Conquistador Dorado Joint Venture

CourtArmed Services Board of Contract Appeals
DecidedJune 12, 2020
DocketASBCA No. 60042, 60475, 60620, 60942, 60943, 61111, 61733, 61952
StatusPublished

This text of Conquistador Dorado Joint Venture (Conquistador Dorado Joint Venture) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conquistador Dorado Joint Venture, (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) Conquistador Dorado Joint Venture ) ASBCA Nos. 60042, 60475, 60620 ) 60942, 60943, 61111 ) 61733, 61952 Under Contract No. N69450-08-C-1267 )

APPEARANCES FOR THE APPELLANT: Stephen B. Hurlbut, Esq. John M. Neary, Esq. Daniel R. Miktus, Esq. Akerman LLP Washington, DC

Andrew Schwartz, Esq. Joseph M. Goldstein, Esq. Shutts & Bowen, LLP Ft. Lauderdale, FL

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney David M. Marquez, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE THRASHER ON THE GOVERNMENT’S PARTIAL MOTION FOR SUMMARY JUDGEMENT AND PARTIAL MOTION TO DISMISS

These appeals arise from a Navy contract awarded to Conquistador Dorado Joint Venture (CDJV or appellant) for the clearing of vegetation and improvement of drainage conditions at Naval Air Station Key West (NAS Key West). The Navy (government) moves for partial summary judgment on Counts I and II of CDJV’s Consolidated Complaint 1 (ASBCA Nos. 60042 and 60475) (gov’t mot. at 1).

1 On April 10, 2017, the Board docketed CDJV’s appeal of the denial of its June 20, 2016 third Claim as ASBCA No. 61111, and consolidated the six pending appeals as ASBCA Nos. 60042, 60475, 60620, 60942, 60943 and 61111. On August 7, 2017, the Board denied CDJV’s Motion for Order Requiring Respondent to File the Complaint in ASBCA Nos. 60942 and 60943, thereby requiring CDJV to file a consolidated complaint in all six appeals. Count I (ASBCA No. 60042) involves CDJV’s claim for additional costs from encountering a Differing Site Condition (DSC) during performance, and Count II (ASBCA No. 60475) is CDJV’s associated claim for delays resulting from the DSC (cons. compl. at 14-18). Additionally, the Navy moves to dismiss, or in the alternative stay, Count III of the consolidated Complaint (ASBCA No. 60620) alleging the claim submitted in this appeal was an improper undisputed invoice depriving the board of jurisdiction, and that the appeal is duplicative and should be dismissed. (Gov’t mot. at 1) For the reasons stated below, we deny the government’s motions.

MOTIONS FOR PARTIAL SUMMARY JUDGMENT, ASBCA Nos. 60042 and 60475

STATEMENT OF FACTS (SOF) FOR THE PURPOSES OF THESE MOTIONS

Solicitation

1. The Navy issued Solicitation No. N69450-08-R-1267 (solicitation) on March 26, 2008, to bring Naval Air Station Key West (NAS Key West) into compliance with relevant airfield safety requirements (ASBCA Nos. 60042, 60475 R4, tab 1 at GOV0001, 3 at GOV0165). Although the solicitation contemplated a fixed price, design-build contract for the clearing of vegetation and improvement of drainage conditions at NAS Key West, the Navy’s partial motion for summary judgment primarily rests upon the vegetation work elements generally described throughout the contract documents as “vegetation conversion” (see, e.g., ASBCA Nos. 60042, 60475 R4, tab 3 at GOV0191). Vegetation conversion includes “vegetation removal, excavation of soft materials and sediment, filling areas to adjust grades, providing special planting soil, planting new vegetation, and maintaining the new vegetation during the establishment/warranty period” (id. at ¶ 4.4). The solicitation sets forth a defined area of NAS Key West that is subject to vegetation conversion, and divides that area into 23 units referred to as “Vegetation Conversion Work Areas,” also known as “VCAs” (id. at ¶ 4.4.1). For each VCA, the solicitation specifies one or more “Treatment Types” that describes the work to be performed in that VCA (ASBCA Nos. 60042, 60475 R4, tab 3 at GOV0193, 0195).

Geotechnical Survey

2. The solicitation provided the offerors with a topographic survey prepared in June 2007, but required the contractor to perform additional topographical surveys of the project site and obtain additional soil borings, testing, or other geotechnical information necessary to provide a final design; specifically, warning offerors the geotechnical information is “intended for proposal [] and preliminary design only.” The solicitation also provided that the contractor “shall perform, at his expense, such subsurface exploration, investigation, testing, and analysis as his Designer of Recorder

2 deems necessary for the design and construction of the project facilities.” (ASBCA Nos. 60042, 60475 R4, tab 3 at GOV0213)

Contract Award

3. On September 3, 2008, the Navy awarded Conquistador Dorado JV (CDJV) Contract No. N69450-08-C-1267 (the “Contract”) for the design and construction of Phase I (CLINs 0001-0010) of the Airfield Vegetation Construction Project at NAS Key West (ASBCA Nos. 60042, 60475 R4, tab 9 at GOV0549-95). CLIN 0001 required that the contractor “[p]rovide the complete design efforts for all project work included in the RFP on and adjacent to Boca Chica Field including field investigations, data collection, preparing design submittals, responding to review comments, and finalizing designs” (id. at GOV0551).

4. The contract incorporated Federal Acquisition Regulation (FAR) 52.236-2, DIFFERING SITE CONDITIONS (Apr 1984) (the DSC clause) and FAR 52.243-4, CHANGES (JUN 2007) (id. at GOV0578-79).

CDJV’s April 28, 2011, First Request for Equitable Adjustment

5. On April 28, 2011, CDJV submitted a request for equitable adjustment (First REA) alleging a DSC as a result of encountering conditions in the project area that resulted in an increase in volume of backfill required to complete the project in excess of the geotechnical information provided in the RFP (ASBCA Nos. 60042, 60475 R4, tab 13 at GOV0991). Upon consideration, the Navy determined that it was not necessary to excavate as much material as originally contemplated by the RFP. The RFP called for the complete removal of soft, compressible soils, and placement of backfill. (ASBCA Nos. 60042, 60475 R4, tab 16 at GOV1017) After discussions with CDJV regarding the REA, the Navy decided to revise Part 3 of Subsection 4.4.3 of the Statement of Work-specifically the descriptions of Treatment Types C and D. (Id. at GOV1017-1019) Pursuant to the revised treatment types, CDJV would be required to excavate and backfill only as necessary to support the weight of vegetation maintenance equipment (not aircraft as originally required) (id. at GOV1019). As a result of the REA, the parties negotiated an equitable adjustment rather than pay the cost of excavating and backfilling the additional volume of material identified by CDJV in the REA.

CDJV’s Revised REA Proposal with New Excavation Specifications

6. By email on May 23, 2011, Contract Specialist Gloria Colon forwarded the Navy’s SOW revisions to CDJV directing CDJV to submit a revised REA package based upon the Navy’s revisions by May 25, 2011(ASBCA Nos. 60042,

3 60475 R4, tab 16 at GOV 1017-19). In response, CDJV submitted its revised REA proposal by email dated May 26, 2011 (ASBCA Nos. 60042, 60475 R4, tab 17 at GOV1021-1033). The revised REA proposal specifically included the revised excavation specifications, i.e., the revised descriptions for Treatment Types C and D which the Government had provided CDJV via email on May 23, 2011 (id. at GOV1025).

Modification No. P00010 and Government Final Design

7. It was not until a year later, on May 3, 2012, that the Navy executed bilateral Modification No. P00010, responding to CDJV’s April 28, 2011, REA, incorporating CDJV’s revised REA proposal dated May 26, 2011 and increasing the contract amount (ASBCA Nos. 60042, 60475 R4, tab 10 at GOV0719-21). The modification’s purpose was stated as:

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Conquistador Dorado Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conquistador-dorado-joint-venture-asbca-2020.