Consolidated Electrical Distributors of El Paso, Inc. v. Peinado

478 S.W.2d 565, 1972 Tex. App. LEXIS 2851
CourtCourt of Appeals of Texas
DecidedMarch 8, 1972
DocketNo. 6215
StatusPublished

This text of 478 S.W.2d 565 (Consolidated Electrical Distributors of El Paso, Inc. v. Peinado) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Electrical Distributors of El Paso, Inc. v. Peinado, 478 S.W.2d 565, 1972 Tex. App. LEXIS 2851 (Tex. Ct. App. 1972).

Opinion

OPINION

WARD, Justice.

This action was brought by the plumbing subcontractor’s materialman, Consolidated Electrical Distributors of El Paso, Inc., against the general contractor, Emilio Pei-nado, who built the Fiesta Apartments in El Paso. The cause of action was based on an alleged breach of the terms of a written joint check agreement entered into between the general contractor, Peinado, the plumbing subcontractor, Barton-Moon Plumbing Company, and the materialman, Consolidated Electrical, which provided that certain checks issued by Peinado on the plumbing would be payable jointly to the plumbing subcontractor, Barton-Moon, and to the materialman, Consolidated Electrical. Trial was to a jury which determined that the plaintiff, Consolidated Electrical, had waived its rights under the terms of the joint check agreement. The trial Court then rendered judgment on the ver-' diet for the defendant, Peinado. We affirm the judgment of the trial Court.

Previous to November, 1967, Emilio Peinado as the general contractor had [566]*566accepted a bid from Barton-Moon to perform all plumbing- on the project for the sum of $57,000.00. Payments on the contract were to be based on progress reports furnished at the end of each month by Barton-Moon and were to be paid by the tenth of the month following less ten per cent retainage. Barton-Moon was engaged in the general plumbing contracting business and purchased all of its material from Consolidated Electrical. It was obvious that Barton-Moon was in a financially distressed condition, and, to assure itself, Consolidated Electrical had secured some fifty joint check agreements covering the various projects which had been undertaken by Barton-Moon. Following this policy, on November 9, 1967, Consolidated Electrical, Barton-Moon, and Peinado entered into the written tri-party Joint Check Agreement, under our consideration, the first part of which provided as follows:

“1. That the aforesaid parties agree that unpaid invoices which have heretofore been rendered or may hereafter be rendered by the said materialman to said Subcontractor for materials sold by said materialman to said Subcontractor for use in said project shall be paid for by a negotiable check made by the said Prime Contractor payable jointly to the said Subcontractor and the said materialman. Said checks shall be delivered to the said material-man within the credit periods allowed to the said Subcontractor. Attached hereto is a true list of the invoices heretofore rendered by said material-man to the said Prime Contractor and presently unpaid by said Subcontractor. The said Prime Contractor will deliver a joint check to the said materialman for the total sum of all unpaid invoices shown on the attached list which are due on the same date as shown on said attached list on or before such due date.
2. The said materialman will present each such joint check to the said Subcontractor and the said Subcontractor will immediately endorse said joint check and return the same to the said materialman.
3. All joint checks shall be in payment of a specific unpaid invoice or invoices and shall be in the amount of the exact total of said unpaid invoice or invoices.”

Additional provision of the agreement provided that it did not constitute an assignment of funds nor payment but constituted security for payment; that rights against bondsmen, and lien rights would not be affected. No list of invoices were attached to the agreement.

Performance of the express and implied duties and obligations of the agreement can be said to have been wholeheartedly ignored during the construction of the project. The very heart of the agreement is that Peinado will deliver to Consolidated Electrical a joint check of specific unpaid invoices in the exact amount of the invoice or invoices within the credit period allowed to Barton-Moon. The credit period on the invoice provided for payment within thirty days. This was later extended by agreement between Consolidated and Barton-Moon to ninety days, and this later partially abrogated by the taking of a note as herein discussed. No check was ever issued covering any unpaid invoice or invoices. Again, at the heart of the agreement is an implied condition that either Barton-Moon or Consolidated would get the unpaid invoices to Peinado. None were ever presented to Peinado until after completion of the project. Peinado continued to pay to Barton-Moon the monthly progress reports less the ten per cent retainage with the final payment of the $57,000.00 contract being made on September 12, 1968, by check for $1,400.-00, after the plumbing construction contract had been completed. It was only after November, 1968, that any demand was ever made by the material supplier to Pein-ado. At that time it was asserted that $38,592.44 was owing by Barton-Moon to the supplier for the unpaid materials used by Barton-Moon on the project. This was after Barton-Moon had become insolvent [567]*567and was well on its way toward bankruptcy. Suit being instituted for this amount, Pein-ado answered that a condition precedent to any obligation arising on his part under the terms of the joint check agreement was the furnishing by either Consolidated Electrical or Barton-Moon of unpaid invoices subject to the joint check agreement. In addition, the defenses of waiver and estoppel were urged.

The case was submitted on the theory that the waiver issue was applicable, and we will ignore the implied condition precedent. Appellant in this regard presents to us “no evidence” and “insufficient” points to attack the jury finding that the appellant had waived its right to be paid by negotiable joint check. Considering the legal insufficiency point first, we will of course consider only the evidence and the inferences arising therefrom tending to support the jury finding. In this regard, we are fortunate, as a review of the evidence shows that no dispute developed except in the area regarding the amount of unpaid for materials that were actually used in the Fiesta Apartment project. As pointed out, it was the contention of Consolidated Electrical that this amounted to $38,-592.44. Peinado, asserted a less figure, and the jury determined the amount to be $19,-171.22.

The joint check agreement is explicit in calling for the issuance of any joint check to be in the exact amount of unpaid invoice or invoices covering the materials furnished by Consolidated to Barton-Moon for use in the project. The agreement refers to a true list of the previously rendered and unpaid invoices which are attached. The prime contractor was obligated to deliver a joint check to the ma-terialman for the total sum of the unpaid invoices. According to the exhibits of Consolidated, on that date there were invoices unpaid in the amount of $2,975.48, yet no list was attached nor was any information furnished to Peinado nor was any request made for the payment of this amount.

Again, the joint check agreement called for all of Peinado’s checks to be delivered by Peinado to Consolidated. Yet, all checks paid by Peinado to Barton-Moon were always delivered to Barton-Moon. The first check, made payable under the plumbing contract, was dated December 11, 1967, was in the amount of $6,000.00, and was made payable to Barton-Moon Plumbing and Consolidated. After being delivered to Barton-Moon, it was thereafter endorsed and delivered to Consolidated which thereafter credited the Barton-Moon account.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Terrazas v. Sullivan
470 S.W.2d 904 (Court of Appeals of Texas, 1971)
Maryland Casualty Co. v. Palestine Fashions, Inc.
402 S.W.2d 883 (Texas Supreme Court, 1966)
Stowers v. Harper
376 S.W.2d 34 (Court of Appeals of Texas, 1964)
Massachusetts Bond. & Ins. Co. v. Orkin Exterm. Co.
416 S.W.2d 396 (Texas Supreme Court, 1967)
Rolison v. Puckett
198 S.W.2d 74 (Texas Supreme Court, 1946)
Texas & Pacific Railway Co. v. Wood
199 S.W.2d 652 (Texas Supreme Court, 1947)
Prætorians v. Strickland
66 S.W.2d 686 (Texas Commission of Appeals, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
478 S.W.2d 565, 1972 Tex. App. LEXIS 2851, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-electrical-distributors-of-el-paso-inc-v-peinado-texapp-1972.