Consolidated Rail Corp. v. State

589 A.2d 569, 87 Md. App. 287, 1991 Md. App. LEXIS 112
CourtCourt of Special Appeals of Maryland
DecidedMay 9, 1991
Docket1041, September Term, 1990
StatusPublished
Cited by4 cases

This text of 589 A.2d 569 (Consolidated Rail Corp. v. State) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Rail Corp. v. State, 589 A.2d 569, 87 Md. App. 287, 1991 Md. App. LEXIS 112 (Md. Ct. App. 1991).

Opinion

ROBERT M. BELL, Judge.

Consolidated Rail Corporation, appellant, appeals from the judgment of the Circuit Court for Prince George’s County granting summary judgment in favor of the State of Maryland, appellee, (hereinafter “the State”), for the costs incurred by the State in connection with appellant’s performance of work at a railroad grade crossing. It presents two questions for our resolution:

1. Do the provisions of § 8-640 and § 8-642 of the •Transportation Article of the Annotated Code of Mary *290 land apply to the case at bar thus limiting the State’s recovery to 25% of the cost of its detour and repair work? 2. Does the State’s claim, which sounds in negligence, entitle it to recover the costs of its detour work which was undertaken prior to Conrail’s alleged negligent action?

We resolve the first issue against appellant, but hold in its favor as to the second. Therefore, we will affirm in part and reverse in part.

This appeal had its genesis when appellant performed work on its tracks and the adjacent roadway at a railroad grade crossing located on U.S. Route 301, south of Maryland Route 4, in Upper Marlboro, Maryland. Although the work was done with its knowledge, the State contended that it was negligently and improperly done, thus creating an unsafe condition for motorists 1 and necessitating it, the State, to perform emergency repairs. When appellant did not respond to the State’s demand that it be reimbursed for the expenses it incurred in correcting appellant’s work, the State filed this action in the Circuit Court for Prince George’s County. That court granted the State’s motion for summary judgment as to liability and determined, from the undisputed facts, that the total possible damages amounted to $31,082.67. It denied the State’s motion for summary judgment as to damages, however. As to that, the court “ordered that this matter be scheduled on the basis of possible apportionment of payment____” Following discovery and a further hearing, the court granted the State’s motion for summary judgment in the full amount of the damages previously determined. It ruled “that the [apportionment] statute doesn’t apply, so, therefore, there is *291 no apportionment.” It is from this aspect of the judgment, i.e., that the apportionment statute does not apply, that appellant has appealed.

1.

Appellant first argues that, pursuant to §§ 8-640(e) 2 and 8-642 3 of the Maryland Transportation Code Ann., it is obligated to pay, and the State may only recover, 25 percent of the cost of the repair work it performed at the grade crossing. This result is mandated, it says, by the clear and unambiguous language of the statutes, the application of which would not result in an illogical or unfair result.

Not surprisingly, the State takes the opposite position. It argues that “[t]he intent of the apportionment statute ... is to require railroads to pay only 25% of project costs, if, but only if, the State is either the cause or beneficiary of the work.” Thus, it maintains that, because it is required, pursuant to subtitle 6 of Title 8 of the Transportation Code Ann., and, in particular, § 8-601, to “construct, reconstruct, and repair State highways as necessary and [to] maintain them in good condition,” the legislature authorized the State to reimburse the railroad for 75 percent of the cost of *292 any work performed by the railroad which directly or incidentally carries out the State’s mandate, that is, that it helps it to meet its statutory responsibilities. Like appellant, the State relies upon statutory construction to support the position it espouses.

We approach the interpretation of a statute with the goal of determining its legislative purpose, “the general aim or policy, ‘the ends to be accomplished ... ’ by the statute construed.” Norris v. United Cerebral Palsy of Central, Maryland, et al., 86 Md.App. 508, 516, 587 A.2d 557 (1991), quoting Morris v. Prince George’s County, 319 Md. 597, 603-04, 573 A.2d 1346 (1990). See also Department of Environment v. Showell, 316 Md. 259, 270, 558 A.2d 391 (1989); ANA Towing, Inc. v. Prince George’s County, 314 Md. 711, 715, 552 A.2d 1295 (1989). Since “what the legislature has written in an effort to achieve a goal is a natural ingredient of analysis to determine that goal,” Kaczorowski v. City of Baltimore, 309 Md. 505, 513, 525 A.2d 628 (1987), the language of the statute is the logical starting place for the process. Brodsky v. Brodsky, 319 Md. 92, 98, 570 A.2d 1235 (1990). Nevertheless, the “meaning of the plainest language” is affected by its context, Matter of Diane M., 317 Md. 652, 658, 566 A.2d 108 (1989), and, therefore, even though it may not be necessary to go beyond a review of the statutory language when that language sufficiently expresses the legislative purpose, Davis v. State, 319 Md. 56, 61, 570 A.2d 855 (1990), the court is always free to consider the statutory language in the context in which it appears. State v. Runge, 317 Md. 613, 618, 566 A.2d 88 (1989); Warfield v. State, 315 Md. 474, 499-500, 554 A.2d 1238 (1989). Moreover, a court should neither resort to subtle or forced interpretations for the purpose of extending or limiting the operation of the statute, Mayor and City Council of Baltimore v. Hackley, 300 Md. 277, 283, 477 A.2d 1174 (1984); Schweitzer v. Brewer, 280 Md. 430, 438, 374 A.2d 347 (1977); Board of Trustees v. Kielczewski, 77 Md.App. 581, 587-88, 551 A.2d *293 485, cert. denied, 315 Md. 692, 556 A.2d 673 (1989); Department of Health v. Congoleum Corp., 51 Md.App. 257, 264, 443 A.2d 130 (1982), nor adopt a construction leading to results which are unreasonable, illogical, and inconsistent with common sense. State v. Bricker, 321 Md.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Comptroller of the Treasury v. Hickey
689 A.2d 1316 (Court of Special Appeals of Maryland, 1997)
Lombardi v. Montgomery County
673 A.2d 762 (Court of Special Appeals of Maryland, 1996)
Barr v. Barberry Bros., Inc.
635 A.2d 64 (Court of Special Appeals of Maryland, 1994)
C & R CONTRACTORS v. Wagner
614 A.2d 1035 (Court of Special Appeals of Maryland, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
589 A.2d 569, 87 Md. App. 287, 1991 Md. App. LEXIS 112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-rail-corp-v-state-mdctspecapp-1991.