CONSTRUCTION CONSULTING, INC. v. THE DISTRICT BOARD OF TRUSTEES OF BROWARD COLLEGE

CourtDistrict Court of Appeal of Florida
DecidedSeptember 7, 2022
Docket21-3104
StatusPublished

This text of CONSTRUCTION CONSULTING, INC. v. THE DISTRICT BOARD OF TRUSTEES OF BROWARD COLLEGE (CONSTRUCTION CONSULTING, INC. v. THE DISTRICT BOARD OF TRUSTEES OF BROWARD COLLEGE) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CONSTRUCTION CONSULTING, INC. v. THE DISTRICT BOARD OF TRUSTEES OF BROWARD COLLEGE, (Fla. Ct. App. 2022).

Opinion

DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT

CONSTRUCTION CONSULTING, INC., Appellant,

v.

THE DISTRICT BOARD OF TRUSTEES OF BROWARD COLLEGE, Appellee.

No. 4D21-3104

[September 7, 2022]

Appeal from the Circuit Court for the Seventeenth Judicial Circuit, Broward County; Carlos A. Rodriguez, Judge; L.T. Case No. CACE16- 007456.

Kenneth D. Cooper, Fort Lauderdale, for appellant.

Joseph W. Jacquot, Jonathan K. Osborne, and Lawrence G. Horsburgh of Gunster, Jacksonville, for appellee.

GROSS, J.

Construction Consulting, Inc. (“CCI”) appeals from a final judgment entered in favor of the District Board of Trustees of Broward College (the “College”) after the trial court granted the College’s motion for summary judgment. This court has jurisdiction. 1 See Fla. R. App. P. 9.030(b)(1)(A).

1 We reject the College’s argument that, because CCI did not attach copies of certain interlocutory orders to the notice of appeal, CCI failed to comply with Florida Rule of Appellate Procedure 9.110(d) and waived any arguments relating to these prior orders. The interlocutory orders at issue made various legal rulings, including dismissing certain counts. Rule 9.110(d) states, in relevant part, that “a conformed copy of the order or orders designated in the notice of appeal shall be attached to the notice . . . .” Here, CCI attached a conformed copy of the final judgment. This was sufficient to bring up for review all interlocutory orders entered as a necessary step in the proceeding. See Auto Owners Ins. Co. v. Hillsborough Cnty. Aviation Auth., 153 So. 2d 722, 724 (Fla. 1963) (“The appeal from the final judgment brings up for review all interlocutory orders entered as a necessary step in the proceeding.”). This case arises out of a construction contract between CCI and the College. The College offered a final payment to cover outstanding invoices. CCI accepted the payment, thus barring its later claims under both the common law doctrine of accord and satisfaction and a waiver clause in the contract.

The Master Contract

The College and CCI were parties to a construction contract (the “Master Contract”) dated May 23, 2012. The Master Contract refers to CCI as the “Construction Manager” and to the District Board of Trustees of Broward College as the “Owner.”

Article 14 of the Master Contract, entitled “Payment to Construction Manager,” governs pay requests by CCI. Paragraph 14.4 provides that “[p]ay requests shall be accompanied by documentation in support of Subcontract Costs and Reimbursable Expenses, if any, as Architect or Owner’s Representative may require.” Paragraph 14.4 also provides that “[s]trict compliance with the requirements of this paragraph 14.4 shall be a condition precedent to any payment, including Final Payment, under this Agreement.”

Paragraph 14.5, entitled in part “Lien Releases,” states that CCI’s “application for Final Payment shall be accompanied by final lien releases and waivers of claim from [CCI] and all Subcontractors,” which “shall be a condition precedent to Final Payment to [CCI].”

Paragraph 14.8, entitled “Payment at Substantial Completion,” governs payment due “after execution of the Certificate of Substantial Completion”:

14.8 Payment at Substantial Completion. Subject to the limitations of the GMP [Guaranteed Maximum Price], and provided that all conditions precedent have been satisfied, within thirty (30) days after execution of the Certificate of Substantial Completion of the Project, Owner shall pay Construction Manager all sums due Construction Manager, including retainage, less any amounts attributable to liquidated damages, and less two hundred percent (200%) of the reasonable cost for completing all incomplete Work, correcting and bringing into conformance all defective and nonconforming Work, and handling all unsettled claims. As a condition precedent to such payment, however, Construction Manager shall deliver to Owner’s Representative the final complete set of as-built drawings in the form of

2 marked-up blueline drawings, and an electronic format of the as-built documents, all required releases of claim, all certificates of occupancy or similar documents required for the occupation and use of the Project for its intended purposes, all required warranties and all Project Documentation as described in Article 12 herein.

Paragraph 14.9, entitled “Payment at Final Completion,” states that if all conditions precedent have been satisfied, “Final Payment” is due “within thirty (30) days after execution of the Certificate of Final Completion.” Paragraph 14.9 defines “Final Payment” as “all unpaid sums due [CCI] under this Agreement, less any amount properly withheld pursuant to this Agreement,” and further states that CCI’s “acceptance of Final Payment shall constitute an unconditional waiver and release of all claims by [CCI] for additional compensation beyond that provided in the Final Payment”:

14.9 Payment at Final Completion. Subject to the limitations of the GMP, and provided that all conditions precedent have been satisfied, within thirty (30) days after execution of the Certificate of Final Completion of the Project, Owner shall pay Construction Manager all unpaid sums due Construction Manager under this Agreement, less any amount properly withheld pursuant to this Agreement (“Final Payment”). Construction Manager’s acceptance of Final Payment shall constitute an unconditional waiver and release of all claims by Construction Manager for additional compensation beyond that provided in the Final Payment. Final Payment by Owner shall not, however, constitute a waiver by Owner of its rights or claims arising from Construction Manager’s failure to perform in strict accordance with the requirements of the Contract Documents.

(Emphasis added).

Paragraph 14.12, entitled “Conditions Precedent to Payment,” provides that “[i]n addition to all other conditions contained herein, it shall be a condition precedent to any payment otherwise due hereunder that . . . [CCI] have submitted its pay requests and backup documentation in the time, form, and manner required by this Agreement.”

Paragraph 25.8, entitled “Entire Agreement/Amendments in Writing,” states in part that “this Agreement may be amended only by written instrument signed by both Owner and Construction Manager.”

3 Significantly, as it concerns a point raised by CCI, the Master Contract did not prohibit the collection of statutory interest for late payments.

The Dispute

Between 2012 and 2014, the College hired CCI to work on numerous construction projects pursuant to the Master Contract. Among those projects were the following: (1) North Campus Building 49 Site Drainage; (2) ADA Hardware Project; and (3) Central Campus Building 6 Sound Booth Project (the “Sound Booth project”).

On July 29, 2013, the College executed a purchase order for CCI to perform the Sound Booth project. Susanne Valdes was the College’s project manager for this project. Subsequently, the parties corresponded regarding payment applications submitted by CCI on the project.

By letter dated April 25, 2014, Valdes wrote to CCI that “effective immediately we are terminating your agreement for the Building 6 Sound Booth project due to lack of response.” Valdes added that “we have not heard back from you on a plan to complete the work.” Valdes also noted that the College had rejected Payment Application #3 “due to an incomplete submittal.”

The next day, April 26, 2014, CCI’s principal, Thomas Carney, notified Valdes via email that CCI had “stopped all work” and was “preparing a final invoice.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Eder v. Yvette B. Gervey Interiors, Inc.
407 So. 2d 312 (District Court of Appeal of Florida, 1981)
Yelen v. Cindy's Inc.
386 So. 2d 1234 (District Court of Appeal of Florida, 1980)
Blunt v. TRIPP SCOTT, PA
962 So. 2d 987 (District Court of Appeal of Florida, 2007)
Thornber v. City of Ft. Walton Beach
568 So. 2d 914 (Supreme Court of Florida, 1990)
Burke Co. v. Hilton Development Co.
802 F. Supp. 434 (N.D. Florida, 1992)
Barrett v. City of Margate
743 So. 2d 1160 (District Court of Appeal of Florida, 1999)
Unicare Health Facilities, Inc. v. Mort
553 So. 2d 159 (Supreme Court of Florida, 1989)
Republic Funding Corp. v. Juarez
563 So. 2d 145 (District Court of Appeal of Florida, 1990)
Pino v. Lopez
361 So. 2d 192 (District Court of Appeal of Florida, 1978)
Volusia County v. Aberdeen at Ormond Beach
760 So. 2d 126 (Supreme Court of Florida, 2000)
AUTO OWN. INS. CO. v. Hillsborough County Aviation Auth.
153 So. 2d 722 (Supreme Court of Florida, 1963)
Frankel v. City of Miami Beach
340 So. 2d 463 (Supreme Court of Florida, 1976)
Martinez v. South Bayshore Tower, LLLP
979 So. 2d 1023 (District Court of Appeal of Florida, 2008)
Mortell v. Keith
528 So. 2d 1362 (District Court of Appeal of Florida, 1988)
Huffman v. State
813 So. 2d 10 (Supreme Court of Florida, 2000)
McGehee v. Mata
330 So. 2d 248 (District Court of Appeal of Florida, 1976)
Miller-Dunn Company, Inc. v. Green
16 So. 2d 637 (Supreme Court of Florida, 1944)
Cirrus Design Corp. v. Sasso
95 So. 3d 308 (District Court of Appeal of Florida, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
CONSTRUCTION CONSULTING, INC. v. THE DISTRICT BOARD OF TRUSTEES OF BROWARD COLLEGE, Counsel Stack Legal Research, https://law.counselstack.com/opinion/construction-consulting-inc-v-the-district-board-of-trustees-of-broward-fladistctapp-2022.