Consolidation Coal Co. v. United States

60 Ct. Cl. 608, 1925 U.S. Ct. Cl. LEXIS 502, 1925 WL 2650
CourtUnited States Court of Claims
DecidedApril 20, 1925
DocketNo. A-262
StatusPublished
Cited by10 cases

This text of 60 Ct. Cl. 608 (Consolidation Coal Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidation Coal Co. v. United States, 60 Ct. Cl. 608, 1925 U.S. Ct. Cl. LEXIS 502, 1925 WL 2650 (cc 1925).

Opinion

GRAham, Judge,

delivered the opinion of the court:

This is an action to recover payment for bituminous coal claimed to have been requisitioned by the Navy under separate orders at two different times. The petition sets up two causes of action. The first cause of action grows out of an order designated N-69, which is dated the 10th of August, 1917, and covered shipments of coal beginning the latter part of June and terminating the 30th of September, 1917. The second cause of action grows out of two orders by the Navy Department, with modifications and extensions thereof Imown as N-6123 and N-6157, each dated the 12th day of June, 1919, for deliveries of coal from the 1st of July, 1919, [621]*621to the 31st of December, 1919. These last two orders were for different grades of coal, the conditions and terms of them are the same except as to the price, and originally they were the same as to price. For the purposes of this discussion only one of them will be alluded to, namely, N-6123, it being understood that what is said applies as well to N-6157. The order of August 10,1917, in the first cause of action was for 92,400 tons of coal at a price named of $2.335 per gross ton, f. o. b. mines. The plaintiff began deliveries on the 27th of June, 1917, and concluded its deliveries on September 30, 1917. On August 21, 1917, the President issued a proclamation regulating the sale of bituminous coal. The price that covered the run of mine of the plaintiff’s coal under this proclamation was $2 per net ton, equivalent to $2.24 per gross ton; and thereafter, about the 1st of September, 1917, the Navy Department informed the plaintiff .that it should adjust its billing from the price previously named in the order of $2.335 per gross ton to $2.24 per gross ton. On the 4th of September it instructed the plaintiff to continue billing at $2.335, but again, about September 17, adjusted the price to $2.24, and plaintiff delivered the coal and was paid at the provisional prices as adjusted from time to time. It is suing here to recover the difference between the sum so received and such other sum as would make just compensation for the value of the coal. The theory on which the suit is brought is that the order N-69 was a requisitioning of the coal.

The first cause of action arises under paragraph .(b) of the order, which in substance provides that a price would be tentatively fixed. If the price was accepted it would make the contract; if it was not accepted, then the plaintiff, upon delivery of the coal, would be paid the price fixed and such additional sum as would make up the difference between the price fixed and the value of the coal, being the fair market juice of the same at the time and place of delivery fixed in the order. In the first cause of action the plaintiff refused to accept the price but delivered the coal. It was paid the price and it is entitled to a further recovery in an amount which will make up the difference between the amount paid and the fair market value of the coal at the [622]*622time and place of delivery fixed by the order, which, according to the Findings of Fact, is $115,923.86. Federal Sugar Refining Co. v. United States, ante, p. 184.

The second cause of action presents a somewhat different situation. It is under subparagraph (A) of the order; and the orders in both of these causes of action, it might be stated, are in terms and conditions the same except that the first cause of action is under subparagraph (B) of the order and the second under subparagraph (A). Subparagraph (A) provides:

“ The price herein stated has been determined as just compensation for material to be delivered or service to be rendered. If satisfactory to you, payment will be made accordingly and acceptance of this price will be considered as constituting a formal release of all claims arising under this order.”

The order in another section provides:

“Prices herein stated will be subject to change due to change in wage scale or freight rate as may in general be applicable to the field in question and operative on the coal called for hereunder.”

Two orders were placed, as stated, under this second cause of action, on the 12th of June, 1919, for coal to be delivered between July 1, 1919, and the 31st of December, 1919. The price named in these orders, $3,364 per gross ton, was accepted as satisfactory by the plaintiff, and the plaintiff was paid on the basis of this accepted price for coal delivered under these orders between July 1, 1919, and November 1, 1919. For coal delivered after the 1st of November the price named in the order was increased by the Secretary of the Navy on a showing by the plaintiff that there had been an increase in wages, the amount allowed being the amount of such claimed increase. And for coal delivered from the 1st of November to the 1st of April the plaintiff was paid at this increased price. On the 25th of November the two original orders, under an order of the Secretary of the Navy, were extended. The period for delivery and the amounts to be delivered within that period were not named in the order, it being provided that they would be subject to future arrangements between the par[623]*623■ties.. This .modified and. extension.. order, provided that it should be á part of the two original orders. No price was named in it, and it is to be assumed that the price named in the original orders was to remain the same. It was accepted as satisfactory by the plaintiff. Thereafter it was arranged between the parties for the .delivery of coal from the 1st of April, 1920, to the 31st of March, 1921, and the coal embraced in the second cause of action was delivered during' that period. ■ * : ‘

The Secretary of the Navy, on the'lst of June, 1920, on a showing by the plaintiff that it had had* another increase in wages beginning the ,1st of April, again increased the price ■effective-the Tst of. April.. This monease was cumulative, being an increase on the increase already allowed. Later, on the 18th of August, the Secretary Reviewed the whole ■situation, and' it would, seem that in, order to cover all claims, those.of others as..well.as the\plaintiff — for the Navy was getting ■ coat from: other - sources — fixed- the price for all coal delivered after’1‘the51st1 ofMApril, 1920,. at $4.25. This was to cover all increases in wages after the 1st of April, 1920. As far as the plaintiff is concerned it does not appear that it had .any increase,.ip wages ¡from the 1st of April to the 16th ■o.f August, /SO- that /jUjdei?', the • contract this price of $4.25 ■covered..the original', price naipLed..i¡nvt¿!¡i@ orders plus all increases in,wages up to the JCfilr pf;August; and therefore -on coal delivered between the 1st of April and the 16th of August, 1920, the plaintiff should be paid on the basis of $4.25 per ton. .On the 16th of August-the plaintiff had .another raise of wages, which apparently, was not known to the Secretary of the Navy on the 18th pf August, at the time he named the price $4.25, and was afterwards, in September following, brought to his attention, and upon a formal claim for this increase by the plaintiff in November, 1920, the Secretary of the .Navy increased the price to •the extent of this claim for increase, effective for all coal delivered on and after the 16th of August.' As it does not appear that the plaintiff had any raise in’wage scale after August 16, 1920, the plaintiff should be paid'fbf all coal delivered after that date up to the 31st of March, 19*21, at the rate of $4.468 per ton for coal delivered under Order [624]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Services Commission v. Little-Tex Insulation Co.
39 S.W.3d 591 (Texas Supreme Court, 2001)
General Services v. Little-Tex Insulation
39 S.W.3d 591 (Texas Supreme Court, 2001)
Blaze Construction, Inc. v. United States
27 Fed. Cl. 646 (Federal Claims, 1993)
American Satellite Co. v. United States
37 Cont. Cas. Fed. 76,308 (Court of Claims, 1992)
Marathon Oil Co. v. United States
16 Cl. Ct. 332 (Court of Claims, 1989)
New York & Baltimore Transportation Line v. United States
67 Ct. Cl. 491 (Court of Claims, 1929)
Penn Chemical Co. v. United States
63 Ct. Cl. 15 (Court of Claims, 1927)
Pocahontas Fuel Co. v. United States
61 Ct. Cl. 231 (Court of Claims, 1925)
Interocean Oil Co. v. United States
61 Ct. Cl. 360 (Court of Claims, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
60 Ct. Cl. 608, 1925 U.S. Ct. Cl. LEXIS 502, 1925 WL 2650, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidation-coal-co-v-united-states-cc-1925.