Consulting and Financial Services, Inc v. John H. Friedmann, Sr.

CourtCourt of Appeals of Tennessee
DecidedApril 24, 2014
DocketM2013-01416-COA-R3-CV
StatusPublished

This text of Consulting and Financial Services, Inc v. John H. Friedmann, Sr. (Consulting and Financial Services, Inc v. John H. Friedmann, Sr.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consulting and Financial Services, Inc v. John H. Friedmann, Sr., (Tenn. Ct. App. 2014).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE March 19, 2014 Session

CONSULTING AND FINANCIAL SERVICES, INC, ET AL. V. JOHN H. FRIEDMANN, SR.

Appeal from the Chancery Court for Sumner County No. 2008C205 Tom E. Gray, Chancellor

No. M2013-01416-COA-R3-CV - Filed April 24, 2014

This is the second appeal of this case, arising from the installation of tile flooring. In Consulting and Financial Services, Inc. v. Friedmann, No. M2011-00093- COA-R3-CV, 2012 WL 1390621(Tenn. Ct. App. April 19, 2012), we held that the trial court’s measure of damages was correct, but remanded for re-calculation of the amount of damages. The remand was necessary because the original judgment included damage amounts that were based upon tile repairs to certain areas of the home, which repairs were not raised by Appellees/homeowners within the one-year warranty period. We did not, however, mandate the method by which the trial court could determine the adjusted amount. Upon remand, the only evidence presented was from the original contractor, who relied upon his original estimate. To arrive at the portions of the original estimate that were for the excluded areas, the contractor had his tile subcontractor submit separate estimates for those areas. The separate estimates were calculated using the current price-per-square-foot applicable at the time of remand, which was less than the price-per-square-foot that was used in the original estimate. To arrive at the adjusted damages amount, the trial court simply subtracted the separate estimate amounts from the original estimate. Appellant/Contractor appeals, arguing, inter alia, that the lower price-per-square-foot applicable at the time of remand should apply to the entire judgment, or, in the alternative, that the excluded amounts should be calculated using the same price as was used in the original estimate. The “law of the case,” based upon our holding in the first appeal, was that the judgment would be adjusted to exclude all costs associated with the excluded areas. Although we did not mandate that the trial court re-try the issue of damages, we did not preclude that option in our first opinion. However, it was implicit in our holding that, if the trial court chose to use the original estimate (which it did), then the total costs for the excluded areas would be calculated, at the same price used in the original estimate, and subtracted from the original estimate. Because the trial court used new estimates for the excluded areas, which were not calculated at the same rate as in the original estimate, the adjusted judgment did not remove the full amount for repairs to the excluded areas that were contemplated in the original estimate. Accordingly, the law of the case was not followed. Vacated and remanded with instructions.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court is Vacated and Remanded

J. S TEVEN S TAFFORD, J., delivered the opinion of the Court, in which D AVID R. F ARMER, J., and H OLLY M. K IRBY, J., joined.

Bruce N. Oldham, Gallatin, Tennessee, for the appellant, John H. Friedmann, Sr.

Russell E. Edwards and Michael W. Edwards, Hendersonville, Tennessee, for the appellees, Consulting and Financial Services, Inc. and Paul G. Crenshaw.

OPINION

In Consulting and Financial Services, Inc. v. Friedmann, No. M2011-00093-COA- R3-CV, 2012 WL 1390621(Tenn. Ct. App. April 19, 2012) (“Friedmann I”), the Contractor, Appellant John H. Friedmann, Sr., appealed the trial court’s award of $106,103.92 in damages, plus $4,252.00 in discretionary costs, to Appellee/homeowners. In Friedmann I, we were asked to review the trial court’s finding of liability, and particularly whether the trial court failed to apply the standard of performance contained in the contract and whether the trial court erred in its calculation of damages. In Friedmann I, we determined that the trial court applied an implied warranty of workmanship standard, as first enumerated in Dixon v. Mountain City Const. Co., 632 S.W.2d 538 (Tenn.1982), rather than the contractual standard. However, after a de novo review of the evidence, we modified the trial court’s judgment to hold that the Mr. Friedmann had breached the contractual standard, and remanded the case for a determination of the appropriate amount of damages. A full recitation of the factual history of the case is set out in Friedmann I. In the interest of continuity and judicial economy, we restate the relevant facts here:

On May 10, 2004, Consulting and Financial Services, Inc. (“CFS”) contracted with John H. Friedmann, Sr., a licensed general contractor, to construct a home in the Fairvue Plantation subdivision in Gallatin, Tennessee. The “Building Contract” (“the contract”) provided, among other things, as follows:

-2- 1. That the Contractor will construct in a good, workmanlike manner, and without delay, a dwelling or other specified building in accordance with the plan, drawings, and specifications attached to and made part of this Contract on the following described property. . . .

8. The Contractor shall correct any work that fails to conform with the requirements of the contract documents where such failure to conform appears during the progress of the work, and shall remedy any defects due to faulty materials, equipment or workmanship which shall appear within a period of one year from the date of the issuance of a Use and Occupancy Permit. The provision of this article apply [sic] to work done by subcontractors as well as work done by direct employees of the Contractor. Contractor warrants the fitness and habitability of the work, and compliance with all codes.

[The president of CFS,] Paul G. Crenshaw [together with CFS, Appellees] . . . and Sherry Steffey, wife of Mr. Crenshaw and vice president of CFS, took possession of the residence on May 7, 2005. Approximately six months after moving into the home, Ms. Steffey noticed cracked tile in the kitchen. She notified Mr. Friedmann about the damaged tile; Mr. Friedmann came to inspect the tile, but he did not repair it. Subsequently, tile in the master bathroom, hallways, and foyer began to crack.

On August 8, 2008, CFS and Paul G. Crenshaw (collectively referred to as [“Appellees”]) filed suit against Mr. Friedmann. The complaint alleged that Mr. Friedmann “poorly and negligently constructed” the home, which constituted a “breach of warranty, breach of contract, and/or unjust enrichment.” With respect to the allegations of breach of contract and breach of warranty, [Appellees] specifically alleged that Mr. Friedmann “failed to construct this dwelling in a workmanlike manner, and thus, has breached the warranty and/or contract with CFS.” [Appellees] requested damages

-3- equaling the cost of repair, cost of inspections, and attorney’s fees.

A bench trial commenced on July 14, 2010. Mr. Crenshaw and Ms. Steffey testified primarily regarding their plans for construction of the home, their concerns about the cracked tile, their interactions with Mr. Friedmann, and how the condition of the tile worsened over time. Three consultants, hired by [Appellees], testified regarding their inspections and their reports relative to the condition of the tile and the structural significance of the cracks. A real estate agent, an engineer, a licensed contractor, and tile installation specialist testified on behalf of Mr. Friedmann regarding the installation and replacement of the tile.

The trial court entered an Order on October 15, 2010, awarding judgment to [Appellees] in the amount of $132,565.00; the court found that “the construction of the residence at 836 Plantation Way, Gallatin, Sumner County, Tennessee, by John H.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White v. Moody
171 S.W.3d 187 (Court of Appeals of Tennessee, 2004)
Estate of Walton v. Young
950 S.W.2d 956 (Tennessee Supreme Court, 1997)
Walker v. Sidney Gilreath & Associates
40 S.W.3d 66 (Court of Appeals of Tennessee, 2000)
GSB Contractors, Inc. v. Hess
179 S.W.3d 535 (Court of Appeals of Tennessee, 2005)
McCaleb v. Saturn Corp.
910 S.W.2d 412 (Tennessee Supreme Court, 1995)
Bruce v. Bruce
801 S.W.2d 102 (Court of Appeals of Tennessee, 1990)
Edenfield v. Woodlawn Manor, Inc.
462 S.W.2d 237 (Court of Appeals of Tennessee, 1970)
Dixon v. Mountain City Construction Co.
632 S.W.2d 538 (Tennessee Supreme Court, 1982)
Beaty v. McGraw
15 S.W.3d 819 (Court of Appeals of Tennessee, 1998)
Cole v. Clifton
833 S.W.2d 75 (Court of Appeals of Tennessee, 1992)
Simpson v. Frontier Community Credit Union
810 S.W.2d 147 (Tennessee Supreme Court, 1991)
Wilhite v. Brownsville Concrete Co., Inc.
798 S.W.2d 772 (Court of Appeals of Tennessee, 1990)
Whitaker v. Whitaker
957 S.W.2d 834 (Court of Appeals of Tennessee, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Consulting and Financial Services, Inc v. John H. Friedmann, Sr., Counsel Stack Legal Research, https://law.counselstack.com/opinion/consulting-and-financial-services-inc-v-john-h-fri-tennctapp-2014.