Constellation Power Source, Inc. v. Select Energy, Inc.

467 F. Supp. 2d 187, 2006 U.S. Dist. LEXIS 83061, 2006 WL 3333748
CourtDistrict Court, D. Connecticut
DecidedNovember 14, 2006
Docket3:04cv983 (MRK)
StatusPublished
Cited by2 cases

This text of 467 F. Supp. 2d 187 (Constellation Power Source, Inc. v. Select Energy, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Constellation Power Source, Inc. v. Select Energy, Inc., 467 F. Supp. 2d 187, 2006 U.S. Dist. LEXIS 83061, 2006 WL 3333748 (D. Conn. 2006).

Opinion

MEMORANDUM OF DECISION

KRAVITZ, District Judge.

This is a diversity action between two energy companies, Constellation Power Source, Inc., now known as Constellation Energy Commodities Group, Inc. (“Constellation”), and Select Energy, Inc. (“Select”). Each company claims the other owes it millions of dollars under a wholesale power contract they entered into in November 1999 to supply power for customers of Connecticut Light & Power (“CL & P”) in Connecticut. While each side raises certain ancillary issues, this is fundamentally a dispute about contract interpretation.

*190 The case was tried to the Court over a three-day period. The parties presented a total of nine witnesses at trial, each of whom presented their direct testimony through a written declaration submitted before trial. Those witnesses affirmed their declarations at the time of trial, and the trial itself was principally devoted to cross-examination and redirect. The testimony of certain other witnesses was presented through deposition transcripts. The parties also submitted detailed stipulations, proposed findings of fact and conclusions of law, and pretrial briefs. Following trial, the parties submitted supplemental briefs, and the Court held a lengthy oral argument. Counsel for each side distinguished themselves throughout this case by their skillful advocacy, professionalism, and civility. The Court is grateful to each of them.

In accordance with Rule 52 of the Federal Rules of Civil Procedure, the Court makes the following findings of fact and conclusions of law.

I.

The summary that follows, which is based upon the parties’ Joint Stipulation of Facts and Agreed Principles of Law [doc. # 103] Ex. A, and the facts adduced at trial, is intended to provide general background information needed to understand the parties’ contractual dispute. Further facts bearing directly on certain contested issues are also discussed in later sections. The Court begins by providing background information about the structure and functioning of the energy market in New England, since the parties entered into the contracts at issue within that market and subject to the rules and practices governing that market. Those rules and practices informed the parties’ agreements and their dispute in this case. Thereafter, the Court will describe the agreements at the center of this dispute, as well as the parties’ implementation of those agreements. Finally, the Court will describe the parties’ claims in this action.

To give the reader some context, it suffices at this point to say that the parties’ dispute centers on two contractual issues: (1) whether Select is entitled to recover from Constellation congestion charges imposed in the period before the New England energy market adopted a pricing methodology known as “Standard Market Design” (described in detail below); and (2) whether, in the period after the adoption of Standard Market Design, Constellation is entitled to recover from Select certain charges for congestion and losses in view of the fact that CL & P reimbursed Select for some of those charges. For the uninitiated reader, the Court apologizes in advance for the proliferation of acronyms and jargon, which regrettably is unavoidable in this case.

NEPOOL and ISO New England.

Constellation’s Expert John J. Reed and Select’s Expert Joseph J. Staszowski described in detail in their expert reports the operation of the New England energy market. See Witness Statement of John Reed, dated Aug. 3, 2006, with attached Report, dated December 24, 2004 (“Reed Report”); Witness Statement of Joseph Staszowski, with attached Report, dated July 29, 2005 (“Staszowski Report”). 1 The Court assumes familiarity with their reports, which will not be repeated in detail here.

The transactions at issue occurred within the wholesale power market of the New *191 England Power Pool (“NEPOOL”). NE-POOL is a voluntary association of member entities, known as “Participants,” engaged in the electric power business in the New England region, including Connecticut. Constellation, Select, and CL & P are all Participants in NEPOOL.

On July 1, 1997, ISO New England, Inc. (“ISO New England”), a non-profit independent system operator, took over the dispatch of generation resources and management of NEPOOL’s high voltage transmission lines, known as the NEPOOL “Pool Transmission Facilities” or “PTF.” The PTF is the backbone that connects the various utility distribution systems throughout the region and allows energy to move throughout New England. In every power transaction on the NEPOOL PTF, there is both a physical dispatch (the generation and consumption of energy) and a financial settlement (who pays whom and how much for that generation and consumption of energy). ISO New England serves as a clearing agent for the physical and financial markets to ensure that generation equals consumption and that the payments it collects equal the amounts it pays out.

ISO New England also became responsible for implementing and enforcing the agreements, rules, tariffs, and other regulations governing NEPOOL. On May 1, 1999, ISO New England implemented a new market-based system of prices in NE-POOL pursuant to the Restated NEPOOL Open Access Transmission Tariff (the “NEPOOL Transmission Tariff’) and the NEPOOL Market Rules and Procedures (the “NEPOOL Market Rules”). In this new market-based system, ISO New England determined which generator(s) would run to meet the total requirements of consumers, while maintaining the safety and reliability of the NEPOOL PTF. ISO New England’s determination of which generators to run, or “dispatch,” is generally based on the cost to the overall system (so that generators with lower bids usually get dispatched first) and is not based on bilateral contracts between Participants, including those contracts recognized and administered by ISO New England. ISO New England administers the financial settlement process according to the NE-POOL Market Rules, Pl.’s Ex. 4, and NE-POOL Transmission Tariff, PL’s Ex. 5. Specifically, ISO New England maintains a “settlement account” for each Participant, which tracks the net amount owed by or to each Participant.

ISO New England groups consumers into something called “Load Assets.” A Load Asset represents the right and obligation to provide power to a certain geographically-defined group of customers. The owner of the Load Asset has the right and obligation to provide power to the group of customers that make up the Load Asset. As of November 22, 1999, Section 12 of the NEPOOL Market Rules addressed various types of bilateral contracts between Participants. Among them was a “Load Asset Contract,” which was a contract pursuant to which one Participant could assign to another Participant some or all of the benefits and obligations within the ISO New England settlement system for serving a Load Asset or another Load Asset Contract held by the Participant. Another form of contract was known as a Block Power Contract, under which a generator simply provides power to a customer (such as CL & P) and is not subject to the benefits and obligations associated with serving a Load Asset, as is true with a Load Asset Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chesapeake Energy Corp. v. Bank of New York Mellon Trust Co.
957 F. Supp. 2d 316 (S.D. New York, 2013)
Beary v. ING Life Insurance & Annuity Co.
520 F. Supp. 2d 356 (D. Connecticut, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
467 F. Supp. 2d 187, 2006 U.S. Dist. LEXIS 83061, 2006 WL 3333748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/constellation-power-source-inc-v-select-energy-inc-ctd-2006.