Conti Enterprises, Inc. v. Thermogen I, LLC

CourtSuperior Court of Maine
DecidedOctober 27, 2015
DocketCUMbcd-cv-15-49
StatusUnpublished

This text of Conti Enterprises, Inc. v. Thermogen I, LLC (Conti Enterprises, Inc. v. Thermogen I, LLC) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conti Enterprises, Inc. v. Thermogen I, LLC, (Me. Super. Ct. 2015).

Opinion

STATE OF MAINE BUSINESS AND CONSUMER COURT CUMBERLAND, ss. Location: Portland

CONTI ENTERPRISES, INC.,

Plaintiff,

v. Docket No. BCD-CV-15-49 /

THERMOGEN I, LLC CATE STREET CAPITAL, INC. and GNP WEST, INC.,

Defendants

ORDER ON DEFENDANTS' MOTION TO DISMISS AND MOTION TO DISSOLVE ATTACHMENT

Defendants Cate Street Capital, Inc. ("Cate Street"), GNP West, Inc. ("GNP West"), and

Thermogen I, LLC ("Thermogen") have filed a Motion to Dismiss all of Conti's claims against

Cate Street and GNP West and some of the claims against Thermogen. Cate Street and GNP

West have also filed a Motion to Dissolve Attachment addressed to the ex parte order of

attachment and attachment upon trustee process granted by the Superior Court on February 4,

2015, modified on February 22, 2015, as to all three Defendants. 1 Oral argument on both

motions was held October 1, 2015.

Conti's Complaint arises out of a project at the former Great Northern paper mill in

Millinocket. The first count of Conti's five-count Complaint alleges that defendants

Thermogen and Cate Street breached a contract with Conti by failing to pay for work Conti

performed and for refusing to negotiate a further agreement. The remaining counts are

asserted against all three defendants and allege the defendants: were unjustly enriched at

1The defendants are not moving to dissolve the $3.85 million attachment and trustee process as to Thermo gen. Conti's expense (Count II); breached an implied contract with Conti (Count III); are liable to

Conti under a theory of promissory estoppel (Count IV); and breached their contract with Conti

entitling Conti to reasonable attorneys' fees, penalties, and expenses pursuant to the Maine

Construction Contracts Act (Count V).

For the reasons discussed below, the court denies Defendants' Motion to Dismiss and

grants the Motion to Dissolve the ex parte attachment as to Cate Street and GNP West.

Background

A. Allegations in Conti's Complaint

For purposes of the motion to dismiss, the pertinent allegations of Conti's Complaint

are to be taken as true, see Analysis section A( 1), infra:

Cate Street wholly owns, manages, and controls Thermogen and GNP West. (Compl.

~~ 6-7.) Conti entered into a contract with Thermogen to improve and redevelop property

located at the former Great Northern Paper Mill in Millinocket so that it could become a wood

pellet production plant (the "Project"). (Id. at~ 12.) Thermogen holds a leasehold interest in

and to the former paper mill (the "Project Site"). (Id. at~ 14.) GNP holds the fee interest in

the Project site and is participating and cooperating with Thermogen in the redevelopment of

the Project. (Id. at~~ 15-16.) In addition, Cate Street is participating and cooperating with

Thermogen by doing business associated with the Project and with Conti. (Id. at~ 17.)

Specifically, Thermogen, by and through Cate Street, agreed with Conti that Conti would be

awarded a contract to perform the engineering, procurement, and construction of the Project

(the "EPC Agreement"). (Id. at~ 18.)

Before the final terms of the EPC Agreement could be reached, certain preliminary

work had to be performed. (Id. at~ 19.) Thermogen, by and through Cate Street, entered into

a preliminary agreement with Conti to perform said work (the "Pre-EPC Agreement"). (Id.)

2 Subsequently, Conti and Thermogen, through Cate Street, made amendments and additions to

the Pre-EPC Agreement resulting in a second Pre-EPC Agreement (collectively, the "Pre-EPC

Agreements"). (Id. at~ 20.)

Cate Street performed and assumed duties assigned to Thermogen under the Pre-EPC

Agreements, (!d. at ~ 21.) One instance involved Cate Street officers and employees carrying

out all business dealings on behalf ofThermogen and making payments-along with another

entity allegedly controlled by Cate Street-for a portion of the work performed, supposedly for

Thermogen, by Conti under the Pre-EPC Agreements. (Id.) Another instance involved the

President and CEO ofCate Street assuring Conti that it would receive full payment for its

work under the Pre-EPC Agreements. (!d.)

The Pre-EPC Agreements required Thermogen-and Cate Street, which had assumed

Thermogen's obligations under the Agreements-to pay for Conti's work performed under the

Pre-EPC Agreements and to negotiate the EPC Agreement. (!d. at~ 22.) Conti performed

fully under the Pre-EPC Agreements. (!d. at~~ 2.'3-24.) Conti's work was induced by

representations from Thermogen and Cate Street that Conti would be paid for its work and

that the EPC Agreement would be executed. (!d. at~ 25.) Thermogen and Cate Street,

however, have not paid Conti for the work performed under the Pre-EPC Agreements and have

not negotiated the EPC Agreement. (!d. at~~ 26-27.) Furthermore, Thermogen and Cate

Street are utilizing the benefit of Conti's work to enter into an EPC Agreement with other

persons or firms to complete and redevelop the Project. (Id. at~~ 28-29.)

B. Facts Outside Conti's Complaint

For purposes of the motion to dissolve attachment, the following further facts are taken

to have been established:

3 The Pre-EPC Agreement dated September 19, 2012, 2 provides that it is "made and

entered into ... by and between THERMOGEN I, LLC ('Company') and CONTI

ENTERPRISES, INC. ('Contractor'). Company and Contractor are sometimes referred to

individually as a 'Party' and collectively as the 'Parties."' (Ex. A, p. 1 to 1/23/15 Conti Aff.)

The Pre-EPC Agreement further provides that "[i]t is the intention of the Parties to conclude

the final negotiations of the EPC Agreement and to execute it, but neither party makes any

commitment to do so until such negotiations are complete." 3 (Id. at p. S.)

On or about September 8, 2015, Cate Street filed a Complaint against Conti in New

Jersey State Court. In the New Jersey Complaint, Cate Street alleges that it, notThermogen,

entered into preliminary negotiations with Conti regarding the Project. (Ex. A. to Pl.'s

Supplemental Mem. in Opp. to Def's Mot. to Dismiss (the "New Jersey Complaint") ~ ~ S-4.)

Cate Street also alleged that Conti hired a subcontractor to provide engineering services and

materials, and that Cate Street paid the contractor $800,000 to cover the balance ofinvoices the

contractor claimed to have earned working on the Project. (!d. at ~ ~ 5-7.)

On or about September SO, 2015, Cate Street amended the New Jersey Complaint to

allege that Thermogen and Conti-not Cate Street and Conti-entered into preliminary

negotiations regarding the Project. (Ex. A. to Def's Resp. to Pl.'s Supplemental Mem. in Opp.

to Def.'s Mot. to Dismiss (the "First Amended New Jersey Complaint") ~ ~ 5-6.) The First

Amended New Jersey Complaint still alleges, however, that Cate Street paid Conti's

subcontractor the $800,000 allegedly owed. (!d. at~~ 14-15.)

~The court presumes that this is the second Pre-EPC Agreement, which revised and added to the initial Pre-EPC Agreement.

~The Pre-EPC Agreement also addresses multiple contingencies if the EPC Agreement is not finalized and executed. (!d. at pp. 2-S.)

4 Analysis

A. Defendants' Motion to Dismiss

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moody v. State Liquor & Lottery Commission
2004 ME 20 (Supreme Judicial Court of Maine, 2004)
Saunders v. Tisher
2006 ME 94 (Supreme Judicial Court of Maine, 2006)
Johnson v. Exclusive Properties Unlimited
1998 ME 244 (Supreme Judicial Court of Maine, 1998)
McCain Foods, Inc. v. St. Pierre
463 A.2d 785 (Supreme Judicial Court of Maine, 1983)
Burns v. Architectural Doors and Windows
2011 ME 61 (Supreme Judicial Court of Maine, 2011)
Doe v. Graham
2009 ME 88 (Supreme Judicial Court of Maine, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Conti Enterprises, Inc. v. Thermogen I, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conti-enterprises-inc-v-thermogen-i-llc-mesuperct-2015.