Connecticut Investment Casting Corp. v. Made-Rite Tool Co.

416 N.E.2d 966, 382 Mass. 603, 31 U.C.C. Rep. Serv. (West) 531, 1981 Mass. LEXIS 1099
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 17, 1981
StatusPublished
Cited by4 cases

This text of 416 N.E.2d 966 (Connecticut Investment Casting Corp. v. Made-Rite Tool Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Connecticut Investment Casting Corp. v. Made-Rite Tool Co., 416 N.E.2d 966, 382 Mass. 603, 31 U.C.C. Rep. Serv. (West) 531, 1981 Mass. LEXIS 1099 (Mass. 1981).

Opinion

Hennessey, C.J.

Connecticut Investment Casting Corporation (Casting) brought an action in the Springfield Division of the District Court Department to recover the contract price of $5,170.81 for barrel latches sold and delivered to Made-Rite Tool Co., Inc. (Made-Rite). Made-Rite filed a counterclaim for $50,000, alleging that it had been damaged by Casting’s breach of contract. The District Court judge found for Made-Rite on Casting’s complaint and for Casting on Made-Rite’s counterclaim. Casting, *604 claiming to have been aggrieved by the denial of certain requests for rulings, requested a report to the Appellate Division of the District Court Department, which found no prejudicial error and dismissed the report. From the decision of the Appellate Division Casting now appeals to this court pursuant to G. L. c. 231, § 109.

In the written report, which states that it contains all the evidence material to the questions reported, the District Court judge summarized the evidence as follows. Casting and Made-Rite had an agreement under which Casting was to supply 1,600 barrel latches by January 27,1976. Casting shipped seventy-four parts on January 21, 1976, 228 parts on February 27, 1976, 623 parts on March 9, 1976, 629 parts on April 8, 1976, and seventy parts on May 14, 1976. Made-Rite introduced evidence that it needed the parts for a contract with the United States government. There was conflicting evidence of Casting’s awareness of the government contract. Made-Rite produced evidence that on January 28, 1976, the day after the due date of the contract with Casting, Made-Rite telephoned Casting and stated that Casting had breached the contract but that Made-Rite would make every effort to obtain an extension on its contract with the government. Made-Rite managed to obtain several extensions on the latter contract but did not meet the final deadline of June 28, 1976. During the same period, Made-Rite had approximately forty other government contracts, six or seven of which were priority contracts. When Made-Rite missed the deadline of June 28, 1976, the government cancelled that contract, as a result of which Made-Rite lost the contract price and certain administrative expenses, and was assessed a penalty. Made-Rite was not able to resell the latches to the government or to use them itself. At the time of trial, all the latches were still in Made-Rite’s possession.

Made-Rite introduced evidence that some of the latches did not meet the contract specifications. Of the approximately 1,625 latches provided, Made-Rite returned 179 as nonconforming in early April of 1976; Casting reworked *605 164 of these and redelivered them on April 28,1976. An in-house inspection of eighty additional latches on April 26, 1976, revealed that seventeen (approximately twenty per cent) were nonconforming. Made-Rite decided not to return any more nonconforming latches to Casting for reworking, but rather to rework them itself.

Made-Rite offered evidence of numerous discussions with Casting, during which Made-Rite pressured Casting to deliver the latches and Casting responded that it was encountering unanticipated difficulties.

The District Court judge denied Casting’s requested rulings numbered 2 through 8, set forth in the margin, 1 and entered judgment for Made-Rite on Casting’s complaint. The judge found that Casting had broken the contract with Made-Rite in that “[t]he parts that were delivered were not in conformity with the specifications as given nor were they delivered on time.” The judge entered judgment for Casting on Made-Rite’s counterclaim for lost profits, finding that Casting neither knew nor should have known of Made-Rite’s contract with the government, and that in any *606 event Made-Rite’s alleged damages as a result of the loss of that contract were not the natural and probable consequences of Casting’s breach. 2

The Appellate Division treated the case as involving only questions of fact and found no prejudicial error. We conclude that the District Court judge erred in refusing to grant Casting’s requested ruling that Made-Rite, as a matter of law, had accepted the barrel latches.

1. Acceptance of latches by Made-Rite. The contract between Casting and Made-Rite is for the sale of goods and is governed by art. 2 of the Uniform Commercial Code. G. L. c. 106, § 2-102. Casting contends that Made-Rite, both by retaining the goods in spite of any nonconformity and by failing to make a proper rejection under § 2-602 (1), accepted the goods. G. L. c. 106, § 2-606 (1) (a) (b). 3 Under § 2-602 (l), 4 a buyer who does not intend to accept the goods delivered must give the seller timely notice of his rejection. Failure to do so constitutes acceptance of the goods by the buyer, as long as he has had a reasonable opportunity to inspect them. G. L. c. 106, § 2-606 (1) (b). See, e.g., Akron Brick & Block Co. v. Moniz Eng’r Co., 365 Mass. 92, 94 (1974).

*607 There is no evidence that Made-Rite ever notified Casting of any intention to reject the barrel latches. Made-Rite had a reasonable opportunity to inspect, and in fact did inspect, the latches in its possession in early April. Rather than rejecting them, however, Made-Rite sent back to Casting only those latches found to be nonconforming, which Casting reworked and redelivered. After Made-Rite inspected additional latches on April 26, it decided to rework any nonconforming parts itself. These actions by Made-Rite do not constitute rejection of the barrel latches. Nor can we accept Made-Rite’s contention that the “numerous conversations” with Casting constituted proper notice of rejection. On the contrary, the report of the District Court judge states that “[t]he substance of these conversations was that Defendant [Made-Rite] was pressuring Plaintiff [Casting] to deliver and Plaintiff was responding that it was encountering unanticipated difficulties.” Ry pressuring a seller to deliver, a buyer does not reject the goods delivered.

Made-Rite argues that, even if it accepted the goods, it subsequently revoked its acceptance as allowed by G. L. c. 106, § 2-608. 5 Revocation of acceptance is ineffective, however, unless the buyer notifies the seller within a reasonable time after the buyer discovers the ground for revocation. § 2-608 (2). There is no evidence that Made-Rite *608 ever revoked its acceptance within a reasonable time by notifying Casting, and Made-Rite points to nothing that could be construed as notice of revocation. Made-Rite did notify Casting of two breaches of the contract — the failure to meet the January 27, 1976, delivery date, and the failure to conform 179 latches to the contract specifications. Despite the late delivery, however, all but the 179 nonconforming latches were accepted by Made-Rite, and 164 of the latter were accepted after they had been reworked and redelivered by Casting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stigman v. Nickerson Enterprises, Inc.
2000 Mass. App. Div. 223 (Mass. Dist. Ct., App. Div., 2000)
Delano Growers' Cooperative Winery v. Supreme Wine Co.
473 N.E.2d 1066 (Massachusetts Supreme Judicial Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
416 N.E.2d 966, 382 Mass. 603, 31 U.C.C. Rep. Serv. (West) 531, 1981 Mass. LEXIS 1099, Counsel Stack Legal Research, https://law.counselstack.com/opinion/connecticut-investment-casting-corp-v-made-rite-tool-co-mass-1981.