Construction Associates, Inc. v. Peru Community School Building Corp.

393 N.E.2d 792, 182 Ind. App. 10, 71 Ind. Dec. 239, 1979 Ind. App. LEXIS 1300
CourtIndiana Court of Appeals
DecidedAugust 29, 1979
DocketNo. 3-177A25
StatusPublished
Cited by2 cases

This text of 393 N.E.2d 792 (Construction Associates, Inc. v. Peru Community School Building Corp.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Construction Associates, Inc. v. Peru Community School Building Corp., 393 N.E.2d 792, 182 Ind. App. 10, 71 Ind. Dec. 239, 1979 Ind. App. LEXIS 1300 (Ind. Ct. App. 1979).

Opinion

STATON, Judge.

Construction Associates, Inc., the general contractor for the construction of the Peru Senior High School, filed its complaint against the Peru Community School Corporation and the Peru Community School Building Corporation (hereinafter collectively referred to as “Peru”) to recover: (1) the retainage on the project, including $20,-000 for having substantially completed construction on time; (2) damages incurred by Construction Associates as a result of delays allegedly caused by Peru; (3) additional compensation for unit price work. Peru counterclaimed for damages attributable to Construction Associates’ alleged delay in completing the project.

The trial court awarded Construction Associates retainage in the amount of $48,-740.99, which amount was offset by an award to Peru of liquidated damages in the sum of $5,423.04. The trial court denied the other claims, including the $20,000 claim for substantial completion.

On appeal, Construction Associates challenges the denial of its claims and the award of liquidated damages.

We affirm in part and reverse and remand in part.

I.

Substantial Completion

The bid form provided by Peru requested Construction Associates to submit a bid on the total contract price based upon Construction Associates’ estimate of the time required for substantial completion. In addition, Construction Associates was required to submit a bid as to the additional costs it would incur in order to meet an earlier completion date (subsequently designated in the contract as December 1, 1970). Construction Associates submitted a base bid of $2,602,350 and to the base bid added $20,000 for substantial completion by December 1, 1970. Peru accepted those bids.

The bid documents and the contract made it clear, however, that the early completion date set forth in the contract was not absolute. Rather, it was subject to extensions of time. The bid form provided:

“All guaranteed completion requirements set forth in the foregoing are subject to the provisions of Article 18 of the General Conditions of Contract, in connection with ‘Delays and Extensions of time.’ ”

Article 18 of the General Conditions of Contract read as follows:

“DELAYS AND EXTENSIONS OF TIME
Should the contractor be delayed in the execution of the work at any time as a result of any neglect or act of the Architect or Owner,1 or by any representative or employee of either, or by any contractor under separate contract with the Owner, or by change orders, or caused by unforseeable [sic] circumstances not the fault or negligence of the contractor, or by causes beyond his control, including but not restricted to acts of God, or the Public enemy, Acts of Government, fires, floods, epidemics, quarantine restrictions, unavoidable casualties, labor disputes, strikes, freight embargoes, unusual delays in transportation, unusually severe weather or delays in the work of subcontractors due to such causes, or by delay authorized by the Architect pending arbitration, or by any cause which the Architect shall decide justifies such delay, then the time of completion shall be extended by such reasonable time as the Architect may decide.”

The architect did allow an extension of 43 working days for delays caused by unusually severe weather, thus extending the early completion date to February 1, 1971. Substantial completion was not effected by that date. Hence, the trial court’s denial of [794]*794Construction Associates’ $20,000 claim for early completion.

Construction Associates contends that there were several delays other than those for which the architect granted extensions which fell within the purview of Article 18 and which mandated further extensions of time.

Several of the trial court’s findings support that contention:

“6. The Bid Form provided by the Owners to the Contractor requested the Contractor to submit a lump sum proposal for completion of the work based on Contractor’s estimate of the time required to complete such project. In addition, the Contractor was required to submit a bid as to the additional costs it would incur in order to meet an early completion date as specified by the Owners. For the latter purpose, the Contractor bid the amount of Twenty Thousand Dollars ($20,000.00) as such additional costs for guaranteed early completion. In making such estimates, the Contractor was justified in relying upon and did rely upon the provisions of Addendum # 2 which included a map of soil test boring and the following language:

‘All bidders are also informed that the rock level shown on the revised contour map, and on the original drawings, represents the surface of limestone which is extremely weathered and easily removed. In all cases, it is assumed that this rock will be able to be removed with the use of power equipment, such as, backhoes, doz-ers, and the like. All contractors are to base their bids on this premise.’
******

“17. Based on Article 38, Section 3 of the General Conditions of Contract, the court finds that Ronald H. Fanning and the firm of Fanning & Howey, were, in their capacities as architect, the agent and representative of the Owners, and the court further finds that the Owners were responsible and are bound by the acts and omissions of Ronald H. Fanning and the firm of Fanning & Howey as set forth in the Contract.

******

“20. Under terms of the General Conditions of Contract, Article 51, p. 48, the Owner was to ‘establish the lot line, restrictions, and at least one usable benchmark.’ The benchmark so required to be provided by the Owner was the prime measurement from which and upon which all other elevations on the project were to be drawn or based. Such benchmark is sighted on a stationary object and is given as a precise elevation above sea level.

“21. The original benchmark was specified by the architect in Job Report No. 1 under date of January 17, 1969. (See Pit’s. Ex. 7) While Contractor proceeded to prepare a site layout and grade lines based on that benchmark, one month later, on February 26, 1969, the architect advised that the original benchmark was in error and established a new benchmark as set forth in Job Inspection Report No. 9 (Pit’s. Ex. 8) On March 4, 1969, the architect again determined that the benchmark was in error and directed all contractors to ignore previous benchmarks and to use a newly established benchmark. (See Job Visit 10, Pit’s. Ex. 10)

“22. The drawings and plans provided by the architect disclosed that a 16" water main traversed the project site, but failed to disclose that it was located upon and around hard rock rather than soft weathered limestone as represented by the architect in the Bid Documents. The main was also closer to the surface than shown by the plans and drawings failed to disclose that the main was constructed with leaded joints rather than modern mechanical joints making it extremely susceptible to damage and rupture during any heaving grading operations. (Pit’s. Ex. 11)

“23. Plaintiff’s Exhibit 12 sets forth the actual elevation of the subsurface rock at the various locations in which the test bor-ings were made. The evidence shows that the subsurface rock was three to four feet higher than shown on the contour drawings.

“24.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zimmerman v. 1660 Condominium Ass'n
466 N.E.2d 1158 (Appellate Court of Illinois, 1984)
Morton v. E-Z Rake, Inc.
397 N.E.2d 609 (Indiana Court of Appeals, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
393 N.E.2d 792, 182 Ind. App. 10, 71 Ind. Dec. 239, 1979 Ind. App. LEXIS 1300, Counsel Stack Legal Research, https://law.counselstack.com/opinion/construction-associates-inc-v-peru-community-school-building-corp-indctapp-1979.