CONSOLIDATED CONSTR. CO. v. Metal Bldg. Components, LP

961 So. 2d 820, 2007 WL 80799
CourtSupreme Court of Alabama
DecidedJanuary 12, 2007
Docket1031498
StatusPublished
Cited by5 cases

This text of 961 So. 2d 820 (CONSOLIDATED CONSTR. CO. v. Metal Bldg. Components, LP) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CONSOLIDATED CONSTR. CO. v. Metal Bldg. Components, LP, 961 So. 2d 820, 2007 WL 80799 (Ala. 2007).

Opinion

961 So.2d 820 (2007)

CONSOLIDATED CONSTRUCTION COMPANY OF ALABAMA and Hartford Accident and Indemnity Company
v.
METAL BUILDING COMPONENTS, L.P., d/b/a MBCI; David Sorrells; and Gregory M. Horne.

1031498.

Supreme Court of Alabama.

January 12, 2007.

Michael L. Fees and Allen L. Anderson of Fees & Burgess, P.C., Huntsville, for appellants.

Marc James Ayers of Bradley Arant Rose & White, LLP, Birmingham; and Greg Revera of Bradley Arant Rose & White, LLP, Huntsville, for appellee Metal Building Components, Inc., d/b/a MBCI.

Larry S. Logsdon of Wallace, Jordan, Ratliff & Brandt, L.L.C., Birmingham, for appellees David Sorrells and Gregory M. Horne.

PER CURIAM.

AFFIRMED. NO OPINION.

See Rule 53(a)(1) and (a)(2)(F), Ala. R.App. P.

*821 NABERS, C.J., and SEE, LYONS, WOODALL, STUART, SMITH, and PARKER, JJ., concur.

HARWOOD and BOLIN, JJ., concur specially.

BOLIN, Justice (concurring specially).

Consolidated Construction Company of Alabama ("Consolidated") and Hartford Accident and Indemnity Company ("Hartford") appeal from the trial court's judgment enforcing a claim against Consolidated's public-works-payment bond. Consolidated also appeals from the trial court's judgment in favor of David Sorrells and Gregory M. Horne on its third-party claims against Sorrells and Horne arising out of their ownership interest and operation of D.S. Sorrells & Company.

In 2000, Consolidated entered into a contract with the Madison County Board of Education ("the Board") to build the Endeavor Elementary School. In accordance with the requirements of § 39-1-1, Ala.Code 1975, Consolidated supplied a payment bond in favor of the Board with Hartford as the surety.[1] Subsequently, Consolidated executed a purchase order with D.S. Sorrells & Company. D.S. Sorrells then ordered materials from Metal Building Components, L.P., d/b/a MBCI.

D.S. Sorrells paid each invoice owed MBCI until April 2001 when a check from D.S. Sorrells to MBCI in the amount of $58,507.72 was returned due to insufficient funds. No payment was made by D.S. Sorrells to cover the returned check. D.S. Sorrells ceased doing business shortly thereafter. At the time D.S. Sorrells ceased operations, it owed MBCI $65,221.78.

On October 31, 2001, MBCI made a demand for payment on the bond against Consolidated and Hartford pursuant to § 39-1-1. No payment was made on the demand, and on December 27, 2001, MBCI sued D.S. Sorrells, Consolidated, and Hartford to recover amounts owed for the materials that had been furnished by MBCI. Specifically, MBCI alleged (1) that D.S. Sorrells was liable for breach of contract; (2) that D.S. Sorrells and Consolidated were liable under the Alabama Prompt Payment Act, § 8-29-1 et seq., Ala.Code 1975; (3) that Consolidated was liable to pay the amounts owed MBCI from its payment bond pursuant to § 39-1-1; and (4) that Hartford was also liable to pay MBCI on the payment bond pursuant to § 39-1-1. Consolidated filed a third-party complaint against D.S. Sorrells and David Sorrells and Greg Horne, as *822 officers, directors, and shareholders of D.S. Sorrells. In its third-party complaint, Consolidated asserted claims of fraudulent misrepresentation and fraudulent suppression against Sorrells and Horne[2] and Consolidated sought to pierce D.S. Sorrells's corporate veil. We note that Sorrells was president of D.S. Sorrells and Horne was the secretary/treasurer.

MBCI moved for a summary judgment. Consolidated and Hartford filed motions for a partial summary judgment, asking the trial court to dismiss all of MBCI's claim asserted under § 39-1-1. In support of their argument, Consolidated and Hartford argued that § 39-1-1 does not allow a materialman to a materialman to recover on a public-works-payment bond. Consolidated also filed a motion for a partial summary judgment with regard to MBCI's claims asserted under § 8-29-1 et seq., Ala.Code 1975. Sorrells and Horne each moved for a summary judgment with regard to Consolidated's third-party claims against them.

The trial court denied MBCI's motion for a summary judgment and denied Consolidated's and Hartford's motions for a partial summary judgment as to MBCI's claims under § 39-1-1. The trial court granted Consolidated's motion for a partial summary judgment with regard to MBCI's claims under § 8-29-1. Also, the trial court denied Sorrells's and Horne's summary-judgment motions.

Following a bench trial, the trial court entered a final judgment on May 14, 2004. In its order, the trial court found that MBCI had not been paid for materials it furnished for use in the construction of the Endeavor Elementary School building. The court concluded that § 39-1-1 allows a materialman to a materialman to recover on a public-works-payment bond. The court also determined that even if § 39-1-1 did not protect a materialman to a materialman, D.S. Sorrells was a subcontractor to Consolidated; therefore, MBCI, as a materialman to a subcontractor, would be able to recover from Consolidated and Hartford under their interpretation of § 39-1-1. The court found that Sorrells and Horne had made material misrepresentations to Consolidated, but the court concluded that Consolidated had failed to present sufficient evidence to pierce the corporate veil.

The trial court ordered: (1) that MBCI recover $109,997.02 in principal and attorney fees from D.S. Sorrells, Consolidated, and Hartford (jointly and severally); (2) that MBCI recover $23,446.12 in interest from D.S. Sorrells; (3) that MBCI recover $9,542.04 in interest from Consolidated and Hartford; (4) that Consolidated recover from D.S. Sorrells any amounts Consolidated *823 pays MBCI in satisfaction of the final judgment. The trial court also entered a final judgment in favor of Sorrells and Horne. Consolidated and Hartford appeal.

The trial court correctly entered a judgment in favor of MBCI as to MBCI's right to recover under the payment bond supplied by Consolidated in favor of the Board with Hartford as the surety. However, I write specially to address the trial court's judgment in favor of Sorrells and Horne on Consolidated's fraud claim based on the insufficiency of the evidence to warrant piercing the corporate veil.

The trial court expressly found that there was insufficient evidence to pierce the corporate veil, and it entered a judgment in favor of Sorrells and Horne on Consolidated's claims. However, the court found that Sorrells and Horne individually made material misrepresentations and concealed information on behalf of D.S. Sorrells. The trial court stated in its judgment:

"D.S. Sorrells, acting through David Sorrells and Greg Horne, implicitly and expressly represented to Consolidated, on a repeated basis in early 2000 and up to the trial of this civil action, that D.S. Sorrells intended to pay, and had in fact paid, all monies owed by it to MBCI for materials supplied for use in the Endeavor Elementary construction project. This is a material representation that D.S. Sorrells knew to be false.
"When Consolidated became aware that MBCI was claiming it had not been fully paid by D.S. Sorrells for materials used in connection with the Endeavor Elementary construction project, D.S. Sorrells implicitly and expressly represented to Consolidated that the claim was a mere misunderstanding or accounting error. This is a material representation that D.S. Sorrells knew to be false.
"In the summer of 2001 D.S. Sorrells repeatedly represented to Consolidated that any misallocations of monies which should have been applied to D.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ASTRAZENECA LP v. State
41 So. 3d 15 (Supreme Court of Alabama, 2009)
Penmont, LLC v. Blue Ridge Piedmont, LLC
607 F. Supp. 2d 1266 (M.D. Alabama, 2009)
Ex Parte Novartis Pharmaceuticals Corp.
991 So. 2d 1263 (Supreme Court of Alabama, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
961 So. 2d 820, 2007 WL 80799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-constr-co-v-metal-bldg-components-lp-ala-2007.