Constitution Pipeline Company, LLC v. A Permanent Easement for 1.16 Acres and Temporary Easement for 1.59 Acres in Davenport, Delaware County, New York, Tax Parcel Number 17.-2-4.3

CourtDistrict Court, N.D. New York
DecidedSeptember 17, 2020
Docket3:14-cv-02071
StatusUnknown

This text of Constitution Pipeline Company, LLC v. A Permanent Easement for 1.16 Acres and Temporary Easement for 1.59 Acres in Davenport, Delaware County, New York, Tax Parcel Number 17.-2-4.3 (Constitution Pipeline Company, LLC v. A Permanent Easement for 1.16 Acres and Temporary Easement for 1.59 Acres in Davenport, Delaware County, New York, Tax Parcel Number 17.-2-4.3) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Constitution Pipeline Company, LLC v. A Permanent Easement for 1.16 Acres and Temporary Easement for 1.59 Acres in Davenport, Delaware County, New York, Tax Parcel Number 17.-2-4.3, (N.D.N.Y. 2020).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK

Constitution Pipeline Company, LLC, Plaintiff, v. Cases 1:14-CV-2000, et al. (Case Nos. at Exhibit A) (NAM/DJS) A Permanent Easement for 3.62 Acres and Temporary Easements for 3.08 Acres in Middleburgh, Schoharie County, New York Tax Parcel Number 81.-4-13, et al., Defendants.

Norman A. Mordue, Senior U.S. District Judge: MEMORANDUM-DECISION & ORDER 1. INTRODUCTION Now before the Court is Plaintiffs Omnibus Motion under Federal Rule of Civil Procedure 60(b)(6) to dissolve an injunction previously granted in this case which permitted Plaintiff possession of right of ways on Defendants’ properties for a now-defunct pipeline. (Dkt. No. 26). In addition, Plaintiff proposes to: 1) amend the complaint to clarify the duration and scope of the rights of way; 2) maintain the security bond posted for the injunction until such time as the claims in the complaint are resolved by settlement or trial; and 3) record this Order in the land records of the county of the Defendants’ properties. (/d.). Plaintiff originally identified 65 cases subject to this request, but after settlement and stipulations of dismissal, approximately 39 cases remain. (See Exhibit A). Although Plaintiff's motion is unopposed in most of these cases, several Defendants have filed a cross-motion to dismiss the complaint, which is also addressed herein.

Il. BACKGROUND Plaintiff commenced this action in 2014 by seeking condemnation of the Defendants’ properties pursuant to Rule 71.1 of the Federal Rules of Civil Procedure, in order to secure rights of way for a proposed natural gas pipeline (the “Pipeline Project”). (Dkt. No. 1). On February 21, 2015, the Court granted Plaintiff's motions for partial summary judgment and a A! preliminary injunction, thereby giving Plaintiff a permanent right of way and easement on the Defendants’ properties for the purpose of constructing, operating, and maintaining a pipeline for the transportation of natural gas, as well as temporary easements for use during pipeline construction and maintenance. (Dkt. Nos. 16, 17, 20). Plaintiff also posted bonds as security for the payment of just compensation to Defendants. (/d.). Ultimately, Plaintiffs parent company decided not to proceed with the Pipeline Project, which is now permanently cancelled. »| (See Dkt. No. 24). Therefore, the Court granted Plaintiff's request to re-open all the cases related to the Pipeline Project for the purpose of dissolving the injunctions and compensating the Defendants. (Dkt. No. 25). I. DISCUSSION A. Plaintiff’s Motion Plaintiff argues that the injunctions should be dissolved pursuant to Rule 60(b)(6), the catchall provision that permits the court to relieve a party from a final judgment or order for “any other reason that justifies relief.” (Dkt. No. 26-5, p. 5). Since the Pipeline Project was cancelled, Plaintiff seeks to “relinquish possession of the Rights of Way to the Landowners, and proceed to the determination of compensation due for the time it had such possession.” (/d.). Thus, in each of the remaining cases, Plaintiff proposes to vacate the Order that granted its earlier motion for a preliminary injunction. Plaintiff also seeks to amend the complaint “to

reflect that it does not seek any permanent easements on the Property, and only seeks possession of the Rights of Way temporarily for the period of time from the date of taking ... to the date of dissolution of the injunction.” (/d., p. 5). B. Defendants’ Responses In most of the remaining cases, Plaintiffs motions are unopposed. For example, the 4! Defendants in Case No. 14-cv-2000 state that, because Plaintiff has abandoned the Pipeline Project and preserved the security bonds for the affected properties, they have no objection to the relief sought. (Dkt. No. 27). In others, Defendants have consented to dissolution of the injunctions, retention of bonds, and recording the related orders.' However, several Defendants have filed opposing papers and cross-moved for dismissal of the complaint.” In these cases, Defendants argue that: 1) the Orders granting Plaintiff partial summary judgment and a | preliminary injunction are now void and should be vacated; 2) Plaintiffs motion under Rule 60(b) should be denied because it is not seeking relief from a final judgment or order; 3) Plaintiff should not be permitted to amend the complaint; and 4) the complaint should be dismissed pursuant to Rule 71.1. (See, e.g., Dkt No. 28-3 in Case No. 14-cv-2118). C. Dissolving the Injunctions There is no dispute that the injunctions should be dissolved. Rather, the Court’s task is z| to decide the proper mechanism to do so, with an eye towards a swift and equitable resolution. First, the Court recognizes that by its plain language Rule 60(b) only provides for relief from a final judgment or order, Fed. R. Civ. P. 60(b), while the preliminary injunction in this case is interlocutory in nature. Some courts have nonetheless interpreted Rule 60(b) to extend to

' See Case Nos. 14-cv-2023, 14-cv-2027, 14-cv-2047, 14-cv-2048, 14-cv-2050, 14-cv-2093. ? See Case Nos. 14-cv-2054, 14-cv-2057, 14-cv-2004, 14-cv-2008, 14-cv-2031, 14-cv-2036, 14-cv-2039, 14-cv-2045, 14-cv-2049, 14-cv-2059, 14-cv-2069, 14-cv-2071, 14-cv-2080, 14-cv-2083, 14-cv-2118.

modifications of preliminary injunctions. See, e.g., Halo Optical Products, Inc. v. Liberty Sport, Inc., No. 14-CV-282, 2017 WL 4011261, at *3, 2017 U.S. Dist. LEXIS 146472, at *8 (N.D.N.Y. Sept. 11, 2017). However, Rule 60(b) need not be applied in this case because the preliminary injunction can be dissolved through the Court’s power of equity. As the Second Circuit has observed, “[w]hile changes in fact or in law afford the clearest bases for altering an A! injunction, the power of equity has repeatedly been recognized as extending also to cases where a better appreciation of the facts in light of experience indicates that the decree is not properly adapted to accomplishing its purposes.” King-Seeley Thermos Co. v. Aladdin Industries, Inc., 418 F.2d 31, 35 (2d Cir. 1969); see also 42 AM. JUR. 2D INJUNCTIONS § 284 (“Generally, a court exercises the same power over its injunctive orders which it, as a court of equity, exercises over its other orders or decrees. Thus, a court of equitable jurisdiction has the intrinsic or inherent | power to dissolve, vacate, or modify its injunctions.”). Under equitable principles, a preliminary injunction can be modified or dissolved if “the moving party demonstrates that a material change in circumstances justifies its alteration.” Jnt’] Equity Invs., Inc. v. Opportunity Equity Partners, Ltd., 427 F. Supp. 2d 491, 501 (S.D.N.Y. 2006); see also 42 AM. JUR. 2D INJUNCTIONS § 288 (““Generally, a court may modify or dissolve an injunction, whether permanent or preliminary. . . based upon changed circumstances.”). Here, Plaintiff has shown that the Pipeline Project—the object of the preliminary injunction— has been cancelled. Specifically, on April 13, 2020, Plaintiff notified the New York State Department of Environmental Conservation of its decision to withdraw its pending applications for permits for the Pipeline Project. (See Dkt. No. 26-5, p. 3). Plaintiff states that it no longer needs possession of the rights of way for further survey or construction because the project will not be moving forward. (/d., p. 4).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Constitution Pipeline Company, LLC v. A Permanent Easement for 1.16 Acres and Temporary Easement for 1.59 Acres in Davenport, Delaware County, New York, Tax Parcel Number 17.-2-4.3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/constitution-pipeline-company-llc-v-a-permanent-easement-for-116-acres-nynd-2020.