Consumers Paper Co. v. United States

94 Ct. Cl. 713, 1941 U.S. Ct. Cl. LEXIS 46, 1941 WL 4579
CourtUnited States Court of Claims
DecidedOctober 6, 1941
DocketNo. 44089
StatusPublished
Cited by1 cases

This text of 94 Ct. Cl. 713 (Consumers Paper Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consumers Paper Co. v. United States, 94 Ct. Cl. 713, 1941 U.S. Ct. Cl. LEXIS 46, 1941 WL 4579 (cc 1941).

Opinion

Jones, Judge,

delivered the opinion of the court:

The plaintiff instituted this suit to recover the increased costs incurred in fulfilling two contracts with the Government, alleging that these costs were the direct result of the enactment of the National Industrial Eecovery Act.

The action is brought under the Act of Congress approved June 25, 1938 (52 Stat. 1197), which confers jurisdiction upon the Court of Claims to hear, determine, and enter judgments against the United States upon the claims of contractors on contracts entered into before August 10,1933, and whose costs were increased as a result of the enactment of the National Industrial Eecovery Act. The Act provides that claims shall be allowed upon a fair and equitable basis and notwithstanding the bars or defenses of settlement or adjustment heretofore made.

Plaintiff was engaged in the business of purchasing old rags and discarded garments. These were purchased in large quantities from dealers. The rags were then washed and sterilized and after grading as to size, texture, and quality were sold as wiping cloths for machinery and utensils of various kinds.

On March 27, 1933, plaintiff entered into a contract (No. 30878) with the defendant to furnish to the Navy Department 700,000 pounds of cloths suitable for wiping machinery, delivery to be completed within approximately 75 days.

[717]*717May 9, 1933, plaintiff entered into another contract (No. 31313) to furnish 300,000 pounds of such cloths. These contracts will be referred to as Nos. 1 and 2, respectively.

The National Industrial Recovery Act was approved June 16, 1933. August 22, 1933, plaintiff signed the President’s Reemployment Agreement. February 17, 1934, the President approved the Code for Fair Competition for the Wiping Cloth Industry.

The claim for increased costs was for deliveries made during the period from August 31, 1933, to August 24, 1934.

After the passage of the National Industrial Recovery Act the plaintiff’s representative called on Mr. Van Patten, the Chief of the Bureau of Supplies of the Navy Department, and asked that plaintiff be released from the contracts, or that a higher price be allowed, stating that plaintiff would not be able to complete them on account of the increase in prices.

Mr. Van Patten told such representative that he had no authority either to cancel or to increase the price stipulated in the contracts, but suggested that plaintiff might be given a third contract at a higher price and with a longer period for delivery. Plaintiff and defendant entered into such a contract (No. 33384) hereinafter referred to as Contract No. 3, on October 10, 1933, but there is no claim for any increased costs in connection with the completion of such Contract No. 3.

The auditors of plaintiff and defendant differed in calculating the cost of material and labor shown by the books of the plaintiff as such books were interpreted by these respective auditors.

Finally plaintiff and defendant entered into a stipulation as to the method that should be used in arriving at labor costs, which was to divide the total pounds manufactured during any particular period into the total wages paid out during that period and thus to arrive at the average cost of labor per pound of manufactured production. It was agreed that the plaintiff’s auditor should furnish as a part of the record a supplemental audit showing the average labor costs' per pound, according to this method. [718]*718It was also agreed and stipulated that the plaintiff should submit a supplemental schedule showing the average cost per pound of the manufacturing expenses and thus show the total amount of the claim for increased labor costs and increased manufacturing costs. These were accordingly made up and filed separately for each contract covering the entire period of that part of the deliveries that form the basis of this claim.

It was also agreed and stipulated that defendant’s accountant would prepare a schedule showing the labor costs per pound — using the method agreed upon — for the period commencing with the month of August 1932 and continuing through the month of July 1933.

The schedule of labor costs as filed by defendant’s accountant shows that the average for April, May, and June of 1933 was no higher in plaintiff’s organization than the average for the three months immediately preceding that period. The plaintiff’s auditor filed no separate schedule of labor costs for this period.

The record and testimony do not justify a finding of recoverable increased costs in connection with the performance or carrying out of Contract No. 1.

Had plaintiff delivered the cloths provided in Contract No. 1 within the time contemplated, or within a reasonable time thereafter, there would have been no substantial increased cost, either upon the labor or material used by the plaintiff in fulfilling Contract No. 1.

Tire excuse offered for not complying with the contract within the time specified was the fact of the bank holiday. The so-called bank holiday began in the early part of March — several weeks before plaintiff entered into the contract. It was fully cognizant of the facts in connection with such holiday and had full knowledge of the conditions that prevailed at the time it entered into Contract No. 1 on March 27, 1933. We conclude, therefore, that defendant should not be held liable and made to pay damages in connection with the carrying out of the contract which was entered into with full knowledge of the facts, nor for the situation in which plaintiff found itself, and for which the defendant was not responsible.

[719]*719Plaintiff claims that when its representative had the conversation with Mr. Van Patten the, time of delivery was waived and a longer period allowed within which to deliver the remaining portion of the articles provided for in Contract No. 1. Plaintiff’s request, however, was that it be relieved from the remaining part of the contract by cancellation or that a higher price be allowed. The representative was told that this could not be done. It was suggested that the defendant might by tendering an additional or third contract at a higher price endeavor to help plaintiff with its difficulties. While in a sense by permitting the completion of Contract No. 1 the time of delivery was waived, we do not think that this necessarily carried with it an obligation to pay any and all increased costs which the delivery under the contract at a later period would occasion, especially since the time of delivery was unreasonably delayed, and the proof as to increased costs is not sufficiently definite.

The items of increased costs were for two deliveries under Contract No. 1, one on August 31, 1933, and the other on September 9, 1933.

In the peculiar facts and circumstances of this case these deliveries were delayed far beyond the date when it would be “fair and equitable” to permit recovery of increased costs by virtue of such deliveries.

The items of increased cost in connection with Contract No. 2 were for deliveries beginning September 25, 1933, and ending August 24,1934, as set out in Finding 10.

Defendant contends that these items should also be eliminated because of the fact that they were for shipments which were not made within 75 days from the time Contract No. 2 was entered into.

We think this contention is untenable for several reasons.

At the time Contract No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adam v. States
60 F. Supp. 200 (Court of Claims, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
94 Ct. Cl. 713, 1941 U.S. Ct. Cl. LEXIS 46, 1941 WL 4579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consumers-paper-co-v-united-states-cc-1941.