Conselyea v. . Blanchard

8 N.E. 490, 103 N.Y. 222, 2 N.Y. St. Rep. 738, 1886 N.Y. LEXIS 1051
CourtNew York Court of Appeals
DecidedOctober 5, 1886
StatusPublished
Cited by10 cases

This text of 8 N.E. 490 (Conselyea v. . Blanchard) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conselyea v. . Blanchard, 8 N.E. 490, 103 N.Y. 222, 2 N.Y. St. Rep. 738, 1886 N.Y. LEXIS 1051 (N.Y. 1886).

Opinion

Earl, J.

The only claim the plaintiffs have to share in the fund in controversy and to have priority therein is based upon the two orders taken by their testator, for the first of which he paid $850, and for the second of which he paid $595. There was no evidence that the money thus advanced bore any rela *227 tian to, or had any connection with, the bridge or its erection, and the plaintiffs claim priority of payment solely on the ground that these orders are prior in date to the other orders.

Blanchard & O’Rourke base their claim to priority of payment upon facts found by the judge at Special Term as follows: They were the owners of a certain patent for the construction of bridge turn-tables, which were known and designated as “ Blanchard & O’Rourke patent turn-tables,” and as such patentees they had the exclusive right to construct and use such turn-tables; and Swift & Van Aken by their contract with the two counties were bound to furnish such a turn-table. For the purpose of performing their contract with the counties, Swift & Van Aken entered into contract with Blanchard & O’Rourke to furnish, supply and erect one of these turn-tables for the price of $2,500, $2,000 of which was to be paid when the turn-table should be complete, in running order and accepted as such, and the balance of $500, when the bridge should be accepted by the counties. By the contract of Swift & Van Aken with the counties it was provided that the work on the bridge should be commenced within ten days and finished within sixty days after the completion and delivery of the central pier, and if there was delay beyond that time, they agreed to pay as liquidated damages to the counties, the sum of $50 per day for every day of such delay, the amount to be retained from the contract-price stipulated to be paid by the counties. By the contract between Swift & Van Aken, and Blanchard & O’Rourke, it was provided that the turn-table should be completed within the time specified for the completion of the bridge. After the making of the two contracts mentioned, and in or about the month of July, 1881, the central pier for the bridge having been completed and delivered, Swift & Van Aken entered upon the performance of their contract, and in that month, after doing some work thereon, they refused to proceed further under their contract until a payment was made to them which they were not entitled to, as the engineer in charge on behalf of the counties refused to certify therefor; whereupon the joint committee of the *228 two counties, duly authorized thereto, took entire charge of the supervision of the work, and the engineer ceased to act further; and the committee on the twenty-first day of July, for the purpose of inducing Swift & Yan Aken to proceed with the work, although nothing was actually due them under the contract, reported a resolution to the boards of supervisors of the two counties recommending a payment of $3,000 to them on their contract, which sum was paid on such recommendation by the counties. On the reporting of such recommendation by the committee, Swift & Yan Aken resumed work on the bridge, and on the passage of the resolution to make the payment recommended they again ceased work. When such sum was paid to them they again resumed work on the bridge, and immediately thereafter again ceased work and left the bridge unfinished and thereafter absolutely failed and refused to proceed any further with the work or to complete their contract. Blanchard & O’Bourke duly proceeded with the erection of the turn-table and performed their contract in respect thereto, so far as the condition of the work to be performed by Swift & Yan Aken permitted; but they were unable to fully complete and erect the turn-table for the reason that Swift & Yan Aken had not, when they ceased to work, progressed to an extent sufficient to enable them to complete the same or further proceed therewith. Although they repeatedly demanded and required Swift & Yan Aken to proceed with the erection of the bridge so as to permit them to proceed with the erection of the turn-table, they continually refused so to do, and in violation of their contract, hindered, delayed and prevented them from finishing the turn-table and completing their contract. Swift & Yan Aken were thus in default from July to October, 1881, and Blanchard & O’Bourke were not, at any time, in default. In the month of October, while Swift & Yan Aken were thus in default, there was a meeting of the joint committee at which Swift & Yan Aken refused further to perform their contract and declared their inability so to do, and their intention absolutely to abandon the performance thereof. Whereupon Blanchard & O’Bourke notified the committee that they would not *229 proceed with the building of the turn table, unless payment of the amount which they were to receive therefor should be assumed by the committee and thus secured to them; and they being then and there in possession of the work and material already used by them in the building of the turn-table so far as the same had progressed, declared their intention, unless so secured, to remove the materials and not to furnish the counties with the turntable or to permit the construction or use thereof. Whereupon the committee having full power and authority so to do requested them to erect the turn-table, and promised and agreed that on the completion thereof the counties would pay them the sum of $2,500; and then and there, with the consent and concurrence of Swift & Van Aken, that sum was reserved, set apart, assigned and appropriated from the amount still unpaid to Swift & Van Aken under their contract with the counties to and for the payment of Blanchard & O’Rourke on the completion of the turn-table; and the boards of supervisors of the two counties thereafter duly ratified the agreement. Blanchard & O’Rourke, relying upon the agreement thereupon agreed to proceed with the work, and did accordingly thereafter finish and complete the same. Swift & Van Aken did not thereafter proceed with the contract with the counties and no money ever fell due to them thereunder except as hereinafter stated. Blanchard & O’Rourke with the consent of Swift & Van Aken finished the contract of the latter with the counties and permitted them to have the ultimate benefit thereof and to receive the amount unpaid on the contract after first deducting the amount of $2,500 so appropriated, assigned and set apart for paying for the turn-table. On the 29th day of December, 1881, the committee, in pursuance of the agreement to pay Blanchard & O’Rourke for the turn-table on the completion thereof, and for the purpose of carrying out the agreement, duly certified to the boards of supervisors that the sum of $5,000 was due to Swift & Van Aken on account of their contract, one-half thereof payable by each county; that $1,250 of the same was to be paid by each county to Blanchard & O’Rourke before any other sum should be paid to any other *230 person, and that the balance, $750, was to be paid by each county to Swift & Van Aken. The boards of supervisors severally adopted resolutions of the same tenor and effect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spengler v. Stiles-Tull Lumber Co.
48 So. 966 (Mississippi Supreme Court, 1909)
In re Cramond
145 F. 966 (N.D. New York, 1906)
Cogan v. Conover Manufacturing Co.
60 A. 408 (New Jersey Court of Chancery, 1905)
Weeks v. City of New York
42 Misc. 436 (New York Supreme Court, 1904)
Hay v. Peterson
34 L.R.A. 581 (Wyoming Supreme Court, 1896)
Mason Stable Co. v. Lewis
16 Misc. 359 (Appellate Terms of the Supreme Court of New York, 1896)
Pappenheim v. Metropolitan Elevated Railway Co.
7 N.Y.S. 679 (Superior Court of New York, 1889)
Graves v. Graves
5 Silv. Sup. 539 (New York Supreme Court, 1889)
Conselyea v. Blanchard
12 N.Y. St. Rep. 872 (New York Supreme Court, 1887)
Jemison v. Citizens' Savings Bank
51 N.Y. Sup. Ct. 412 (New York Supreme Court, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
8 N.E. 490, 103 N.Y. 222, 2 N.Y. St. Rep. 738, 1886 N.Y. LEXIS 1051, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conselyea-v-blanchard-ny-1886.