Constructors & Associates, Inc. v. First National Bank of Cameron

CourtCourt of Appeals of Texas
DecidedJuly 14, 2011
Docket03-10-00357-CV
StatusPublished

This text of Constructors & Associates, Inc. v. First National Bank of Cameron (Constructors & Associates, Inc. v. First National Bank of Cameron) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Constructors & Associates, Inc. v. First National Bank of Cameron, (Tex. Ct. App. 2011).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-10-00357-CV

Constructors & Associates, Inc., Appellant

v.

First National Bank of Cameron, Appellee

FROM THE DISTRICT COURT OF MILAM COUNTY, 20TH JUDICIAL DISTRICT NO. CV30,426, HONORABLE ED MAGRE, JUDGE PRESIDING

MEMORANDUM OPINION

This dispute involves competing claims on a series of construction subcontracts.

After Tedco Electric, Inc. (“Tedco”) filed bankruptcy, First National Bank of Cameron (the “Bank”),

a lender with a secured interest in Tedco’s accounts receivable, initiated suit against Constructors

& Associates, Inc. (“Constructors”) for payment of the outstanding balances on ten construction

subcontracts between Constructors and Tedco. In response to the parties’ competing motions for

summary judgment, the district court granted summary judgment in favor of the Bank and denied

Constructors’ motion. We reverse the trial court’s grant of summary judgment, affirm its denial of

Constructors’ summary-judgment motion, and remand the case to the trial court for further

proceedings consistent with this opinion. BACKGROUND

Constructors is a general contractor engaged in commercial construction throughout

Texas. Between November 2001 and August 2004, Constructors entered into a series of

subcontracts with Tedco where Tedco agreed to provide electrical work for ten of Constructors’

projects. At least three of these subcontracts contained identical language providing that,

If Subcontractor [Tedco] defaults or fails to carry out the Work in accordance with the Subcontract and fails within twenty-four (24) hours after receipt of written notice from Constructors to commence and continue correction of such default or failure to perform with diligence and promptness, Constructors may, without prejudice to any other remedies otherwise available to Constructors, make good such deficiencies through its own efforts and deduct the cost thereof from payments then or thereafter due Subcontractor.

In order to complete the subcontracts, Tedco further contracted with three sub-subcontractors (the

“suppliers”) to purchase goods, materials, and services for the Constructors projects.

In February 2004, Tedco executed two promissory notes payable to the Bank. One

note was secured by Tedco’s equipment. The other note, in the amount of $2,144,654, was secured

by Tedco’s “accounts and other rights to payment . . . whether or not earned by performance” and

perfected by a financing statement.

On August 24, 2004, Constructors sent notice to Tedco that Tedco was in default “on

numerous Austin and San Antonio Projects” and should, within 24 hours, provide proof of financial

security and a plan to pay all vendors. When Tedco did not respond by August 26, Constructors

notified Tedco that it was “hereby terminated on any and all projects with Constructors.”

2 On August 31, Tedco filed for Chapter 7 bankruptcy. As of the petition date,

Constructors still owed Tedco $883,291.90 on the subcontracts.1 Shortly after Tedco filed for

bankruptcy, the bankruptcy court granted the Bank leave from the automatic stay to collect the assets

named as collateral in the Bank’s promissory notes. After other relevant collateral was collected,

Tedco still owed the Bank $1,650,634.03.2 The Bank sent notice to Constructors that its perfected

security interest in Tedco’s accounts receivable required that Constructors pay the Bank

$883,291.90, the remaining balance on the subcontracts between Constructors and Tedco.

Constructors responded that because Tedco defaulted on the subcontracts, the subcontracts’ curative-

measures provision allowed Constructors to withhold payment to Tedco and use the unpaid contract

balance to complete the projects that Tedco failed to complete. Constructors claimed that it spent

the entire $883,291.90 subcontract balance along with an additional $859,113.52—for a total of

$1,742,405.42—to complete Tedco’s unfinished work. The expenses necessary to complete Tedco’s

projects included $948,374.22 in payments made to the suppliers (materialmen hired by Tedco as

sub-subcontractors on the projects) to fulfill Tedco’s contractual obligations under the sub-

subcontracts. Because Constructors’ cost to complete Tedco’s unfinished work exceeded the

remaining balance on the subcontracts between Constructors and Tedco, Constructors claimed that

it did not owe Tedco any money, and therefore the Bank had no claim.

1 The record does not indicate whether this balance represented work yet to be done or whether it also included money earned but not yet paid. 2 The record does not indicate which portion of this balance originated from the promissory note secured by Tedco’s accounts receivable, as opposed to the other promissory note secured by Tedco’s equipment.

3 After Constructors failed to pay the Bank, the Bank filed suit in district court for

breach of contract, conversion, declaratory judgment, and attorney’s fees. The parties filed cross-

motions for summary judgment and, after a hearing on the motions, the district court granted the

Bank’s motion for summary judgment and denied Constructors’ motion. The trial court further

ordered that Constructors pay the Bank $883,291.90 plus interest.3 Constructors now appeals the

granting of the Bank’s summary-judgment motion and the denial of its own.

STANDARD OF REVIEW

We review the district court’s summary judgment rulings de novo. Valence

Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex. 2005). A movant is entitled to traditional

summary judgment if (1) there are no genuine issues of material fact, and (2) it is entitled to

judgment as a matter of law. Tex. R. Civ. P. 166a(c). A movant is entitled to no-evidence summary

judgment if an adverse party presents no evidence of one or more essential elements of its claim or

defense. Id. R. 166a(i). When reviewing a summary judgment, we take as true all evidence

favorable to the nonmovant, and we indulge every reasonable inference and resolve any doubts in

the nonmovant’s favor. Valence, 164 S.W.3d at 661. When both parties move for summary

judgment on the same issues and the trial court grants one motion and denies the other, we consider

the summary-judgment evidence presented by both sides and determine all questions presented. Id.

3 While this order stated that it was not a final order for the purposes of appeal because the Bank’s request for attorney’s fees remained pending, the Bank later nonsuited its attorney’s-fees claim and the trial court entered a final judgment in favor of the Bank on October 20, 2010.

4 DISCUSSION

Constructors bases its appellate arguments on the assumption that the trial court

granted the Bank’s summary-judgment motion on the ground that the Bank prevailed on its

conversion claim as a matter of law. Though the trial court stated during the hearing, “I’m going to

grant the Plaintiff’s motion for summary judgment, finding that . . . this did constitute a conversion

of funds that were due to the bank,” the Bank’s motion for summary judgment did not clearly

identify the claim on which it requested summary judgment nor does the written order granting

summary judgment specify on what grounds the order was granted.4 The arguments made and relief

requested in the Bank’s motion, however, are inconsistent with either its breach of contract or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

N.A. Flash Foundation Inc. v. Palmetco Inc.
298 F. App'x 355 (Fifth Circuit, 2008)
Begier v. Internal Revenue Service
496 U.S. 53 (Supreme Court, 1990)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
AIG Life Insurance Co. v. Federated Mutual Insurance Co.
200 S.W.3d 280 (Court of Appeals of Texas, 2006)
Stone Fort National Bank v. Elliott Electric Supply Co.
548 S.W.2d 441 (Court of Appeals of Texas, 1977)
Panhandle Bank & Trust Co. v. Graybar Elec. Co., Inc.
492 S.W.2d 76 (Court of Appeals of Texas, 1973)
Larry F. Smith, Inc. v. the Weber Co., Inc.
110 S.W.3d 611 (Court of Appeals of Texas, 2003)
Provident Life & Accident Insurance Co. v. Knott
128 S.W.3d 211 (Texas Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Constructors & Associates, Inc. v. First National Bank of Cameron, Counsel Stack Legal Research, https://law.counselstack.com/opinion/constructors-associates-inc-v-first-national-bank--texapp-2011.