Consolidated Engineering Co. v. State Road Commission

1 Ct. Cl. 358
CourtWest Virginia Court of Claims
DecidedNovember 23, 1942
DocketNo. 106
StatusPublished

This text of 1 Ct. Cl. 358 (Consolidated Engineering Co. v. State Road Commission) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Engineering Co. v. State Road Commission, 1 Ct. Cl. 358 (W. Va. Super. Ct. 1942).

Opinion

WALTER M. ELSWICK, Judge.

On the 23rd day of September 1932, the state road commission entered into a contract with claimant, Consolidated Engineering Company, a corporation, for certain excavation, hauling and filling in the construction of what is now known as route No. 2 immediately south of Moundsville in Marshall county, West Virginia, and more particularly designated as Round Bottom hill, Moundsville road, project No. e-184-c. Claimant started work on the project on October 10, 1932 and completed same on November 28, 1934.

[359]*359The work consisted of excavation, hauling and filling through a rugged, mountainous locality. The surface of the mountainside was irregular and the slope varied. This excavation was made of the mountainside above the Baltimore and Ohio Railroad tracks, which tracks and roadway run parallel with the mountain.

It appears from the evidence that the right-of-way for this road was surveyed in April 1928. At this time the engineers for the state road commission took cross-sections or laid down a base line with stakes approximately fifty feet apart along the ditch line of the railway track. No additional surveys of the topography of the mountainside or slope were made until after the excavations were completed.

The terms of payment for excavation and hauling under the contract were: Unclassified excavation was to be paid for at the rate of 34 cents per cubic yard dug. Overhaul consisting of a measure for each cubic yard per 100 feet hauled a greater distance than 1000 feet was to be paid at a price of one-fourth cent per station yard. Paragraph 12, page 6 of the contract provided that the certificate of estimates of the engineer shall state, from actual measurements, the whole amount of work done by the contractor. Section 74 subsection “a” of the specifications, entitled “basis to pay” provides that the work shall be paid for at the contract unit price per cubic yard of excavation measured in its original position, excavated and deposited in accordance with the specifications.

After the excavations were made the state road commission by its engineers in 1935 undertook to ascertain the amount of excavation by running cross-sections in the cut in accordance with the purported original base line run by the survey in 1928. From the evidence it appears that the usual and customary method to obtain the amount of excavation made is from measurement in the cut based upon the preliminary survey, but from good engineering practice in order to do so in a practical manner in a rugged and irregular country like the one in question it is necessary to survey the topography of tfie surface within a reasonable time before the excavation and to survey the cut within a reasonable time after the excavation is made. [360]*360From all ihe facts and circumstances in evidence in this .case, it appears that the surveying was not done in that way in this case.

It further appears from the evidence in this case that the original survey made in 1928, nearly five years before the excavation, was inaccurate and insufficient to enable the engineers to use same as a basis of obtaining actual measurements of the whole amount of the work done. For it appears that at the request of the claimant’s representatives the engineers undertook to take cross-sections of the cut at intervals of less than 50 feet on the original base line and it was impossible to make the majority of those taken to close. Some of these cross-sections failed to close with living monuments (record pp. 45-47). For a distance of approximately 8800 lineal feet along the project running from the south to the north between station 437 plus 50 to station 525 plus 50, it appears that at least a total of 478 separate cross-sections were run, and that of this number 312 were so defective in closing with the original surface as taken from the old survey that they were not used in making calculations of the measurement of the excavation. Of the remaining 156 cross-sections used in making calculations 105 or approximately two-thirds of them had errors or discrepancies shown on them. (Record p. 87). It appears that the engineers in calculating the measurements from these 156 cross-sections used undertook to resolve in favor of claimant certain measurements in some of the 105 cross-sections used which had errors and discrepancies. But even then it does not appear that they could arrive at actual measurements of the excavations made, for after they went back for re-checks on these cross-sections it was found that they could not be made to close with the purported survey of 1928 made of the original ground surface. Therefore, not having accurate measurements of the original ground surface immediately prior to the time of the excavations they could not arrive at an actual measurement of the excavation made even though these 156 cross-sections used had been taken at sufficient intervals to calculate measurement of a slope with a regular surface.

Although the excavation was completed on November 28, 1934, final cross-sections were not completed until about April [361]*3611935. The' engineers in making said final survey after (he work was completed had to use the old survey made in 1928 with stations fifty feet apart. They then endeavored to take cross-sections at closer intervals, at the request of claimant, as close as ten feet or less. Forced to use their old survey with stations. 50 feel apart they interpolated in between to get Ihe original ground surface to be laken in the calculation from the cut surface on the excavated section. This could have; been done more or less successfully if the original survey and final sui vey had been accurate. They were then in position to re-check the final survey of the cut which they did and which was verified. They could not however re-check the original survey for the material had been removed. The interpolated cross-sections were so inaccurate and out of proportion with the survey of the cut as compared with the old survey that they could not. be used. They were of no benefit in arriving at actual measurements of the work done. We can come to no other conclusion than that either the original survey was inaccurate or that there had been a material change in the contour of the hillside by slipping or slides between the time of Ihe original survey and that of the excavation.

The question confronting us upon this inquiry is whether or no! the claimant has been paid for the work done under its contract. The contract provides that this shall be arrived at by actual measurements. We are of the opinion that the claimant has shown by a preponderance of the evidence that the amount of actual excavation done, by measurement of the cut, would not bo an actual measurement, since this cannot be done with any degree of certainly due to the failure of cross-sections of the cut take'll from (he final survey to close with Ihe original survey within (he bounds of tolerance by averages under all engineering practice. And of course it would seem that when 478 cross-sections are first reduced by 312 cross-sections discarded, and, out of the remaining 15(i used. 105 cross-sections had errors or discrepancies, leaving only approximately IF, of those taken to be accurate, the law of averages would become more and more disrupted and out of proportion as a guide' for actual measurements. It appears that lb»re must have been a fundamental error in the original [362]*362survey of 1928 throughout this area excavated and that same could serve no purpose in the measurements of the cut.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
1 Ct. Cl. 358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-engineering-co-v-state-road-commission-wvctcl-1942.