Constitution Indemnity Co. of Philadelphia v. Morgan

49 S.W.2d 497, 1932 Tex. App. LEXIS 403
CourtCourt of Appeals of Texas
DecidedApril 14, 1932
DocketNo. 2654.
StatusPublished

This text of 49 S.W.2d 497 (Constitution Indemnity Co. of Philadelphia v. Morgan) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Constitution Indemnity Co. of Philadelphia v. Morgan, 49 S.W.2d 497, 1932 Tex. App. LEXIS 403 (Tex. Ct. App. 1932).

Opinion

WABTHAB, J.

Appellee J. E. Morgan, in 1929, had made-a contract with the University of Texas for the erection of a gymnasium, auditorium, and' *498 swimming pool to be erected at Austin, and thereafter, on June 17, 1929, Morgan made a subcontract with J. N. Johnson, operating and doing business as South Texas Steel Erection Company whereby, in the erection of said gymnasium, auditorium, and swimming pool, Johnson was to furnish all material and labor and erect and rivet in place about seven hundred 'tons of structural steel, at the price of $17 per ton, Johnson, in addition thereto, agreeing to furnish all tools and equipment, paint all connections, and do all riveting, as per an exhibit attached to 'and made a part of the appellee’s petition, payments therefor to be 85 per cent, of the materials in place, as the work progressed. Morgan required Johnson to give bond for the faithful performance of his subcontract, which Johnson did with the appellant herein as his surety; Morgan paying the amount of the premium thereon.

. Morgan brought this suit stating the facts substantially as above, and asked judgment against Johnson and appellant, Constitution Indemnity Company of Philadelphia, in the "sum of $3,996.37, with interest, alleging that he (Morgan) did all that was required of him under said contract, but that Johnson and South Texas Steel Erection Company failed and refused to carry out the said subcontract and defaulted in its performance, stating wherein he defaulted, and that he (Morgan) was compelled to and did expend large sums of money in carrying out, executing, and performing the work which Johnson and South Texas Steel Company had contracted to do, all to his cost and damage, as above stated.

Morgan alleged in substance that the sums of money expended .by him for Johnson were agreed upon as correct, reasonable, and necessary; that such agreement was made in the presence of an agent of appellant bonding company and a copy of such agreement was attached to and made a part of his petition; that Morgan gave notice to appellant of the inability of Johnson to perform his said contract, and he was instructed by an authorized agent of appellant bonding company to continue advancing pay rolls but to pay no more money to the South Texas Steel Erection Company; that acting under said instruction he was forced to expend the above-mentioned sum in excess of the original contract price for which he sues.

Johnson filed an answer to Morgan’s suit but thereafter paid no attention to the suit.

Appellant bonding company filed answer setting up various defenses, principally to the effect that, as a matter of fact, Johnson had completed his subcontract; that appellant was released as surety because Morgan had made excess payments to Johnson in violation of the contract either voluntarily on Morgan’s part, or by reason of a subsequent contract between Johnson and Morgan, thereby discharging the surety; that Morgan had discharged the surety by making payments to or for Johnson greatly in excess of what was' allowable under the contract, that is, he (Morgan) failed to retain the 15 per cent, required; that the contract requirement that payments were to be made on certificate of the architect -was wholly disregarded; that Morgan allowed Johnson to use his (Morgan’s) credit, Morgan thereby incurring liabilities greatly in excess of the amount due Johnson; that Morgan had paid out various sums for material, etc., wholly beyond the terms of the contract.

The case started with a trial to a jury, but later the jury was waived and the matter submitted to the court; the court entered judgment against Johnson and appellant, Surety, for the amount sued for. The court filed findings of fact and conclusions of law.

In the first two paragraphs of the findings the court found that Morgan entered into the contract for the erection of the gymnasium, auditorium, and swimming pool, as stated in the petition, and the making of the subcontract with Johnson, as stated; Johnson doing business under the name of South Texas Steel Erection Company. The subsequent findings are substantially as follows:

Third. Johnson proceeded under said contract until about the 18th of November, 1929, when Morgan, being informed by Johnson that he was without funds or credit to complete the contract, submitted the facts to the general agents of appellant bonding company, Trezevant & Cochrane, and on that day Morgan was authorized by appellant, acting through said general agents, to proceed with the execution of the contract, under instructions to refrain from advancing to the South Texas Steel Erecting Company any further money until work under their contract was completed, but otherwise, Morgan to continue to advance the weekly pay rolls, in order that the job might be completed as soon as possible.

Fourth. That at the time of the interview between Morgan and the agents of appellant as above, Morgan had not breached his contract with Johnson or with appellant surety company; that the authorization of the agents of the appellant surety company to proceed with the contract and to advance money for weekly pay rolls waived the provisions of the contract requiring Morgan to retain 15 per cent, of the money earned thereunder, and such authorization was a ratification of what had been done by Morgan and Johnson under the contract, and was a waiver of any requirement of written notice to appellant surety company.

Fifth. Payments made by Morgan to or for Johnson were not made upon certificates of the architects representing the university, *499 but were made in accordance with the contract between Morgan and Johnson.

Sixth. Morgan was compelled to expend the sum of $3,996.37 in doing the work which Johnson and South Texas Steel Erection Company had contracted to do, and such ex-. penditures so made were reasonable and necessary payments for labor and material necessary in the completion of said contract.

Seventh and Eighth. Morgan retained the portion of the contract price specified until authorized as stated to make payments in advance and in excess thereof.

Ninth. The expenses for labor and material so incurred by Morgan for and on behalf of Johnson in excess of the amount due him as per his contract amounted to $3,996.37, and which sum was agreed upon on F'ebru-ary 27, 1930, between Morgan and Johnson in the presence of D. Y. Ellis, agent of appellant surety company.

The court concluded as a matter of law that Morgan was entitled to recover the sum of money as stated, and that appellant, surety, was entitled to recover over against Johnson.

Opinion.

Appellant surety company submits that a reversal of the case should be ordered for the following reasons: .

Because under all the evidence Johnson completed his contract with Morgan in accordance with its terms.

The evidence shows that Johnson completed the contract, but only after he had signified to Morgan his inability to proceed further with the contract, and Morgan, acting with Johnson’s consent and under the request of appellant surety company, had advanced sufficient money and material to Johnson to complete the contract, as found by the trial court. It was with such financial assistance as Morgan then gave him that he completed his centract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carnegie Public Library Ass'n v. Harris
97 S.W. 520 (Court of Appeals of Texas, 1906)
Hess & Skinner Engineering Co. v. Turney
216 S.W. 621 (Texas Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
49 S.W.2d 497, 1932 Tex. App. LEXIS 403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/constitution-indemnity-co-of-philadelphia-v-morgan-texapp-1932.