Consolidated Gold & Sapphire Mining Co. v. Struthers

111 P. 150, 41 Mont. 551, 1910 Mont. LEXIS 98
CourtMontana Supreme Court
DecidedSeptember 26, 1910
DocketNo. 2,847
StatusPublished
Cited by8 cases

This text of 111 P. 150 (Consolidated Gold & Sapphire Mining Co. v. Struthers) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Gold & Sapphire Mining Co. v. Struthers, 111 P. 150, 41 Mont. 551, 1910 Mont. LEXIS 98 (Mo. 1910).

Opinion

MR. JUSTICE HOLLOWAY

delivered the opinion of the court.

Upon the filing of the verified complaint, the district court of Deer Lodge county issued an order to show cause why an injunction should not be granted restraining defendants from doing certain things of which complaint was made by plaintiff. The defendants appeared by answer, and a hearing was had, at the conclusion of which the court granted an injunction pendente lite, by the terms of which defendants “are enjoined and restrained from depositing sawdust in the stream flowing through plaintiff’s Ruby First placer claim described in the complaint, or upon the banks thereof, from whence it would ultimately naturally deposit in said stream above plaintiff’s said placer claim, or upon the adjacent placer ground, and valley land, within said Ruby First placer claim, and as distinguished from the hill lands. ’ ’ From the order granting this injunction defendants appealed.

The injunction is not so broad as requested by plaintiff in its complaint. It refers only to one ground1 of complaint made, and it will therefore be necessary to consider the pleadings only so far as they relate to the particular matter covered by the injunction. The plaintiff alleges that it is the owner of the Ruby First placer mining claim, that it has expended large sums of money in constructing a steam dredge for conducting its placer mining operations on said claim, and in constructing a dam necessary for impounding water sufficient for its use. It then alleges that the defendants have built and are operating a sawmill immediately above the point where plaintiff is intending to operate its dredge; that there is a stream of water flowing by the sawmill [553]*553and through the placer claim; that defendants are depositing sawdust from their mill in this stream and upon the banks thereof, so that it naturally will be deposited in the stream; that such sawdust is being carried down said stream and intermingled with the sand, gravel, and soil of plaintiff’s placer claim at the point where it intends to operate its dredge; that the sawdust thus deposited will clog and' obstruct the machinery of the dredge, and prevent plaintiff from working it and from extracting the valuable minerals from the ground; and that defendants threaten to continue such operations. Most of these allegations are denied in the answer, and defendants plead affirmatively matters by way of estoppel in pais. In their‘brief counsel for appellants say: “The district court was not justified in issuing an injunction pendente lite restraining appellants from depositing sawdust in the stream flowing through the so-called Ruby First placer, etc., as the proof wholly failed to show that such had been done or was contemplated by appellants, but, on the contrary, demonstrated that the sawdust pile of appellants, to which sawdust was flumed from their sawmill, was so far removed from the creek and so many obstructions intervened that in the natural course of events it could not, and did not, work its way into the creek, and that the respondent has been in no wise damaged thereby. ’ ’

Upon the hearing plaintiff introduced the testimony of a civil engineer who had been upon the ground a short time before the hearing, making surveys, and who observed the conditions about the sawmill and at the sawdust dump. This witness testified that the sawdust was carried away from the mill to the dump by means of water running through a box flume. Some of the pertinent testimony given by this witness follows: “Q. And how did this dump lie at this time, with reference to the creek itself, through the ground ? A. This dump is to the southwest of the creek, but there is a great deal of sawdust that is going down in the creek bed. It is distributed all the way down to the dredge. * * " Q. And how did the water act after it had dumped upon this sawdust heap, or did you observe it? A. It would always dam itself up, and it would form a dam on the pile until [554]*554the pressure got great enough to break it, and then it would be released. Q. And where would it run to? A. It would run in all directions. Q. Any of it go down the creek? A. Some of it would. Q. Carrying sawdust with it, that you observed? A. Yes.”

A witness Simon, for the plaintiff:, testified that, while the main sawdust dump is some fifty feet from the creek, the sawdust is scattered about the creek bank and into the creek, and has been carried down the creek and deposited on the placer ground from the mill to a point below where the dredge was then located,, a distance of about half a mile. This witness also testified that the sawdust, when water-soaked, sinks'and is intermingled with the sand, gravel, and dirt; that, if deposited in the sand, gravel, and dirt to be worked by the dredge, the sawdust would clog up and obstruct the machinery, particularly the trommels and riffles, to such an extent that the valuable minerals would not be saved, and would also interfere with the working of the pumps.

Two other witnesses for plaintiff, William and John Goodwin, who constructed the dredge for plaintiff and who appear to be men of wide experience in handling dredges in placer operations, testified to substantially the same facts so far as the effect which the sawdust would have upon the operations of the machinery is concerned. The witness William Goodwin also testified that there was sawdust on the placer claim which had been washed down from the mill. It is admitted in the answer that defendants claim the right to continue their operations of the mill as theretofore conducted.

Much of the argument of counsel for appellants might be apropos if this question arose upon an appeal from an order granting a permanent injunction after a hearing upon the merits; but the rule applicable in such a case is not the rule to be applied in a case of an injunction pendente lite. And whether or not we might deem the exigencies of this case, as disclosed at the hearing, sufficient to warrant permanent relief by way of injunction, is not now for consideration. It is not essential to the validity of an order granting an injunction pendente lite that the evidence in support of the order should be of such character as to [555]*555warrant permanent relief in plaintiff’s favor at the trial upon the merits. (Heinze v. Boston & Mont. C. C. & S. Min. Co., 26 Mont. 265, 67 Pac. 1134.) In fact, the granting of an order for an injunction pendente lite is within the sound discretion of the trial court, and, in the absence of a manifest abuse of such discretion, the order will be affirmed. (Parrot S. & C. Co. v. Heinze, 25 Mont. 139, 87 Am. St. Rep. 386, 64 Pac. 326, 53 L. R. A. 491; Heinze v. Boston & Mont. C. C. & S. Min. Co., 30 Mont. 484, 77 Pac. 421.)

However much the evidence offered by the defendants may conflict with that given by the plaintiff, we do not feel disposed to interfere with the finding of the trial court that the evidence preponderates in favor of plaintiff’s contention. The trial court, in the first instance, was the sole judge of the credibility of the witnesses and of the weight to be given to their testimony. It occupied a position much more advantageous than does this court, in that it heard the witnesses testify, observed their.demeanor, and was therefore much better qualified to weigh the evidence. Under such circumstances, this court has repeatedly refused to interfere.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Miller
190 P.2d 72 (Montana Supreme Court, 1948)
Cocanougher v. Zeigler
112 P.2d 1058 (Montana Supreme Court, 1941)
Rumsey v. Spratt
255 P. 5 (Montana Supreme Court, 1927)
Atkinson v. Roosevelt County
214 P. 74 (Montana Supreme Court, 1923)
Parsons v. Mussigbrod
196 P. 528 (Montana Supreme Court, 1921)
Cummins v. Cummins
195 P. 1031 (Montana Supreme Court, 1921)
Ringling v. Mahurin
197 P. 829 (Montana Supreme Court, 1921)
Monidah Trust v. Sheehan
123 P. 692 (Montana Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
111 P. 150, 41 Mont. 551, 1910 Mont. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-gold-sapphire-mining-co-v-struthers-mont-1910.