Consumers Power Co. v. Public Service Commission

278 N.W.2d 702, 88 Mich. App. 633, 1979 Mich. App. LEXIS 2010
CourtMichigan Court of Appeals
DecidedFebruary 20, 1979
DocketDocket 78-603, 78-604
StatusPublished
Cited by3 cases

This text of 278 N.W.2d 702 (Consumers Power Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consumers Power Co. v. Public Service Commission, 278 N.W.2d 702, 88 Mich. App. 633, 1979 Mich. App. LEXIS 2010 (Mich. Ct. App. 1979).

Opinion

M. B. Breighner, J.

July 15, 1968, Consumers Power Company filed with the Michigan Public Service Commission a petition to increase the company’s electric rates. After public hearing the commission concluded that Consumers Power was experiencing a revenue deficiency and was entitled to a rate increase of $16,514,000. The commission directed Consumers Power to file rates and schedules designed to achieve that increase.

On October 3, 1969, Consumers Power filed comprehensive rate schedules and also in writing prayed "[t]hat the Commission issue an order authorizing the electric rate schedules * * * to become effective for service supplied on and after October 3, 1969”. Under prior practice, apparently, the utility had been allowed to charge increased rates as soon as the commission determined that the utility was experiencing a revenue deficiency.

The same day, instead of approving the company’s request to put the proposed rates into immediate effect, the commission ordered a second phase of public hearings on the rate schedules, to begin October 6, 1969. The break with apparent past practice was explained in the commission’s order. The order related that two days before Consumers Power filed its schedules, the Attorney General had requested public hearings on the proposed rates. In a later pleading the commission also *637 stated that it was without statutory authority to grant the company’s request.

On October 6, 1969, Consumers Power commenced this action in circuit court for temporary injunctive relief to allow it to put the new electric rates into immediate effect. Consumers Power filed the complaint principally to invoke the circuit court’s original equity jurisdiction. Alternatively, the complaint was filed as a statutory appeal pursuant to § 462.26 of the compiled laws. MCL 462.26; MSA 22.45. On October 21, 1969, the circuit court granted the relief requested. In its order the court required the utility to file a bond to secure a refund of the increases should the commission finally provide for the collection of lesser rates. The circuit court reasoned that the commission’s failure to make such an order was unreasonable.

On April 20, 1970, the Public Service Commission entered its final rate order approving rate schedules substantially as proposed by the company and collected pursuant to the injunction. 1 In the interim between the circuit court’s grant of injunction and the commission’s final rate order the company collected $6,623,417 in increased electric rates. The issue raised on this appeal is whether Consumers Power is entitled to keep that money. 2

The Attorney General and other intervening parties have proffered several reasons why the *638 interim rates collected must be refunded. Only two of their theories merit discussion. First is the contention that the circuit court lacked general equity or statutory appellate jurisdiction to issue the temporary injunction that authorized Consumers Power to collect interim rate increases. Second is the claim that the circuit court erred in assuming jurisdiction before Consumers Power had exhausted its administrative remedies.

On review of its earlier order the circuit court has held that it had jurisdiction to enter the preliminary injunction as part of its general equitable jurisdiction and that Consumers Power had exhausted its administrative remedies. We affirm for the reasons stated below.

The Circuit Court had Statutory Appellate Jurisdiction to Enter a Preliminary Injunction Allowing Consumers Power Company to Collect Interim Rate Increases.

It is unnecessary to decide in this case whether the circuit court had original equity jurisdiction to grant the preliminary injunction at issue. 3 By statute the Legislature has granted the circuit court appellate jurisdiction in any action to vacate and set aside any order fixing rates on the ground that the rates are unreasonable or unlawful. MCL *639 462.26; MSA 22.45. The denial of a request to place increased rates into effect pending final approval is an "order fixing rates”. Accord, Mountain States Telephone & Telegraph Co v Arizona Corporation Comm, 331 F Supp 1167 (D Ariz, 1971). As reasoned by the Arizona district court, "A 'No’ answer is just as much rate fixing as an unreasonably low 'Yes’ ”. Id. at 1170.

By its order of October 3, the Public Service Commission denied the utility’s request for immediate relief. As related above, the utility’s complaint for injunction invoked the circuit court’s appellate jurisdiction to review that order. The circuit court granted the injunction on grounds authorized by the statute.

Consumers Power Company had Exhausted its Administrative Remedies before Seeking Relief in the Circuit Court.

Appellants contend that Consumers Power, before seeking a court injunction, should have sought immediate relief from the Public Service Commission under § 460.6a of the compiled laws. MCL 460.6a; MSA 22.13(6a). In pertinent part that section provides:

"When such utility shall have placed in evidence facts relied upon to support its petition or application to so increase its rates and charges, or to so alter, change or amend any rate or rate schedules, the commission, pending the submission of all proofs by any interested parties, may in its discretion and upon written motion by such utility make a finding and enter an order granting partial and immediate relief, after first having given notice to the interested parties within the service area to be affected in the manner ordered by. the commission, and after having afforded to such interested parties reasonable opportunity for a full and *640 complete hearing: Provided, That no such finding or order shall be authorized or approved ex parte, nor until the commission’s technical staff has made an investigation and report: * * *.” 4

On its face the provision shows that a public utility must do two things to invoke the Public Service Commission’s power to grant an immediate change in rate schedules. First, the utility must introduce facts to support its petition. Second, it must make a written request for immediate relief. Before exercising its discretion to grant such relief, the commission must give notice to interested parties and afford them a hearing. Also the commission’s technical staff must investigate and report. But see Attorney General v Public Service Comm, 63 Mich App 69, 77-78; 234 NW2d 407 (1975).

The apparent statutory purposes are threefold. First, § 460.6a affords utilities some form of immediate or partial relief pending a full-blown public hearing and final rate determination. 5 Secondly, it assures that the decision to grant or deny interim relief will be made in the first instance by an expert administrative body, taking advantage of its legislative-like powers of investigation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Complaint of Knox
660 N.W.2d 777 (Michigan Court of Appeals, 2003)
Consumers Power Co. v. Public Service Commission
327 N.W.2d 875 (Michigan Supreme Court, 1982)
Sullivan v. Public Service Commission
287 N.W.2d 188 (Michigan Court of Appeals, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
278 N.W.2d 702, 88 Mich. App. 633, 1979 Mich. App. LEXIS 2010, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consumers-power-co-v-public-service-commission-michctapp-1979.