Contempo Construction Co. v. Mountain States Telephone & Telegraph Co.

736 P.2d 13, 153 Ariz. 279, 1987 Ariz. App. LEXIS 376
CourtCourt of Appeals of Arizona
DecidedFebruary 26, 1987
DocketNo. 2 CA-CV 5948
StatusPublished
Cited by32 cases

This text of 736 P.2d 13 (Contempo Construction Co. v. Mountain States Telephone & Telegraph Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contempo Construction Co. v. Mountain States Telephone & Telegraph Co., 736 P.2d 13, 153 Ariz. 279, 1987 Ariz. App. LEXIS 376 (Ark. Ct. App. 1987).

Opinion

HATHAWAY, Chief Judge.

Appellant, Contempo Construction Company (Contempo), brought a contract and tort action against appellees, Mountain States Telephone and Telegraph Company (Mt. Bell) and Arizona Public Service (APS), seeking damages for appellees’ failure to move certain utility poles and other equipment. The summary judgments that appellees were granted in their favor are the subject of this appeal. We affirm.

The undisputed facts are as follows. On November 8, 1982, following its successful bid, appellant entered into a contract with the City of Phoenix to improve and repair 19th Avenue. Appellant was required to complete all work within 210 days after the city issued a Notice to Proceed.

The contract also provided that:
If any delay is caused by any act or omission on the part of the Contracting Agency [City of Phoenix] or by any other Contractor working for the Contracting Agency, or if due to no fault or neglect of the Contractor, the Contractor will be granted an extension of time for the completion of the work sufficient to allow for the delay. The allowable extension of time due to such delays shall be determined by the Engineer, provided the Contractor has given the Engineer immediate notice in writing of the cause of such delay.

At a December 8, 1982, pre-construction conference attended by Contempo’s Joel Smith, a City of Phoenix representative, Mr. Sing, questioned appellees as to when they might complete their work in the 19th Avenue area:

MR. SING: ... Now we’ll start with the utility companies and see what comments they have, and problems. Mountain Bell.
* * # * *
What’s your situation currently?
MT. BELL: We’ll be done down there by next Friday—completely out with that conduit running there.
A VOICE: What about the overhead? Do you have any overhead that are going to be involved down there?
MT. BELL: I don’t believe there are any aerials down there that’s going to be involved (inaudible).
MT. BELL: We do have some pipes (inaudible).
[281]*281MT. BELL: That condo (phonetic) running we did put down there. There’s some sidewalk and other things.
* * * * * *
MR. SING: All right. Okay. Al.
MR. FIELD: I’m Al Field with APS. * * * * * *
[W]e have some poles in the area down there, where we’re still not out of the way. We are working on the project now. It probably will be 60 days, probably, before we’re out.
MR. SMITH: Sixty?
MR. FIELD: Probably; yeah. We have got quite a bit of work to do and we’re in the process of coordinating our work with Salt River Project, as well as the cable company, especially on the crossing of the freeway. We’ve got some special poles ordered for that crossing and they’re not in yet, so that will probably be done at the tail-end of the project. Do you know which end you are going to start at, north or south?
* * * * * *
MR. SMITH: South side.
MR. SMITH: But we were talking about that today and I think that if you can do it within the 60-day parameter, we should be able to work around that pretty well.
MR. FIELD: We’re going to do our best, but—we’re going to shoot for that. Let’s put it that way—
MR. SMITH: We will have some difficulty, you know,—

After the conference, appellant agreed to a December 20, 1982, Notice to Proceed. The completion date thereby became July 18, 1983. APS finished its required work by March 20, 1983. Mt. Bell finished by March 24,1983. On June 3,1983, appellant was declared in default and another contractor was hired to finish the job.

Appellant filed suit against several defendants, including appellees. The complaint alleged that appellees entered into an agreement that they would move their equipment at the 19th Avenue right-of-way in a reasonable manner in order to not delay appellant’s contract with the City of Phoenix. Appellant claimed that Mt. Bell agreed to be out by December 17, 1982, and that APS agreed to finish its work within 60 days of the conference. The complaint alleged that appellees breached their agreements and acted negligently so as to cause delays and injure appellant. Appellant claims that the court erred in entering summary judgment in appellees’ favor because: (1) the representations appellees made at the pre-construction conference gave rise to an oral contract; (2) a promissory estoppel issue is present and (3) whether the appellees breached their duty not to injure appellant is an unresolved question of fact.

THE CONTRACT CLAIM

It is well settled in Arizona that:

For an enforceable contract to exist, there must be an offer, an acceptance, consideration, and sufficient specification of terms so that obligations involved can be ascertained. Savoca Masonry Co., Inc. v. Homes and Son Construction Company, Inc., 112 Ariz. 392, 542 P.2d 817 (1975). An offer is “... a manifestation of willingness to enter into a bargain, so made as to justify another person in understanding that his assent to that bargain is invited and will conclude it.” Restatement (2d) of Contracts, § 24. The offer creates a power of acceptance permitting the offeree, by accepting the offer to transform the offer as promised into a contractual obligation. Calamari and Perillo, “Contracts” § 15.

* * * * * *
An acceptance is “... a manifestation of assent to the terms thereof made by the offeree in a manner invited or required by the offer.” Restatement (2d) of Contracts, § 50.

K-Line Builders, Inc. v. First Federal Savings and Loan Association, 139 Ariz. 209, 212, 677 P.2d 1317, 1320 (App.1983).

Appellant relies solely upon the preconstruction conference to support its claim that a contract was entered into. However, appellant made no statements that could be construed as either an offer or an [282]*282acceptance. Most of the questioning was done by Mr. Sing, the City of Phoenix representative. Even his statements did not request a promise or performance in return. The conference is better characterized as an information-gathering session, than as negotiations to enter into a contract. Therefore, as a matter of law, there was no contract, and the trial court’s summary judgment on this issue was appropriate.

Appellant’s allegations that because APS and Mt. Bell were obligated by law to move their poles and other facilities, a contract somehow arose when they agreed as to when they would complete their legal duty, is unpersuasive. Any such legal duty would run between appellees and the City of Phoenix (see discussion infra), not appellant. Appellant’s further contention that custom and usage in the industry support an oral contract is equally unpersuasive.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Arizona, 2026
Plea v. Phoenix
Court of Appeals of Arizona, 2021
Ajman Stud v. Cains
D. Arizona, 2019
Gary Lowry v. Emc Mortgage Corporation
710 F. App'x 752 (Ninth Circuit, 2018)
Sholes v. Fernando
268 P.3d 1112 (Court of Appeals of Arizona, 2011)
Qwest Corp. v. City of Chandler
217 P.3d 424 (Court of Appeals of Arizona, 2009)
Killingsworth v. State Farm Mutual Automobile Insurance
254 F. App'x 634 (Ninth Circuit, 2007)
J-Squared Technologies, Inc. v. Motorola, Inc.
364 F. Supp. 2d 449 (D. Delaware, 2005)
Griffith Energy, L.L.C. v. Arizona Department of Revenue
108 P.3d 282 (Court of Appeals of Arizona, 2005)
State Ex Rel. Romley v. Gaines
67 P.3d 734 (Court of Appeals of Arizona, 2003)
Higginbottom v. State
51 P.3d 972 (Court of Appeals of Arizona, 2002)
Lombardo v. Albu
4 P.3d 395 (Court of Appeals of Arizona, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
736 P.2d 13, 153 Ariz. 279, 1987 Ariz. App. LEXIS 376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contempo-construction-co-v-mountain-states-telephone-telegraph-co-arizctapp-1987.