NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
COMMONWEALTH OF MASSACHUSETTS
APPEALS COURT
25-P-71
CONSTRUCTION SOURCE MANAGEMENT, LLC
vs.
BELLE FLEUR HOLDINGS, LLC, & another.1
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
This action arises from the initial stages of land
development and construction of a marijuana cultivation
facility. After arbitration resulted in a significant monetary
award to Construction Source Management, LLC (CSM), for breach
of contract, defendants Belle Fleur Holdings, LLC (Holdings),
and Belle Fleur Realty, LLC (Realty), unsuccessfully sought
summary discharge of the mechanic's lien placed on the disputed
property and to pursue counterclaims against CSM and its manager
as a third-party defendant. A judgment entered confirming the
arbitration award, a judgment on the pleadings entered
1 Belle Fleur Realty, LLC. dismissing the counterclaims and third-party complaint, and an
order entered denying the motion for summary discharge. The
defendants now appeal from that order and from so much of the
judgment on the pleadings that dismissed Realty's counterclaim
for slander of title.2 We affirm.
Background. In the spring of 2021, CSM agreed to build a
marijuana cultivation facility for Holdings.3 A short time
before CSM began work on the facility, Holdings executed a
quitclaim deed granting the underlying property to Realty, for
no consideration, without informing CSM.4 Partway into the
project, Holdings began having difficulty securing funding to
continue paying for construction. CSM submitted seven bills to
Holdings -- the first two were paid in full while the remaining
five went unpaid. Shortly thereafter, CSM ceased work, filed a
notice of contract to establish a mechanic's lien against the
property pursuant to G. L. c. 254, § 2, and initiated a lawsuit
2 The notice of appeal also identifies the judgment confirming the arbitration award, but these are the only issues argued in the brief.
3 The project was to be built on a parcel of land in Blandford. The building itself was to be sited at least one hundred feet above the main road, requiring CSM to install a long roadway at a steep grade. Once its employees began work, it became clear that the original design for the road would be inadequate, necessitating a change in the scope of work.
4 At the time of the conveyance, Realty was managed by two of Holdings' owners.
2 against both defendants for breach of contract. The defendants
filed counterclaims against CSM and its manager alleging, among
other things, that CSM and its manager had committed fraud and
there was never any contract between the parties. After an
evidentiary hearing in the Superior Court, a judge determined
that a binding contract existed between CSM and Holdings and
allowed CSM's motion to compel arbitration.
The arbitrator conducted a hearing and, over the course of
three days, considered 165 exhibits and the testimony of five
witnesses. The owners of Holdings attended the arbitration but
did not testify. The arbitrator found that Holdings breached
its contract with CSM and awarded damages to CSM. A different
judge of the Superior Court entered an order confirming the
arbitration award by the parties' agreement. Subsequently, CSM
moved to dismiss the defendants' counterclaims. The defendants,
in turn, moved to dissolve CSM's mechanic's lien on the property
and opposed the motion to dismiss its counterclaims. A third
judge (motion judge) allowed CSM's motion, dismissing all
counterclaims, and denied the defendants' motion to dissolve the
lien. The defendants appealed and claim error only in the
dismissal of Realty's slander of title counterclaim and the
denial of their motion dissolve the mechanic's lien.
3 Discussion. 1. Slander of title. Slander of title is a
particular type of injurious falsehood involving the
"disparagement of the property in land, chattels, or intangible
things." Tenants' Dev. Corp. v. AMTAX Holdings 227, LLC, 495
Mass. 207, 224 (2025), quoting Restatement (Second) of Torts
§ 624 comment (1977). In order to prevail on a claim for
injurious falsehood a party must show that the other party
publishes a false statement and "(a) . . . intends for
publication of the statement to result in harm to the interests
of the other having a pecuniary value, or either recognizes or
should recognize that it is likely to do so, and (b) . . . knows
that the statement is false or acts in reckless disregard of its
truth or falsity." Id., quoting Dulgarian v. Stone, 420 Mass.
843, 852 (1995). We note that this case presents an uncommon
theory of slander of title in which Realty claims CSM slandered
Realty's title to intangible property -- the ability of Realty
to obtain future financing -- by falsely claiming that it
entered into a written contract with Realty.
"We review the grant of a motion to dismiss de novo,
accepting as true all well-pleaded facts alleged in the
complaint, drawing all reasonable inferences therefrom in the
plaintiff's favor." Lanier v. President & Fellows of Harvard
College, 490 Mass. 37, 43 (2022). "In assuming the facts as
4 alleged, however, '[w]e do not regard as "true" legal
conclusions cast in the form of factual allegations'" (citation
omitted). Edwards v. Commonwealth, 477 Mass. 254, 260 (2017),
S.C., 488 Mass. 555 (2021). "To survive a motion to dismiss,
the facts alleged must plausibly suggest[] (not merely be
consistent with) an entitlement to relief" (quotations omitted).
Id., quoting Iannacchino v. Ford Motor Co., 451 Mass. 623, 636
(2008).
As a threshold matter, the previous evidentiary hearing and
arbitration decision have preclusive effect on many facts
alleged in the defendants' counterclaim.5 Accordingly, we do not
accept the precluded allegations as true for purposes of our
review. We do not accept as true, for example, any allegation
that CSM engaged in fraudulent or deceptive behavior, as these
5 Although Realty was not party to the arbitration, it was in privity with Holdings because its interests were aligned in, for example, attempting to prove that CSM was not owed any money by either party. See DeGiacomo v. Quincy, 476 Mass. 38, 43-44 (2016) ("whether a nonparty is in privity with a party depends on the nature of the nonparty's interest, whether that interest was adequately represented by a party to the prior litigation, and whether binding the nonparty to the judgment is consistent with due process and common-law principles of fairness").
Free access — add to your briefcase to read the full text and ask questions with AI
NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
COMMONWEALTH OF MASSACHUSETTS
APPEALS COURT
25-P-71
CONSTRUCTION SOURCE MANAGEMENT, LLC
vs.
BELLE FLEUR HOLDINGS, LLC, & another.1
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
This action arises from the initial stages of land
development and construction of a marijuana cultivation
facility. After arbitration resulted in a significant monetary
award to Construction Source Management, LLC (CSM), for breach
of contract, defendants Belle Fleur Holdings, LLC (Holdings),
and Belle Fleur Realty, LLC (Realty), unsuccessfully sought
summary discharge of the mechanic's lien placed on the disputed
property and to pursue counterclaims against CSM and its manager
as a third-party defendant. A judgment entered confirming the
arbitration award, a judgment on the pleadings entered
1 Belle Fleur Realty, LLC. dismissing the counterclaims and third-party complaint, and an
order entered denying the motion for summary discharge. The
defendants now appeal from that order and from so much of the
judgment on the pleadings that dismissed Realty's counterclaim
for slander of title.2 We affirm.
Background. In the spring of 2021, CSM agreed to build a
marijuana cultivation facility for Holdings.3 A short time
before CSM began work on the facility, Holdings executed a
quitclaim deed granting the underlying property to Realty, for
no consideration, without informing CSM.4 Partway into the
project, Holdings began having difficulty securing funding to
continue paying for construction. CSM submitted seven bills to
Holdings -- the first two were paid in full while the remaining
five went unpaid. Shortly thereafter, CSM ceased work, filed a
notice of contract to establish a mechanic's lien against the
property pursuant to G. L. c. 254, § 2, and initiated a lawsuit
2 The notice of appeal also identifies the judgment confirming the arbitration award, but these are the only issues argued in the brief.
3 The project was to be built on a parcel of land in Blandford. The building itself was to be sited at least one hundred feet above the main road, requiring CSM to install a long roadway at a steep grade. Once its employees began work, it became clear that the original design for the road would be inadequate, necessitating a change in the scope of work.
4 At the time of the conveyance, Realty was managed by two of Holdings' owners.
2 against both defendants for breach of contract. The defendants
filed counterclaims against CSM and its manager alleging, among
other things, that CSM and its manager had committed fraud and
there was never any contract between the parties. After an
evidentiary hearing in the Superior Court, a judge determined
that a binding contract existed between CSM and Holdings and
allowed CSM's motion to compel arbitration.
The arbitrator conducted a hearing and, over the course of
three days, considered 165 exhibits and the testimony of five
witnesses. The owners of Holdings attended the arbitration but
did not testify. The arbitrator found that Holdings breached
its contract with CSM and awarded damages to CSM. A different
judge of the Superior Court entered an order confirming the
arbitration award by the parties' agreement. Subsequently, CSM
moved to dismiss the defendants' counterclaims. The defendants,
in turn, moved to dissolve CSM's mechanic's lien on the property
and opposed the motion to dismiss its counterclaims. A third
judge (motion judge) allowed CSM's motion, dismissing all
counterclaims, and denied the defendants' motion to dissolve the
lien. The defendants appealed and claim error only in the
dismissal of Realty's slander of title counterclaim and the
denial of their motion dissolve the mechanic's lien.
3 Discussion. 1. Slander of title. Slander of title is a
particular type of injurious falsehood involving the
"disparagement of the property in land, chattels, or intangible
things." Tenants' Dev. Corp. v. AMTAX Holdings 227, LLC, 495
Mass. 207, 224 (2025), quoting Restatement (Second) of Torts
§ 624 comment (1977). In order to prevail on a claim for
injurious falsehood a party must show that the other party
publishes a false statement and "(a) . . . intends for
publication of the statement to result in harm to the interests
of the other having a pecuniary value, or either recognizes or
should recognize that it is likely to do so, and (b) . . . knows
that the statement is false or acts in reckless disregard of its
truth or falsity." Id., quoting Dulgarian v. Stone, 420 Mass.
843, 852 (1995). We note that this case presents an uncommon
theory of slander of title in which Realty claims CSM slandered
Realty's title to intangible property -- the ability of Realty
to obtain future financing -- by falsely claiming that it
entered into a written contract with Realty.
"We review the grant of a motion to dismiss de novo,
accepting as true all well-pleaded facts alleged in the
complaint, drawing all reasonable inferences therefrom in the
plaintiff's favor." Lanier v. President & Fellows of Harvard
College, 490 Mass. 37, 43 (2022). "In assuming the facts as
4 alleged, however, '[w]e do not regard as "true" legal
conclusions cast in the form of factual allegations'" (citation
omitted). Edwards v. Commonwealth, 477 Mass. 254, 260 (2017),
S.C., 488 Mass. 555 (2021). "To survive a motion to dismiss,
the facts alleged must plausibly suggest[] (not merely be
consistent with) an entitlement to relief" (quotations omitted).
Id., quoting Iannacchino v. Ford Motor Co., 451 Mass. 623, 636
(2008).
As a threshold matter, the previous evidentiary hearing and
arbitration decision have preclusive effect on many facts
alleged in the defendants' counterclaim.5 Accordingly, we do not
accept the precluded allegations as true for purposes of our
review. We do not accept as true, for example, any allegation
that CSM engaged in fraudulent or deceptive behavior, as these
5 Although Realty was not party to the arbitration, it was in privity with Holdings because its interests were aligned in, for example, attempting to prove that CSM was not owed any money by either party. See DeGiacomo v. Quincy, 476 Mass. 38, 43-44 (2016) ("whether a nonparty is in privity with a party depends on the nature of the nonparty's interest, whether that interest was adequately represented by a party to the prior litigation, and whether binding the nonparty to the judgment is consistent with due process and common-law principles of fairness"). Where Realty and Holdings litigated as a single unit, were represented by the same counsel, and had overlapping ownership and management, we are satisfied that their interests were sufficiently aligned to fairly preclude relitigation of the facts found by the arbitrator. Furthermore, they do not appeal from the motion judge's determination that Realty was in privity with Holdings for purposes of their other counterclaims.
5 claims were found to be unsubstantiated. We also note that the
arbitrator interpreted the construction contract between CSM and
Holdings and determined that CSM was not paid the nearly $2.3
million it was due.6 Therefore, to the extent that Realty's
claim of slander of title could be based on allegations that CSM
acted fraudulently in procuring a signed written contract for
its services, these facts have already been determined to
Realty's detriment. In examining the remainder of the facts
alleged in Realty's counterclaim, the only remaining factual
allegation that could possibly form the basis for Realty's
slander of title claim is the allegation that CSM's statement of
account "falsely claimed that BF Realty owed $2,294,038.80 to
CSM under the terms of the non-existent contract between CSM and
BF Realty."7
Specifically, in the defendants' counterclaim, they
summarily allege that CSM published its statement of account
with knowledge or reckless disregard of its falsity. We need
not accept this legal conclusion, which merely restates the
6 We note that the arbitrator adjusted the contractual damages downward from this point, but it is undisputed that this was the amount owed under the contract.
7 The publication of the mere assertion that CSM had a contract with Realty was unlikely to harm Realty's finances. Accordingly, it is the claimed false assertion that Realty owed a significant amount of money to CSM that must form the basis of the slander of title.
6 element to be proven, as true. See Schaer v. Brandeis Univ.,
432 Mass. 474, 479 (2000) ("It is only when . . . conclusions
are logically compelled, or at least supported, by the stated
facts, that is, when the suggested inference rises to what
experience indicates is an acceptable level of probability, that
'conclusions' become 'facts' for pleading purposes" [citation
omitted]). Accordingly, we look to the remainder of the
defendants' allegations to support the inference that CSM knew
or should have known that Realty owed it nothing. Our review of
the defendants' own factual allegations, however, does not
support this inference. The defendants' factual allegations
support the contradictory inference that it was reasonable for
CSM to believe its contract with Holdings would be applicable
against Realty as well.
We take as true the allegations that Realty was not a
signatory of the contract between Holdings and CSM. This fact
alone, however, is insufficient to support an inference of CSM's
knowledge of falsity where the motion judge found that CSM was
never informed that Holdings had transferred the property at
issue to Realty and only learned of the transfer when CSM
started the process of perfecting a mechanic's lien.
Furthermore, other allegations in the defendants' counterclaim
show that the defendants indicated to CSM that Realty would be
7 the party responsible for paying for the construction. For
example, we take as true fact thirty-six of the counterclaim,
which states that CSM's manager was shown a term sheet from the
defendants' putative financier stating Realty was to receive the
construction loan to finance the project. Facts twenty-two and
twenty-four of the counterclaim state that Realty was formed
with the express purpose of securing financing for the project
being completed by CSM. Fact thirty-three alleges that CSM
received assurances that "the BF Entities" (referring to both
Holdings and Realty) expected to receive additional funding for
the project; and fact fifty-three avers that, at some point
during the project, CSM learned "the BF Entities' financing
sources had withdrawn." Furthermore, the counterclaim is
entirely devoid of any allegations that the defendants
assiduously observed corporate formalities and maintained a
strict separation of corporate identities such that CSM should
have been on notice that Realty was not liable for obligations
incurred by Holdings.
In sum, when taking all the nonprecluded facts in the
defendants' counterclaim as true, we conclude Realty has failed
to allege facts that reasonably support the inference that CSM
knew or should have known its statement of account was false as
to Realty. Because the defendants have failed to plausibly
8 allege a necessary element of their slander of title claim, we
affirm its dismissal.
2. Motion to dissolve the mechanic's lien. The defendants
also claim the motion judge erred in denying their motion for
summary discharge of the mechanic's lien, which CSM placed on
the fee interest of the property at issue pursuant to G. L.
c. 254, § 2.8 They argue that dissolution of the lien is
appropriate where, as here, CSM's notice of contract stated that
it had a contract with Realty and none existed, thereby failing
to strictly comply with the statute.
"The mechanic's lien statute provides 'that a debt due to a
person who performs labor or supplies material for the
improvement of real estate by agreement or with the express of
implied consent of the owner is secured by a mechanic's lien'"
(citation omitted). Ng Bros. Constr., Inc. v. Cranney, 436
Mass. 638, 642 (2002). Its purpose is to ensure that
contractors get paid for their labor and materials when they
improve the value of another's property. A mechanic's lien is a
creation of statute and can be enforced only by strict
compliance with the statute. Trace Constr., Inc. v. Dana Barros
8 CSM argues that the defendants' motion to dissolve the lien was improper because, pursuant to G. L. c. 254, § 15A, the proper means to challenge the lien was to file a verified complaint. Because we find no error in the judge's denial of the defendants' motion, we need not reach this issue.
9 Sports Complex, LLC, 459 Mass. 346, 351 (2011), citing National
Lumber Co. v. United Cas. & Sur. Ins. Co., 440 Mass. 723, 726,
(2004). The defendants argue that CSM's lien failed to strictly
comply with the statute because it improperly alleged a contract
with Realty in its notice of contract. According to the
defendants, this amounted to a "knowing and willful"
misrepresentation as to what CSM was owed and dissolution of the
lien is the only equitable decision. We are not persuaded. As
noted above, the fact that CSM was owed nearly $2.3 million was
settled conclusively in the arbitration.
The essence of the defendants' argument is actually that
the lien was subject to summary discharge because it identified
land owned by Realty where the contract was with Holdings, the
putative tenant of the property. General Laws c. 254, § 2,
however, explicitly contemplates a situation such as this, in
which a contractor has a contract with a tenant to improve real
property. The contractor may obtain a mechanic's lien on the
property in such a situation when the owner of the land has
consented to the improvement in question. G. L. c. 254, § 2 ("A
person entering into a written contract with the owner . . . or
with the consent of such owner . . . shall have a lien upon such
real property"). Where an owner's consent to the improvement of
real property is at issue, a judge looks for evidence of the
10 owner's "contemplation and active encouragement" of the
improvements. Trace Constr. Inc., 459 Mass. at 356.
Furthermore, the consent need not be in writing. See id. at 352
n.10.
Here, we cannot conclude the motion judge erred in
determining that Realty contemplated and actively encouraged the
construction of the marijuana cultivation facility by CSM. The
owners of Realty were the same parties managing Holdings and
seeking financing to build the facility. By Realty's own
admission, the owners engaged with CSM as the "BF Entities" in
pursuing the construction project. The property in question was
transferred from Holdings to Realty for no consideration after
the contract to improve the property was in place. Finally, one
of Realty's managers sent a letter to the town where the
property is located expressing Realty's consent to the
improvement of the property for purposes of obtaining permits
and approvals. Because there was ample undisputed evidence in
the record showing that Realty consented to the improvement of
11 the property in question, the judge correctly denied the motion
to dissolve the mechanics lien.
Judgments affirmed.
Order denying motion for summary discharge of mechanic's lien affirmed.
By the Court (Meade, Neyman & Walsh, JJ.9),
Clerk
Entered: November 25, 2025.
9 The panelists are listed in order of seniority.