Construction Coord. v. Cmiel, Schwaber, No. Cv-90-0439047-S (Aug. 26, 1994)

1994 Conn. Super. Ct. 8641
CourtConnecticut Superior Court
DecidedAugust 26, 1994
DocketNo. CV-90-0439047-S
StatusUnpublished

This text of 1994 Conn. Super. Ct. 8641 (Construction Coord. v. Cmiel, Schwaber, No. Cv-90-0439047-S (Aug. 26, 1994)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Construction Coord. v. Cmiel, Schwaber, No. Cv-90-0439047-S (Aug. 26, 1994), 1994 Conn. Super. Ct. 8641 (Colo. Ct. App. 1994).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION The plaintiff in this case, Construction Coordinators Unlimited, P.C., ("Construction Coordinators") brought suit in this matter in March, 1990. In essence, the complaint alleged CT Page 8642 that Joseph Schipani, president of Construction Coordinators, had been hired by defendants in May, 1987, had been wrongly terminated, thus sustaining damages.

Trial was held in December, 1993 and January, 1994, followed by written submissions from plaintiff and the two appearing defendants, Dr. David P. Schwaber and Robert Crochetiere.

For the reasons stated below, having reviewed notes of the trial testimony, the transcript of the testimony, having reviewed the pleadings, and the submissions of counsel, the court finds that judgment should presently enter in favor of plaintiff against the defendants except for defendants Cmiel and Cohn in the amount of $13,300 plus interest from June to October 8, 1989, to the present. On receipt of further information which the court is ordering to be provided as indicated below, the court will decide whether judgment should also enter against defendants Cmiel and Cohn.

Facts

The court will not attempt to set out in detail all of the evidence offered at the trial. Generally speaking, the court endorses and approves the statement of facts as set out on by plaintiff on pages 1 through 19 in its April 19, 1994, brief. In summary, the facts required to understand this ruling are as follows.

Joseph Schipani was at all relevant times the president of Construction Coordinators, a Connecticut corporation engaged in the business of construction management. In May, 1987, defendant Richard Cmiel was a partner with defendant Dr. David Schwaber in a development company known as Stonefield Associates, also referred to in this opinion as Stonefield Associates I. Stonefield Associates I sought plaintiff's services as construction manager at a planned Burlington, Connecticut development construction project (the Burlington project). Schipani proposed that plaintiff would involve itself in construction management and land planning at the Burlington Project. A letter of agreement dated May 22, 1987, memorializes Schipani's proposal. Plaintiff's Exhibit A.

A team comprised of an architect, attorneys, professional engineers, a soil scientist, a traffic specialist, construction CT Page 8643 managers, and land planners worked together on the project. Along with others on the team, Schipani worked to gain certain approvals from the Town of Burlington in connection with the project. Schipani wasn't asked to give, nor did he give, a guarantee that the approvals would be obtained and that the project would be built.

The May 22, 1987, proposal was superseded by formal written contracts. On January 21, 1988, defendants Cmiel and Schwaber, doing business as Stonefield Associates, executed separate written contracts for both the Hogan's View and Thompson's Farm projects. Significant provisions of the contracts, Plaintiff's Exhibits B and C, are set out in detail in plaintiff's April 19, 1994, brief, and will not be recited here. The provisions set out, among other things, the basis upon which plaintiff was to be compensated, and provisions relating to termination of the agreement. The contracts provided no basis for the payment of legal fees or costs in the event of breach. The contracts were American Institute of Architects standard form agreements.

On or about June 14, 1988, defendants Cmiel and Schwaber, doing business as Stonefield Associates, were joined by two additional partners, defendant Alan Cohn and defendant Robert Crochetiere, who had previously done business as Cohn/Crochetiere Development Limited Partnership. Thereafter, Stonefield Associates was known as Stonefield Associates II; the original partnership of defendants Cmiel and Schwaber was referred to as Stonefield Associates I. (Plaintiff's counsel has informed the court in his brief that defendant Cmiel, who was not present at trial, filed for a stay of this action pursuant to Practice Book § 250A, although that is not reflected in the court's file. Plaintiff's counsel has also represented that defendant Cohn, also not present at trial, has filed for bankruptcy, which the court file confirms. However, the court file does not indicate that a stay of this action was sought by Cohn.)

The partnership agreement reached in June, 1988, is entitled "Stonefield Associates II Partnership Agreement." It was signed by Cmiel and Schwaber for Stonefield Associates, and defendant Cohn, identified as the president of Cohn/Crochetiere Development Limited Partnership. Neither at trial, where he chose not to testify, nor in the pleadings, did defendant Crochetiere argue that he was not subject to the June 14, 1988, CT Page 8644 partnership agreement. It was entered into evidence as Defendant's Exhibit 4. No evidence was presented at trial that Schipani knew of the agreement or its contents.

A number of the required permits were in fact obtained for the Burlington Project, while Schipani was working for the project. At the suggestion of legal counsel, defendants withdrew their application, then pending before the town's Planning and Zoning Commission, in August, 1988, fearing denial due to problems with the design of the proposed septic system. Schipani was not responsible for the septic system design.

A period of negotiations followed between Schipani and defendants. Defendants demanded proposed revisions in the contract that had been reached and, without previously informing Schipani, hired Land Engineering Services, Inc., to replace Schipani. Plaintiff unsuccessfully sought to maintain his role in the project, making various proposals to defendants. Plaintiff was never formally terminated in writing.

Necessary permits were ultimately obtained for a phase of Thompson's Farm and the Burlington Project, but the Burlington Project was not built, largely because in defendant Schwaber's view, it was not economically feasible to proceed. Dr. Schwaber testified that one reason plaintiff was not paid all amounts owed was because the Burlington Project was not built. Schwaber could not identify any provision in any contract that required that the Burlington Project to be built as a condition of plaintiff's compensation.

Following plaintiff's termination, defendants failed to pay an invoice for approximately $6,600 relating to construction management services. On May 5, 1989, plaintiff recorded a mechanic's lien dated May 4, 1989, against the Burlington Project of Stonefield Associates II in the amount of $56,700. Schipani's testimony was that approximately $6,700 related to the unpaid August, 1988 invoice for services rendered; whereas the other $50,000 was a proposed buy out figure for plaintiff's then estimated losses relating to land planning and services rendered. Schipani arrived at the $50,000 number after consulting two people as to its propriety.

On June 8, 1989, following demand by plaintiff that defendants pay the outstanding invoice and clarify Schipani's role, direct settlement negotiations were undertaken between CT Page 8645 Schipani and defendants Cmiel and Schwaber. The result was a document entitled "Agreement," Plaintiff's Exhibit G. The agreement was drafted by Schipani, and signed by Cmiel and Schwaber. The agreement states that "This agreement is betweenStonefield Associates I II and Construction Coordinator Unlimited,Inc. made on June 8, 1989." The agreement states that Stonefield Associates will pay the total sum of $20,000 to Construction Coordinators Unlimited, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCarthy v. Taniska
80 A. 84 (Supreme Court of Connecticut, 1911)
Lewis v. Hartford Dredging Co.
35 A. 1127 (Supreme Court of Connecticut, 1896)
O'Hara v. State
590 A.2d 948 (Supreme Court of Connecticut, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
1994 Conn. Super. Ct. 8641, Counsel Stack Legal Research, https://law.counselstack.com/opinion/construction-coord-v-cmiel-schwaber-no-cv-90-0439047-s-aug-26-1994-connsuperct-1994.