CONSTRUCTION SOURCE MANAGEMENT, LLC v. BELLE FLEUR HOLDINGS, LLC, & Another.

CourtMassachusetts Appeals Court
DecidedNovember 25, 2025
Docket25-P-0071
StatusUnpublished

This text of CONSTRUCTION SOURCE MANAGEMENT, LLC v. BELLE FLEUR HOLDINGS, LLC, & Another. (CONSTRUCTION SOURCE MANAGEMENT, LLC v. BELLE FLEUR HOLDINGS, LLC, & Another.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CONSTRUCTION SOURCE MANAGEMENT, LLC v. BELLE FLEUR HOLDINGS, LLC, & Another., (Mass. Ct. App. 2025).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

25-P-71

CONSTRUCTION SOURCE MANAGEMENT, LLC

vs.

BELLE FLEUR HOLDINGS, LLC, & another.1

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

This action arises from the initial stages of land

development and construction of a marijuana cultivation

facility. After arbitration resulted in a significant monetary

award to Construction Source Management, LLC (CSM), for breach

of contract, defendants Belle Fleur Holdings, LLC (Holdings),

and Belle Fleur Realty, LLC (Realty), unsuccessfully sought

summary discharge of the mechanic's lien placed on the disputed

property and to pursue counterclaims against CSM and its manager

as a third-party defendant. A judgment entered confirming the

arbitration award, a judgment on the pleadings entered

1 Belle Fleur Realty, LLC. dismissing the counterclaims and third-party complaint, and an

order entered denying the motion for summary discharge. The

defendants now appeal from that order and from so much of the

judgment on the pleadings that dismissed Realty's counterclaim

for slander of title.2 We affirm.

Background. In the spring of 2021, CSM agreed to build a

marijuana cultivation facility for Holdings.3 A short time

before CSM began work on the facility, Holdings executed a

quitclaim deed granting the underlying property to Realty, for

no consideration, without informing CSM.4 Partway into the

project, Holdings began having difficulty securing funding to

continue paying for construction. CSM submitted seven bills to

Holdings -- the first two were paid in full while the remaining

five went unpaid. Shortly thereafter, CSM ceased work, filed a

notice of contract to establish a mechanic's lien against the

property pursuant to G. L. c. 254, § 2, and initiated a lawsuit

2 The notice of appeal also identifies the judgment confirming the arbitration award, but these are the only issues argued in the brief.

3 The project was to be built on a parcel of land in Blandford. The building itself was to be sited at least one hundred feet above the main road, requiring CSM to install a long roadway at a steep grade. Once its employees began work, it became clear that the original design for the road would be inadequate, necessitating a change in the scope of work.

4 At the time of the conveyance, Realty was managed by two of Holdings' owners.

2 against both defendants for breach of contract. The defendants

filed counterclaims against CSM and its manager alleging, among

other things, that CSM and its manager had committed fraud and

there was never any contract between the parties. After an

evidentiary hearing in the Superior Court, a judge determined

that a binding contract existed between CSM and Holdings and

allowed CSM's motion to compel arbitration.

The arbitrator conducted a hearing and, over the course of

three days, considered 165 exhibits and the testimony of five

witnesses. The owners of Holdings attended the arbitration but

did not testify. The arbitrator found that Holdings breached

its contract with CSM and awarded damages to CSM. A different

judge of the Superior Court entered an order confirming the

arbitration award by the parties' agreement. Subsequently, CSM

moved to dismiss the defendants' counterclaims. The defendants,

in turn, moved to dissolve CSM's mechanic's lien on the property

and opposed the motion to dismiss its counterclaims. A third

judge (motion judge) allowed CSM's motion, dismissing all

counterclaims, and denied the defendants' motion to dissolve the

lien. The defendants appealed and claim error only in the

dismissal of Realty's slander of title counterclaim and the

denial of their motion dissolve the mechanic's lien.

3 Discussion. 1. Slander of title. Slander of title is a

particular type of injurious falsehood involving the

"disparagement of the property in land, chattels, or intangible

things." Tenants' Dev. Corp. v. AMTAX Holdings 227, LLC, 495

Mass. 207, 224 (2025), quoting Restatement (Second) of Torts

§ 624 comment (1977). In order to prevail on a claim for

injurious falsehood a party must show that the other party

publishes a false statement and "(a) . . . intends for

publication of the statement to result in harm to the interests

of the other having a pecuniary value, or either recognizes or

should recognize that it is likely to do so, and (b) . . . knows

that the statement is false or acts in reckless disregard of its

truth or falsity." Id., quoting Dulgarian v. Stone, 420 Mass.

843, 852 (1995). We note that this case presents an uncommon

theory of slander of title in which Realty claims CSM slandered

Realty's title to intangible property -- the ability of Realty

to obtain future financing -- by falsely claiming that it

entered into a written contract with Realty.

"We review the grant of a motion to dismiss de novo,

accepting as true all well-pleaded facts alleged in the

complaint, drawing all reasonable inferences therefrom in the

plaintiff's favor." Lanier v. President & Fellows of Harvard

College, 490 Mass. 37, 43 (2022). "In assuming the facts as

4 alleged, however, '[w]e do not regard as "true" legal

conclusions cast in the form of factual allegations'" (citation

omitted). Edwards v. Commonwealth, 477 Mass. 254, 260 (2017),

S.C., 488 Mass. 555 (2021). "To survive a motion to dismiss,

the facts alleged must plausibly suggest[] (not merely be

consistent with) an entitlement to relief" (quotations omitted).

Id., quoting Iannacchino v. Ford Motor Co., 451 Mass. 623, 636

(2008).

As a threshold matter, the previous evidentiary hearing and

arbitration decision have preclusive effect on many facts

alleged in the defendants' counterclaim.5 Accordingly, we do not

accept the precluded allegations as true for purposes of our

review. We do not accept as true, for example, any allegation

that CSM engaged in fraudulent or deceptive behavior, as these

5 Although Realty was not party to the arbitration, it was in privity with Holdings because its interests were aligned in, for example, attempting to prove that CSM was not owed any money by either party. See DeGiacomo v. Quincy, 476 Mass. 38, 43-44 (2016) ("whether a nonparty is in privity with a party depends on the nature of the nonparty's interest, whether that interest was adequately represented by a party to the prior litigation, and whether binding the nonparty to the judgment is consistent with due process and common-law principles of fairness").

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trace Construction, Inc. v. Dana Barros Sports Complex, LLC
945 N.E.2d 833 (Massachusetts Supreme Judicial Court, 2011)
DeGiacomo v. City of Quincy
63 N.E.3d 365 (Massachusetts Supreme Judicial Court, 2016)
Edwards v. Commonwealth
76 N.E.3d 248 (Massachusetts Supreme Judicial Court, 2017)
Dulgarian v. Stone
420 Mass. 843 (Massachusetts Supreme Judicial Court, 1995)
Schaer v. Brandeis University
735 N.E.2d 373 (Massachusetts Supreme Judicial Court, 2000)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)
National Lumber Co. v. United Casualty & Surety Insurance
802 N.E.2d 82 (Massachusetts Supreme Judicial Court, 2004)
Iannacchino v. Ford Motor Co.
451 Mass. 623 (Massachusetts Supreme Judicial Court, 2008)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
CONSTRUCTION SOURCE MANAGEMENT, LLC v. BELLE FLEUR HOLDINGS, LLC, & Another., Counsel Stack Legal Research, https://law.counselstack.com/opinion/construction-source-management-llc-v-belle-fleur-holdings-llc-massappct-2025.