Constructural Dynamics v. U.S. Venture, Inc.

CourtSuperior Court of Pennsylvania
DecidedJuly 12, 2023
Docket2008 EDA 2022
StatusUnpublished

This text of Constructural Dynamics v. U.S. Venture, Inc. (Constructural Dynamics v. U.S. Venture, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Constructural Dynamics v. U.S. Venture, Inc., (Pa. Ct. App. 2023).

Opinion

J-A07017-23

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37

CONSTRUCTURAL DYNAMICS, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : U.S. VENTURE, INC. : : Appellant : No. 2008 EDA 2022

Appeal from the Judgment Entered July 14, 2022 In the Court of Common Pleas of Bucks County Civil Division at No(s): 2019-01165

BEFORE: DUBOW, J., McLAUGHLIN, J., and McCAFFERY, J.

MEMORANDUM BY McLAUGHLIN, J.: FILED JULY 12, 2023

U.S. Venture, Inc. (“U.S. Venture”) appeals from the judgment entered

against it and in favor of Constructural Dynamics, Inc. (“Constructural

Dynamics”). U.S. Venture contends the trial court erred in its interpretation of

certain terms in a lease agreement, or alternatively, erred in failing to apply

a prevailing wage deduction from the amount of rent it owed to Constructural

Dynamics. We affirm.

Constructural Dynamics is a corporation with real estate holdings in New

Jersey and Pennsylvania. U.S. Venture is a Wisconsin corporation with a

business model that includes the distribution and marketing of compressed

natural gas (“CNG”), biofuels, and other clean energy alternatives. On July

10, 2014, the parties entered into a 10-year lease (“Lease”), whereby U.S.

Venture, as tenant, would lease approximately one-acre of land from

Constructural Dynamics, as landlord, and construct and operate a CNG J-A07017-23

dispensing facility with separate public and private filling lines. The Lease

stated that rent would be $1,000 per month but the rent would increase

(“Increased Rent”) if U.S. Venture was “awarded a grant from the

Commonwealth of Pennsylvania” (the “Commonwealth”):

RENT: $1,000.00 per month; provided however, the Rent shall increase if Tenant is awarded a grant from the Commonwealth of Pennsylvania in which event monthly rent shall be an amount equal the grant amount, minus (a) the incremental increase in documented labor costs resulting directly from the requirement that Tenant retain “prevailing wage” laborers and (b) 10% of the grant amount, representing a contingency fee owed by Tenant to a third party vendor, which total shall be amortized over a thirty (30) month period. The increased rent obligation shall commence on the first day of the month following completion of the CNG Dispensing Facility. Tenant agrees to promptly apply for the grant, process the application in a diligent and commercially reasonable manner and promptly request payment of the grant dollars and shall Produce evidence reasonable [sic] acceptable to Landlord showing the incremental increase in costs as a result of engaging prevailing wage laborers.

Lease at ¶ 9 (emphasis added).

In May 2014, U.S. Venture applied for a grant (“Grant Application”)

offered by the Commonwealth through its Alternative and Clean Energy

(“ACE”) Program. In its Grant Application, U.S. Venture stated that it would

be building “a high-speed public fueling station with private slow-fill lines for

Silvi [Concrete’s] new fleet of CNG-fueled concrete mixers.” Grant Application

at p. 5. U.S. Venture also stated in the Grant Application that the grant funds

would “go directly toward purchasing and installing the CNG equipment as well

as covering the additional costs associated with opening the facility to the

public, such as security fencing, lighting, and improved access.” Id.

-2- J-A07017-23

On October 24, 2014, U.S. Venture received a letter from the

Commonwealth Financing Authority (“CFA”) informing it that the Grant

Application was conditionally approved, subject to conditions set forth in the

letter (“Grant Approval Letter”). The Grant Approval Letter stated that U.S.

Venture was “responsible for seeking competitive bids for all work conducted

with the [g]rant funds.” Grant Approval Letter, 10/24/14, at p. 2. The Grant

Approval Letter also required U.S. Venture to “comply with the Pennsylvania

Prevailing Wage Act which requires prevailing wage rates in all bid documents,

specifications, and construction contracts pertaining to the [p]roject.” Id. at

p. 6.

U.S. Venture and the CFA subsequently entered into a grant agreement

(“Grant Agreement”) on March 18, 2015, and $547,047.00 of Commonwealth

funds were earmarked by the CFA for reimbursement to U.S. Venture of

eligible costs relating to the construction of the CNG facility. The Grant

Agreement incorporated the conditions set forth in the Grant Approval Letter.

Construction on the CNG facility began in 2015. Design Develop

Construct, LLC (“DDC”) was the general contractor on the project.

Construction was completed in December 2016. At the completion of the

project, U.S. Venture submitted a payment request to the CFA. On July 31,

2017, the CFA issued a letter to U.S. Venture notifying it that the CFA would

not disburse the grant funds. The CFA identified two reasons for its refusal to

issue the funds: 1) The funds were specifically awarded to pay U.S. Venture

for construction costs and for the purchase of equipment; however, the CFA

-3- J-A07017-23

learned that U.S. Venture did not incur these costs as it elected to lease, and

not purchase, the CNG equipment/station; and 2) U.S. Venture did not engage

in a competitive bidding process when they chose DDC as general contractor,

which was in contravention of the Grant Agreement. Specifically, the letter

stated, in relevant part:

After reviewing the paperwork submitted, the CFA is unable to disburse the grant funds based on how U.S. Venture, Inc. structured the construction and financing of the project. ACE funds were specifically awarded to pay construction costs incurred by U.S. Venture, Inc. Unfortunately, U.S. Venture, Inc. did not incur construction costs, instead electing to lease the CNG equipment/station. Therefore, there are no eligible costs for the ACE grant to reimburse. Grant funds cannot be used to pay lease payments for the equipment, fund operations, and make grant sharing payments to the landowner.

The CFA was unaware that U.S. Venture, Inc. had decided to lease the CNG equipment/station instead of owning it. The funding commitment letter provided in the original application stated that U.S. Venture, Inc. would provide the matching funds. The application stated that the grant funds would be used to purchase equipment and pay construction costs, not to make lease payments.

In addition, the material provided by Michael Wormley and Catherine Chapple, U.S. Venture, Inc. does not indicate that a competitive bidding process was utilized for the selection of DDC, LLC for each of the projects as required in the grant agreement.

Letter from CFA, 7/31/17.

After the CFA refused to disburse the grant funds, U.S. Venture filed a

Statement of Claim with the Commonwealth’s Board of Claims alleging breach

of contract and equitable claims against the Commonwealth. The Board of

Claims ruled that U.S. Venture’s breach of contract claims were barred by

-4- J-A07017-23

sovereign immunity. U.S. Venture appealed to the Pennsylvania

Commonwealth Court, which affirmed the Board of Claims’ decision. U.S.

Venture then successfully petitioned the Pennsylvania Supreme Court for

allowance of appeal. The Pennsylvania Supreme Court affirmed the

Commonwealth Court and held that U.S. Venture’s breach of contract claims

were barred by sovereign immunity.

Constructural Dynamics filed the instant lawsuit against U.S. Venture

for breach of contract. Constructural Dynamics alleged that although U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prudential Property & Casualty Insurance v. Sartno
903 A.2d 1170 (Supreme Court of Pennsylvania, 2006)
Davis v. Government Employees Insurance
775 A.2d 871 (Superior Court of Pennsylvania, 2001)
Charles D. Stein Revocable Trust v. General Felt Industries, Inc.
749 A.2d 978 (Superior Court of Pennsylvania, 2000)
Murphy v. Duquesne University of Holy Ghost
777 A.2d 418 (Supreme Court of Pennsylvania, 2001)
Century Indemnity Co. v. OneBeacon Insurance Co.
173 A.3d 784 (Superior Court of Pennsylvania, 2017)
Felix v. Giuseppe Kitchens & Baths, Inc.
848 A.2d 943 (Superior Court of Pennsylvania, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Constructural Dynamics v. U.S. Venture, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/constructural-dynamics-v-us-venture-inc-pasuperct-2023.