Consigli & Associates, LLC v. Maplewood Senior Living, LLC

CourtDistrict Court, S.D. New York
DecidedFebruary 8, 2023
Docket1:20-cv-07712
StatusUnknown

This text of Consigli & Associates, LLC v. Maplewood Senior Living, LLC (Consigli & Associates, LLC v. Maplewood Senior Living, LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consigli & Associates, LLC v. Maplewood Senior Living, LLC, (S.D.N.Y. 2023).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK --- --------------------------------------------------------- X : CONSIGLI & ASSOCIATES, LLC, : Plaintiff, : : 20 Civ. 7712 (LGS) -against- : : OPINION AND ORDER MAPLEWOOD SENIOR LIVING, LLC, : Defendants. : ------------------------------------------------------------ X

LORNA G. SCHOFIELD, District Judge: This action is a contract dispute between the parties to a construction contract -- Plaintiff Consigli & Associates, LLC (“Consigli”) as the construction manager and Defendant Maplewood Senior Living, LLC (“MSL”) as the owner’s agent. Plaintiff sues for breach of contract and wrongful termination. MSL counterclaims for breach of contract, violation of sections 39 and 39-A of the New York Lien Law, breach of the implied covenant of good faith and fair dealing and fraud. The parties cross-move for partial summary judgment. For the reasons below, both motions are granted in part and denied in part. BACKGROUND The following undisputed facts are drawn from the parties’ Rule 56.1 statements and other submissions on this motion. On the respective cross-motions, all reasonable inferences are drawn in favor of the non-moving party. See N.Y. State Teamsters Conf. Pension & Ret. Fund v. C & S Wholesale Grocers, Inc., 24 F.4th 163, 170 (2d Cir. 2022). The parties’ contract, dated February 22, 2017 (the “Contract”), consists of a modified American Institute of Architects (“AIA”) A133-2009 Standard Form (“A-133”) and AIA A201- 2007 General Conditions (“General Conditions”). On November 28, 2017, MSL and Consigli executed a Guaranteed Maximum Price (“GMP”) Amendment. The GMP is based upon a list of drawings and specifications that are incorporated in the Contract. The GMP Amendment set an original Substantial Completion deadline of October 18, 2019, which was then extended at least to December 4, 2019. Handel Architects, LLP served as the Project Architect (the “Architect”). During the course of the Project, the Architect issued many additional sketches and several addenda that

changed the design of the project. Many of those changes were issued as part of Addendum 6, dated April 19, 2018. The project was not completed by the Substantial Completion date in the Contract and, beginning in March 2020, was impacted further by the COVID-19 pandemic. As set forth in greater detail below, the Contract contained detailed provisions describing the scope of the “Work” for which Consigli would be paid and the procedures for changing that Scope and the timeline. Several disputes arose between MSL and Consigli over whether Consigli is entitled to compensation for additional work. On March 23, 2021, MSL purported to terminate the Contract for cause and took steps to complete the project without Consigli. STANDARD

Summary judgment is appropriate where the record establishes that “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). “An issue of fact is genuine if the evidence is such that a reasonable [finder of fact] could return a verdict for the nonmoving party.” Frost v. N.Y.C. Police Dep’t, 980 F.3d 231, 242 (2d Cir. 2020) (quoting SCR Joint Venture L.P. v. Warshawsky, 559 F.3d 133, 137 (2d Cir. 2009)). “Only disputes over facts that might affect the outcome of the suit under the governing law will properly preclude the entry of summary judgment.” Anderson v. Liberty Lobby Inc., 477 U.S. 242, 248 (1986); accord Saleem v. Corp. Transp. Grp., 854 F.3d 131, 148 (2d Cir. 2017). In evaluating a motion for summary judgment, a court must “construe the record evidence in the light most favorable to the non-moving party and draw all reasonable inferences in its favor.” Torcivia v. Suffolk Cty., 17 F.4th 342, 354 (2d Cir. 2021). When the movant properly supports its motion with evidentiary materials, the opposing party must establish a genuine issue of fact by citing to particular parts of materials in the record. See Fed. R. Civ. P. 56(c)(1)(A). “A party opposing summary judgment normally does not show the existence of a

genuine issue of fact to be tried merely by making assertions that are based on speculation or are conclusory.” S. Katzman Produce Inc. v. Yadid, 999 F.3d 867, 877 (2d Cir. 2021). DISCUSSION A. MSL’s Motion for Summary Judgment on Counts Two and Four of the SAC Counts Two and Four of the Second Amended and Supplemental Complaint (“SAC”) allege breach of contract based on MSL’s failure to pay Consigli. Count Two alleges that MSL failed to pay for (1) five change order requests (“CRs”) relating to extra and additional work, (2) seven CRs relating to delays and schedule impacts and (3) two other categories of costs incurred by subcontractors. Count Four alleges that MSL failed to pay for six CRs relating to work that MSL directed Consigli to perform on an adjacent building. MSL seeks summary judgment,

arguing that it has no obligation to make these payments because Consigli failed to comply with contractual notice requirements and waived its claims in other agreements. MSL’s motion is granted in part and denied in part. 1. Relevant Contract Provisions Article 7 of the General Conditions, titled “Changes in the Work,” specifies the ways in which the “Work” can change -- including by “Change Order” (“CO”) or “Construction Change Directive” (“CCD”). A CO requires agreement by both the Contractor (Consigli) and Owner’s Agent (MSL). A CCD can be issued without Consigli’s prior agreement. Unless Consigli notifies MSL within ten days after receipt of a CCD of a disagreement with its terms -- such as provisions for additional time or compensation -- Consigli is deemed to have agreed with those terms. Article 7 contemplates that “Supplemental Drawings and Specifications” (“Supplemental Drawings”) may be issued during the project. Consigli is obliged to review such Supplemental Drawings and, if it believes any item constitutes a “Scope Change,” (1) within ten days of receipt, notify MSL and the Architect, and (2) within twenty-one days of receipt, provide a cost

breakdown. When MSL receives notice, it has three options: (1) modify the Supplemental Drawings; (2) if it agrees with the Scope Change, enter into a CO or (3) if it disagrees and does not wish to modify the design, proceed to a dispute process laid out in Article 15 of the General Conditions. Consigli can seek additional payment for Supplemental Drawings only if they give rise to a Scope Change. If Consigli fails to comply with the notice requirement, it waives its right to claim a Scope Change. If the parties execute a CO, “[u]nless expressly reserved . . . [it] shall constitute a final settlement of all matters relating to the change in the Work which is the subject of the” CO. In addition to those provisions governing Supplemental Drawings, section 7.6.3

provides that Consigli cannot claim extra cost or time for any changes to the work unless Consigli gives prompt notice and receives a written order to proceed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
SCR Joint Venture L.P. v. Warshawsky
559 F.3d 133 (Second Circuit, 2009)
Minelli Constr. Co., Inc. v. WDF Inc.
134 A.D.3d 508 (Appellate Division of the Supreme Court of New York, 2015)
Frost v. New York City Police Department
980 F.3d 231 (Second Circuit, 2020)
Zhi Eric Zhang v. ABC Corp.
2021 NY Slip Op 03213 (Appellate Division of the Supreme Court of New York, 2021)
S. Katzman Produce Inc. v. Yadid
999 F.3d 867 (Second Circuit, 2021)
Torcivia v. Suffolk County, New York
17 F.4th 342 (Second Circuit, 2021)
MHR Capital Partners LP v. Presstek, Inc.
912 N.E.2d 43 (New York Court of Appeals, 2009)
Biotronik A.G. v. Conor Medsystems Ireland, Ltd.
11 N.E.3d 676 (New York Court of Appeals, 2014)
Jana L. v. West 129th Street Realty Corp.
22 A.D.3d 274 (Appellate Division of the Supreme Court of New York, 2005)
845 UN Limited Partnership v. Flour City Architectural Metals, Inc.
28 A.D.3d 271 (Appellate Division of the Supreme Court of New York, 2006)
Kocourek v. Booz Allen Hamilton Inc.
114 A.D.3d 567 (Appellate Division of the Supreme Court of New York, 2014)
NY State Teamsters v. C&S Wholesale Grocers
24 F.4th 163 (Second Circuit, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
Consigli & Associates, LLC v. Maplewood Senior Living, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consigli-associates-llc-v-maplewood-senior-living-llc-nysd-2023.