Conservancy, Inc. v. A. Vernon Allen Builder, Inc.

580 So. 2d 772, 1991 WL 83097
CourtDistrict Court of Appeal of Florida
DecidedMarch 29, 1991
Docket90-520
StatusPublished
Cited by3 cases

This text of 580 So. 2d 772 (Conservancy, Inc. v. A. Vernon Allen Builder, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conservancy, Inc. v. A. Vernon Allen Builder, Inc., 580 So. 2d 772, 1991 WL 83097 (Fla. Ct. App. 1991).

Opinion

580 So.2d 772 (1991)

The CONSERVANCY, INC. and Florida Audubon Society, Appellants,
v.
A. VERNON ALLEN BUILDER, INC. and State of Florida Department of Environmental Regulation, Appellees.

No. 90-520.

District Court of Appeal of Florida, First District.

March 29, 1991.
Rehearing Denied May 7, 1991.

*773 Joseph Z. Fleming, of Joseph Z. Fleming, P.A., Miami, for appellants.

Terry E. Lewis and Kevin S. Hennessy, of Messer, Vickers, Caparello, French, Madsen & Lewis, P.A., West Palm Beach, for appellee/A. Vernon Allen Builder, Inc.

Carol A. Forthman, Deputy General Counsel, for appellee/Florida Department of Environmental Regulation.

WIGGINTON, Judge.

The Conservancy, Inc. and Florida Audubon Society bring this appeal from the final order of the Department of Environmental Regulation granting a dredge and fill permit. Although we affirm a number of the issues raised on appeal, we must on one point reverse and remand for further proceedings.

In April 1988, appellee A. Vernon Allen Builder, Inc. (Builder) submitted its application to the Department of Environmental Regulation (DER or Department) for a dredge and fill permit. The permit application was for the excavation and re-disposition of approximately 1,155 cubic yards of material within Gordon Pass in order to imbed a sewage pipeline system along the bottom of Gordon Pass extending from the City of Naples mainland south to Keewaydin (Key) Island. The pipeline will be part of a sewage force-main system which will provide sewer service to present and future development on Key Island.

*774 Gordon Pass is located between the City of Naples and Key Island, a coastal barrier island designated by the United States Congress as a unit to be protected within the coastal barrier resource system pursuant to the provisions of the Coastal Barrier Resources Act (CBRA). The purposes of such congressional designation include prohibiting federal funding of any projects that would enable development on designated coastal barrier islands due to their importance to the estuarine system and public health and safety. Key Island forms the southern shore of Gordon Pass. As a coastal barrier island, Key Island enables the existence and functioning of the estuarine system to the west and serves as a buffer to wave action from the Gulf of Mexico. As numerous witnesses and experts confirmed before the hearing officer, Key Island is a dynamic, evolving and inseparable part of the estuarine system. In turn, the estuarine system is dependent upon and cannot be separated from Key Island for its existence.

The northern tip of Key Island is within the city limits of Naples and contains the Keewaydin Club, a vacation resort long ago developed for an existing small private club. Its existence is so limited that its impact was determined to be minimal by Congress so as to require that Key Island be designated as an undeveloped coastal barrier island entitled to protection pursuant to the CBRA. The proposed subaqueous sewage pipeline is intended to serve the club's existing facilities which presently utilize septic tanks, as well as a proposed new development of 75 exclusive estate homes intended to be built by Builder.

An appraisal was done by the DER local office leading to suggested modifications to the permit application. The modifications were ultimately incorporated into the design of the system and on August 31, 1988, DER issued a Notice of Intent to issue the dredge and fill permit. The permit imposes several conditions upon the construction and operation of the pipeline to ensure minimal disturbance of the area in compliance with Department rules. Further changes to the permit were proposed by the hearing officer in her recommended order and ultimately adopted by DER in the final order.

Appellants were granted a hearing to contest the intended agency action. Prior to the hearing, both Builder and DER persuaded the hearing officer, over appellants' objections, to exclude certain evidence during the hearing relating to the so-called "cumulative impact" that the project would have on Keewaydin Island. Appellants emphasized that Key Island, as a coastal barrier island, is inseparable from and necessary for protection of the national and state estuarine system. Further, they argued that the subaqueous pipeline for untreated sewage clearly enabled the proposed development on the island of 75 estate homes which, in turn, would produce cumulative impacts that would be environmentally devastating to the coastal barrier system.

The hearing officer rejected appellants' request to introduce most of the evidence regarding these cumulative impacts. However, certain evidence was received through the testimony of DER experts who had reviewed, in conjunction with the Department of Community Affairs, the comprehensive plan for the City of Naples, including the area in issue. In doing so, these experts also reviewed the proposed residential development on Key Island but testified that, in their opinion, because of the negative environmental impact of the development, the permit in issue enabling such development should be denied.

Appellants have raised four issues on appeal challenging DER's decision to grant the dredge and fill permit. We affirm Points I, III and IV with little comment other than to say that under the decisions in Hopwood v. Department of Environmental Regulation, 402 So.2d 1296 (Fla. 1st DCA 1981), and Manatee County v. Department of Environmental Regulation, 429 So.2d 360 (Fla. 1st DCA 1983), petition for rev. denied, 438 So.2d 833 (Fla. 1983), the complained of modifications to the project as suggested by the hearing officer and incorporated in the final order did not amount to a denial of due process. Instead, the more troublesome *775 issue involves the hearing officer's exclusion of the proffered evidence regarding the cumulative impacts of the permitted project. It is on this point that we must reverse and remand for further proceedings.

The issue of "cumulative impacts" was initially indirectly addressed in the Department's Notice of Intent, wherein the Builder was advised to make other permit applications before constructing the sewer pipelines if it felt that denial of the other permits would result in unnecessary expenditure of resources. Specifically, in paragraph 10 of the Notice, the Department made the following observations:

The Department is aware that the proposed subaqueous sewer force main is intended to service a planned seventy-five (75) unit single family development and that the completion of this development will include plans to expand an existing docking facility and construct bridges and boardwalks over jurisdictional wetlands. The applicant is advised that dredge and fill permits will be needed for such work as well as any other planned dredging or filling in jurisdictional wetlands. The Department's action in proposing to permit the construction of the force main shall not be construed as an endorsement or opinion of the permittability of any such additional projects and it is understood by the applicant that any such permit applications may be denied in full or in part. Given this, it is suggested that the applicant make such applications before constructing the force main if it is felt that the denial of these anticipated projects would result in the unnecessary expenditure of resources in constructing the force main.

Thereafter, the hearing officer ruled on the matter in regard to appellees' motion to strike appellants' amended petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deep Lagoon Boat Club, Ltd. v. Sheridan
784 So. 2d 1140 (District Court of Appeal of Florida, 2001)
Friends of Matanzas, Inc. v. Department of Environmental Protection
729 So. 2d 437 (District Court of Appeal of Florida, 1999)
Florida Power Corp. v. STATE, DEPT. OF ENV. REG.
605 So. 2d 149 (District Court of Appeal of Florida, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
580 So. 2d 772, 1991 WL 83097, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conservancy-inc-v-a-vernon-allen-builder-inc-fladistctapp-1991.