Consolidated Sheet Metal Works, Inc. v. Board of Education

62 Misc. 2d 445, 308 N.Y.S.2d 773, 1970 N.Y. Misc. LEXIS 1848
New York Supreme Court·Decided February 28, 1970·Published·Cited by 3 cases

Opinion

Henry A. Hudson, J.

The petitioner instituted this article 78 proceeding by order to show cause to annul the rejection of its low bid of $386,268 for the heating, ventilating and air conditioning required for the construction of the new Watertown Elementary School and to direct respondent, sometimes hereinafter referred to as the Board, to award such contract to it as the lowest responsible bidder. A stay was granted by Hon. Richard J. Cardamons, restraining respondent from awarding the contract in question to any other bidder pending the determination of this proceeding.

The respondent advertised for sealed bids for the work in question, to be opened December 23, 1969, the contract to be let to the lowest responsible bidder. The bids were opened by the architect for the Board in the presence of the president of the Board and its attorney. Petitioner’s bid was announced as the low bid, the second lowest bid being that of the J & K Boiler Works of Oswego, N. Y., in the sum of $388,600. It was announced that no action would be taken until the next Board meeting on January 5, 1970. The architect called petitioner’s [447] attention to the lack of the noncollusive bid certification, hereinafter referred to as certificate, required by section 103-d of the General Municipal Law required under the specifications and stated that it should be supplied as soon as possible. It was submitted on the following day and accepted by the architect. Within a few days the second lowest bidder advised the respondent that petitioner’s hid was improper and insufficient without the certificate required by said section 103-d and must be rejected and their hid should he accepted as the resulting low bid. When the Board met on January 5, 1970 they rejected petitioner’s bid solely on the ground that it was incomplete and not in accordance with law or the architects’ specifications in that ,said hid did not contain the certificate required by section 103-d of the General Municipal Law and voted to accept the second low hid.

No answer was submitted on behalf of the respondent. Counsel for the Board submitted an affidavit setting forth the factual circumstances substantially as hereinafter set forth and attached a copy of the resolution of the Board rejecting petitioner’s bid. It was indicated to the court on the argument of the motion that counsel did not consider that there was any material dispute as to the facts involved in the present controversy, and that only a question of law was involved. The petitioner called the attention of the court to the decision of Hon. George H. Vinette, Justice of the Supreme Court, in the Matter of Beaudette Constr. Co. v. City of Syracuse (62 Misc 2d 564), and the decision of Hon. Robert F. Main, Justice of the Supreme Court, in Matter of McConville, Inc. v. City of Ogdensburg. Both of these decisions, they urge, support their position. The respondent called the attention of the court to the decision of Hon. Donald H. Mead, Justice of the Supreme Court, in Matter of Manson Constr. v. City of Oswego, dated October 13, 1969, which they urge, supports their position. The court’s attention was also called to decisions of the Commissioner of Education in Matter of Richards v. Board of Educ. (5 N. Y. Educ. Dept. Rep. 112) and Matter of Kewanee Tech. Furniture Co. v. Board of Educ. (5 N. Y. Educ. Dept. Rep. 96) and the Opinions of the Comptroller identified as Opinions 68-189 and 68-702, dated March 20 and • October 11, 1968, respectively, which the respondent urges supports its position.

The court was advised that by reason of the apparent conflict in the interpretation of section 103-d of the General Municipal Law in the above opinions, that an appeal from the court’s decision would he necessary regardless of the outcome and that it [448] was the hope of the parties that a decision could be forthcoming so that application could be made to argue the appeal jointly with the argument of an appeal from the decision of Justice Vinette (supra) which was presently before the Appellate Division. The court has since been advised that such appeal has already been argued but that no decision will be handed down until at least March 30,1970. *

I do not feel that there is any disputed question of fact which would require a trial as required by CPLR 7804 (subd. [h]). (Matter of Carucci v. Dulan, 24 A D 2d 529.)

Briefly stated the material facts are: The Board of Education of the City of Watertown, N. Y. advertised for bids for the heating, ventilating and air conditioning together with bids for all other work required for the construction of the Watertown Elementary School. The sealed bids were to be publicly opened on December 23, 1969, at the office of the Board at 8:00 p.m. The specifications required that the certificate required by section 103-d of the General Municipal-Law should be ¡submitted with the bid. The bids for heating, ventilating and air conditioning were opened on schedule. The architect, the Board president and the attorney for the Board were present. There were 10 bids submitted. Two of the bids including petitioner’s did not contain the certificate. The petitioner’s bid was the low bid. The results of the bidding were announced and it was also announced that no action would be taken on the bids until the meeting of the Board, which would not be held until January 5,1970. The architect for the Board, who was in charge of the opening and recording of the bids, advised the petitioner that he should submit the certificate as soon .as possible. The petitioner submitted such a certificate the following day, December 24, 1969. Within a few days the second lowest bidder J & K Boiler Co., Inc., of Oswego, advised the Board of Education by telephone and by letter that the petitioner’s bid could not be accepted because of the failure of petitioner to submit the certificate as a part of his sealed bid and insisted that their bid be accepted and the petitioner’s rejected. The Board met on January 5, 1970 and took petitioner’s bid under consideration and by formal resolution rejected the same solely for the reason that it had not contained the certificate at the time that the bid was opened with the declaration; that the bid was incomplete and not in accordance with law or the architectural specifications in that said bid did not contain the certificate required by section 103-d of [449] the General Municipal Law and accepted, subject to final approval of the plans, the bid of the J & K Boiler Co., Inc., of Oswego.

Free access — add to your briefcase to read the full text and ask questions with AI

Consolidated Sheet Metal Works, Inc. v. Board of Education, 62 Misc. 2d 445, 308 N.Y.S.2d 773, 1970 N.Y. Misc. LEXIS 1848 (N.Y. Super. Ct. 1970).

62 Misc. 2d 445 (Consolidated Sheet Metal Works, Inc. v. Board of Education) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Le Cesse Bros. Contracting, Inc. v. Town Board of Williamson
62 A.D.2d 28 (Appellate Division of the Supreme Court of New York, 1978)
General Building Contractors of New York State, Inc. v. City of Syracuse
298 N.E.2d 122 (New York Court of Appeals, 1973)
Bailey v. Colonna
73 Misc. 2d 299 (New York Supreme Court, 1972)