This text of 39 A.D.3d 792 (Consolidated Construction Group, LLC v. Bethpage Union Free School District) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Construction Group, LLC v. Bethpage Union Free School District, 39 A.D.3d 792, 835 N.Y.S.2d 630 (N.Y. Ct. App. 2007).

Opinion

In an action to recover damages for breach of contract, the defendant appeals, as limited by its brief, from so much of an order of the Supreme Court, Nassau County (Brennan, J.), dated February 10, 2006, as granted those branches of the plaintiffs motion which were to dismiss its first through ninth affirmative defenses, denied that branch of its cross motion which was for summary judgment dismissing the first cause of action, and granted that branch of the plaintiffs separate motion pursuant to Education Law § 3813 (2-a) which was to deem its notice of claim timely filed to the extent of extending the time to file a notice of claim relating to the first cause of action.

Ordered that the order is modified, on the law, (1) by deleting the provision thereof granting that branch of the plaintiffs motion which was to deem its notice of claim timely filed to the extent of extending the time to file a notice of claim relating to the first cause of action and substituting therefor a provision denying that branch of the plaintiffs motion, (2) by deleting the provision thereof granting that branch of the plaintiffs motion which was to dismiss the defendant’s second affirmative defense insofar as asserted against the first cause of action and substituting therefor a provision denying that branch of the plaintiffs motion, (3) by deleting the provision thereof granting those branches of the plaintiffs’ motion which were to dismiss the first, third, fourth, fifth, sixth, seventh, eighth, and ninth affirmative defenses with respect to the first cause of action and substituting therefor a provision denying those branches of the [793]*793motion as academic, (4) by deleting the provision thereof denying that branch of its cross motion which was for summary judgment dismissing the first cause of action and substituting therefor a provision granting that branch of the cross motion, (5) by deleting the provision thereof granting those branches of the plaintiff’s motion which were to dismiss the second and seventh affirmative defenses with respect to the second cause of action and substituting therefor a provision denying those branches of the motion, and (6) by adding the words “with leave to the defendant to replead those affirmative defenses” to the provision thereof granting that branch of the plaintiffs motion which was to dismiss the third, fourth, fifth, sixth, eighth, and ninth affirmative defenses with respect to the second cause of action; as so modified, the order is affirmed insofar as appealed from, with costs.

In May 2002 the parties entered into a contract for the renovation of two of the elementary schools operated by the defendant (hereinafter the general contract). In June 2002 the parties entered into a contract for certain heating and mechanical work at the same two schools (hereinafter the heating contract). In 2004 disputes arose over certain aspects of the work to be performed by the plaintiff and payments allegedly due to the plaintiff, and several letters reflecting these issues were exchanged.

By letter to the plaintiff from the defendant’s attorneys dated July 16, 2004, the defendant declared the plaintiff to be in default of the general contract. The plaintiff performed some work under the heating contract until December 28, 2004.

On May 12, 2005, the plaintiff served a notice of claim asserting breach of the general contract and served a separate notice of claim asserting breach of the heating contract. The plaintiff commenced this action on July 14, 2005, seeking, in the first cause of action, to recover the balance allegedly due under the general contract and, in the second cause of action, the balance allegedly due under the heating contract. In its answer, the defendant asserted, inter alia, the following affirmative defenses: “[First] The Complaint fails to state a cause of action upon which relief maybe [sic] granted . . . [Second] Consolidated is barred, in whole or in part, from maintaining this action against the District since it has failed to timely serve the District with a Notice of Claim as required by law and has failed to properly allege the timely service of a Notice of Claim . . . [Third] Consolidated’s claims are barred, in whole or in part, by the doctrines of waiver, estoppel and/or laches . . . [Fourth] Consolidated’s claims are barred, in whole or in part, by the [794]*794doctrine of unjust enrichment . . . [Fifth] Any damages which Consolidated allegedly sustained were not proximately caused by any conduct of the District or its agents, servants, or employees . . . [Sixth] Consolidated’s damages, if any, are the result of its own acts and/or omissions or those of third parties who were not subject to the control of the District . . . [Seventh] Consolidated’s claims are, in whole or in part, barred by the applicable statute of limitations . . . [Eighth] Consolidated’s claims are barred, in whole or in part, by reason of its failure to mitigate damages . . . [Ninth] Consolidated’s claims are barred, in whole or in part, by its own breaches of contract and/or inequitable conduct . . . [Tenth] Consolidated failed to perform the work, labor or services required under its Contracts with the District and/or the Contract Documents in a timely, complete and/or workmanlike manner.”

On August 12, 2005, the plaintiff moved to strike the defendant’s affirmative defenses, and on September 16, 2005, the defendant cross-moved for summary judgment “dismissing the complaint as barred by the notice of claim provisions of Education Law § 3813 (1).” On October 12, 2005, the plaintiff moved “pursuant to Education Law § 3813 (2-a) to deem the plaintiffs Notice of Claim timely filed,” and the defendant opposed that motion. The defendant appeals from an order of the Supreme Court which, inter alia, granted those branches of the plaintiffs motion which were to dismiss its first through ninth affirmative defenses, denied that branch of its cross motion which was for summary judgment dismissing the first cause of action, and granted that branch of the plaintiffs separate motion pursuant to Education Law § 3813 (2-a) which was to deem the notice of claim timely filed to the extent of extending the time to file a notice of claim relating to the first cause of action.

The requirement of Education Law § 3813 (1) that a notice of claim be served upon a school district in an action arising from a contract within three months from accrual of the claim is a condition precedent to maintaining such action (see Parochial Bus Sys. v Board of Educ. of City of NY., 60 NY2d 539 [1983]; Clune v Garden City Union Free School Dist., 34 AD3d 618 [2006]; Cacheiro v Middletown Enlarged City School Dist., 29 AD3d 846 [2006]). Although Education Law § 3813 (2-a) permits a claimant to seek an extension to file a late notice of claim, an application under section 3813 (2-a) must be made within the period of limitations for such claims, which is one year pursuant to section 3813 (2-b) (see Capstone Enters, of Port Chester, Inc. v Valhalla Union Free School Dist., 27 AD3d 411 [2006]; Allshine, C.S. v South Orangetown Cent. School Dist., 305 AD2d 617 [795]*795[2003]; Pope v Hempstead Union Free School Dist. Bd. of Educ., 194 AD2d 654 [1993]). It has frequently been observed that the Supreme Court does not have authority to entertain such an application when made after the expiration of the period of limitation (see e.g. Matter of Ricci v Harrison Cent. School Dist., 27 AD3d 653 [2006]; Cluhe v Garden City Union Free School Dist., supra; Dolce v Bayport, Blue Point Union Free School Dist., 286 AD2d 316 [2001]).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blaize v. New York City Dept. of Educ.
2022 NY Slip Op 03224 (Appellate Division of the Supreme Court of New York, 2022)
Blaze v. New York City Department of Education
112 A.D.3d 428 (Appellate Division of the Supreme Court of New York, 2013)
Moran Enterprises, Inc. v. Hurst
96 A.D.3d 914 (Appellate Division of the Supreme Court of New York, 2012)
Marino v. Chester Union Free School District
859 F. Supp. 2d 566 (S.D. New York, 2012)
Troeller v. Klein
82 A.D.3d 513 (Appellate Division of the Supreme Court of New York, 2011)
Hartsdale Fire District v. Eastland Construction, Inc.
65 A.D.3d 1345 (Appellate Division of the Supreme Court of New York, 2009)
Power Cooling, Inc. v. Board of Education
48 A.D.3d 536 (Appellate Division of the Supreme Court of New York, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
39 A.D.3d 792, 835 N.Y.S.2d 630, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-construction-group-llc-v-bethpage-union-free-school-district-nyappdiv-2007.