance bond by a principal on any contract up to $1,000,000.” 8 The statute likewise provides that no liability will ensue to the SBA if “the total contract amount at the time of execution of the bond or bonds exceeds $1,000,000.” 15 U.S.C. § 694b(e)(2), supra n. 5.

It is irrefutable from these provisions that Congress did not want the SBA to guarantee sureties on agreements or transactions of more than $1,000,000, but it is not absolutely plain on the statute’s face whether that limit is to be measured by (1) the formal separateness of the individual contracts to be guaranteed, or (2) only the particular contracts (out of an integrated transaction) that are bonded, not by the size of the entire transaction itself, or (3) the size of the whole and entire transaction entered into by one contractor (regardless of the formal separation of that transaction into separate contracts or pieces). We think the third is the correct interpretation.

There is, first of all, textual help from the use (in § 604b(e)(2)) of the term “total contract amount

Free access — add to your briefcase to read the full text and ask questions with AI

Continental Casualty Company v. The United States, 786 F.2d 1120, 9 Cl. Ct. 1120, 1986 U.S. App. LEXIS 20030 (Fed. Cir. 1986).

786 F.2d 1120 (Continental Casualty Company v. The United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Federal Crop Ins. Corp. v. Merrill
332 U.S. 380 (Supreme Court, 1947)