Continental Casualty Co. v. City of Pittsburgh

68 F. Supp. 815, 1946 U.S. Dist. LEXIS 2025
Procedural entryThis page is a short order in Continental Casualty Co. v. City of Pittsburgh. Read the opinion of the Court — 68 F. Supp. 805
District Court, W.D. Pennsylvania·Decided November 15, 1946·No. No. 3546·Published

Opinion

McVICAR, District Judge.

This case was tried together with Continental Casualty Co., a Corporation, and Massachusetts Bonding Insurance Company, a Corporation, v. City of Pittsburgh, a Municipal Corporation, D. C., 68 F.Supp. 805. The controlling facts in each case are the same. Opinion was filed today in 68 F.Supp. 805 which by reference is made a part hereof. In this case the contract was completed by the City. In the other case, it was completed by the surety companies.

Let an order for judgment be prepared and submitted in accordance with the Find[816]*816ings of Fact, Conclusions of Law and this Memorandum Opinion.

Findings of Facfi

1. Continental Casualty Company is a corporation organized and existing under and by virtue of the laws of the State of Indiana, having its principal office or place of business in Chicago, Illinois, and is engaged, inter alia, in the business of writing fidelity and surety bonds.

2. The defendant, City of Pittsburgh, is a municipal corporation in the Commonwealth of Pennsylvania.

3. The amount in controversy, exclusive of interest and costs, is in excess of the sum of $3,000.

4. Middle West Construction, Inc., is an Ohio corporation, having its principal office or place of business in. the City of Cleveland, Ohio, and was at all times hereinafter mentioned engaged in general construction work, including construction of roads, highways and sewers.

5. Heretofore, to wit, on May 11, 1939, Middle West Construction, Inc., entered into a written contract with the City of Pittsburgh for the construction of relief sewers in the Negley Run Drainage Basin, Section 2, Project PA 1590 — F, Contract No. 5.

6. The contract referred to in Finding of Fact 5, provides, inter alia, as follows:

“Article 1. Scope of Work.
The Contractor shall furnish all of the materials and perform all of the work shown on the drawings and described in the specifications, entitled ‘Construction of Relief Sewer in the Negley Run Drainage Basin, Section 2, Project Pa 1590 — F, Contract No. 5’, and shall do everything required by this Agreement and the contract document.”
“Article 5. The contract documents shall consist of the following:
(1) Advertisement.
(2) Instructions to bidders.
(3) Proposal (as accepted).
(4) General Conditions.
(5) Supplemental Specifications.
(6) Specifications, including addenda or bulletins.
(7) Drawings.
(8) Bonds executed by the Contractor.
This agreement together with these documents form the contract, and they are as fully a part of the contract as if hereto attached or herein repeated.”

General Conditions.

“Contract Security.
I. The Contractor shall furnish a surety bond (form attached) in an amount at least equal to 100 per cent of the contract price as security for the faithful performance of this contract. The contractor shall also furnish a separate surety bond (form attached) in an amount at least equal to 50 per cent of the contract price as security for the payment of all persons performing labor and furnishing materials in connection with this contract.”
“Payment of Employees.

II. The Contractor and each of his subcontractors shall pay each of his employees engaged in work on the project under this contract in full (unless deductions made mandatory by law) in cash and not less often than once each week.”

“Project Data and Records.

20. Promptly following the preparation of periodical payrolls of the Contractor and of each of his subcontractors, the Contractor shall furnish the City with such number as may be required of certified copies of such payrolls on forms to be supplied by the City. Such certified copies of such payrolls shall be accompanied by such substantial proof that all bills for services rendered and materials supplied have been duly paid as herein required and by such other data as the City may require.”

“Payment.

21. (a) Not later than the 15th day of each calendar month, the City will make partial payment to the Contractor on the basis of a duly certified approved estimate of the work performed during the preceding calendar month by the Contractor, but the City will retain 10 per cent of the amount of each such estimate until final comple[817]*817tion and acceptance of all work covered by this contract.

(b) The Contractor shall pay:

(2) For all materials, tools, and other expendable equipment to the extent of 90 per cent of the cost thereof, not later than the 20th day of the calendar month following that in which such materials, tools, and equipment are delivered at the site of the project, and the balance of the cost thereof not later than the 30th day- following the completion of that part of the work in or on which such materials, tools, and equipment are incorporated or used and

(3) to each of his subcontractors, not later than the Sth day following each payment to the Contractor the respective amounts allowed the Contractor on account of the work performed by his subcontractors, to the extent of each such subcontractor’s interest therein.”

“22. The Contractor and each of his. subcontractors shall comply with the following statute and regulations issued pursuant thereto:

3. Construction of Regulations:

The clause in the payroll affidavit which reads * * * that the attached payroll is a true and accurate report of the full weekly wages due and paid to each person employed by the said contractor * * * is construed to mean:

(a) Wages due are the wages earned during the pay period by each person employed by the Contractor less any deductions required by law.
(b) At the time of signing the affidavit, the wages due each employee have either been paid to him in full or are being held subject to claim by him.
(c) Such unpaid wages will be paid in full on demand of the employee entitled to receive them.”
“City’s Right to Stop Work or Terminate Contract.

24.

Free access — add to your briefcase to read the full text and ask questions with AI

Continental Casualty Co. v. City of Pittsburgh, 68 F. Supp. 815, 1946 U.S. Dist. LEXIS 2025 (W.D. Pa. 1946).

68 F. Supp. 815 (Continental Casualty Co. v. City of Pittsburgh) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Continental Casualty Co. v. City of Pittsburgh
68 F. Supp. 805 (W.D. Pennsylvania, 1946)