Conn Acoustics, Inc. v. Xhema Construction, Inc.

870 A.2d 1178, 88 Conn. App. 741, 2005 Conn. App. LEXIS 166
CourtConnecticut Appellate Court
DecidedMay 3, 2005
DocketAC 25088
StatusPublished
Cited by6 cases

This text of 870 A.2d 1178 (Conn Acoustics, Inc. v. Xhema Construction, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conn Acoustics, Inc. v. Xhema Construction, Inc., 870 A.2d 1178, 88 Conn. App. 741, 2005 Conn. App. LEXIS 166 (Colo. Ct. App. 2005).

Opinion

Opinion

FLYNN, J.

The defendant, Xhema Construction, Inc., appeals from the judgment of the trial court awarding the plaintiff, Conn Acoustics, Inc., $39,093 in damages, plus costs and interest, on its breach of contract complaint. The court also found in favor of the plaintiff on the defendant’s counterclaim. On appeal, the defendant claims that the court improperly applied the parol evidence rule to exclude evidence of the circumstances surrounding the making of the parties’ agreement and concluded that the parties’ unsigned written proposal, with change orders, was a fully integrated agreement without admitting evidence as to the intent of the parties. We agree and remand the case for further eviden-tiary proceedings.

The record reveals the following facts. The defendant, a general contractor, hired the plaintiff, and several other subcontractors, to perform work in connection with the installation of an indoor lap pool in the basement of a Greenwich home. Problems arose with the vapor barrier over the pool because the taping of holes in the barrier was not completed properly. In contracting with the defendant, the plaintiff had sent by facsimile a proposal concerning the work that it was being hired to complete. The parties agree that the plaintiff was to install walls and a ceiling in the basement of a home, which would house an indoor lap pool, beneath a metal deck. The parties disagree as to *743 whether the two page proposal for $66,628, dated May 14, 1998, submitted by the plaintiff to the trial court as exhibit one, along with two change orders, accurately stated the complete terms of the parties’ contract. Of particular significance is the exclusion of “taping” that was contained on page two of this proposal, as well as the provision that stated that the proposal was based on “various conversations and design changes.” No signed copy of this proposal or any contract was submitted into evidence by either party, and the plaintiff stated that a signed copy could not be located in its files. The defendant was not able to locate any record of any contract or proposal concerning this entire project.

In addition to the proposal submitted as exhibit one, the plaintiff submitted two change orders to the court. The first change order, dated August 19,1998, and referencing project number W-2544, stated that the original contract sum was $66,628. It then listed three changes to the contract totaling $33,936. The total revised contract amount was stated to be $100,564. The first change order was signed at the bottom by representatives of both parties. The second change order, dated March 26, 1999, also referencing project number W-2544, added two more changes that amounted to $3329. Unlike the first change order, this change order did not state the original contract price or the new total, but it was signed at the bottom by representatives of both parties.

The plaintiff also tendered, as exhibit four, a notarized document entitled “application and certificate for payment,” dated November 24, 1998, which stated (1) the original contract sum of $66,628, (2) the net change orders of $33,936, (3) the contract sum as of that date of $100,564, (4) the total completed and stored to date of $72,000, (5) a 10 percent retainage amount of $7200, (6) the total earned, less retainage, of $64,800, (7) less previous certificates for payment of $48,780.90, (8) the *744 current payment due of $16,019.10 and (9) the balance to finish, plus retainage, of $35,764. The document was signed by the plaintiff and a notary public. Further, the document notes an approval of apayment of $16,019.10, evidenced by the initials of Pierre Georgetti, an employee of the defendant and the project manager for the lap pool project, on behalf of the defendant on December 4, 1996.

The final “application and certificate for payment,” dated March 30, 1999, was submitted as exhibit five. Similar in many respects to the November 24, 1998 application, it stated (1) the original contract sum of $66,628, (2) the net change orders of $37,265, (3) the contract sum as of that date of $103,893, (4) the total completed and stored to date of $103,893, (5) a 10 percent retainage amount of $10,389.30, (6) the total earned, less retainage, of $93,503.70, (7) less previous certificates for payment of $64,800, (8) the current payment due of $28,703.70 and (9) the balance to finish, plus aretainage of $10,389.30. The document was signed only by the plaintiff and a notary, but payment was neither tendered nor approved by the defendant pursuant to this application.

The plaintiff filed suit seeking to recoup the balance of $39,093 allegedly due on the contract. The defendant, although acknowledging the existence of “a contract” in its answer, denied that it owed the plaintiff this amount. Additionally, the defendant filed a counterclaim alleging that it suffered damages because of the plaintiffs failure to perform its work in a good and workmanlike manner. On the basis of this evidence, the court found that the May 14, 1998 proposal, in combination with the two change orders, embodied the entire agreement of the parties, and it rendered judgment in favor of the plaintiff on both its complaint and on the defendant’s counterclaim.

*745 The defendant submits that our standard of review on its claim of an improper application of the parol evidence rule is plenary. The plaintiff argues that it is a mixed standard of review, clearly erroneous as to the factual issue of the intent of the parties and plenary as to whether the court properly applied the parol evidence rule. We agree with the defendant.

“Ordinarily, [o]n appeal, the trial court’s rulings on the admissibility of evidence are accorded great deference. . . . Rulings on such matters will be disturbed only upon a showing of clear abuse of discretion. . . . Because the parol evidence rule is not an exclusionary rule of evidence, however, but a rule of substantive contract law . . . the [defendant’s] claim involves a question of law to which we afford plenary review.” (Internal quotation marks omitted.) Alstom Power, Inc. v. Balcke-Durr, Inc., 269 Conn. 599, 609, 849 A.2d 804 (2004).

“The parol evidence rule does not apply ... if the written contract is not completely integrated.” (Internal quotation marks omitted.) Benvenuti Oil Co. v. Foss Consultants, Inc., 64 Conn. App. 723, 727, 781 A.2d 435 (2001). As a threshold matter, therefore, a court must conduct an inquiry and take evidence as to whether there is an integrated agreement. See Suburban Sanitation Service, Inc. v. Millstein, 19 Conn. App. 283, 286-87, 562 A.2d 551 (1989). “If the evidence . . . does not indicate that the writing is intended as an integration, i.e., ‘a final expression of one or more terms of an agreement’; 2 Restatement (Second), Contracts § 209 (1) [1981]; then ‘the agreement is said to be “uninte-grated,” and the parol evidence rule does not apply.’ E. Farnsworth, Contracts [1982] § 7.3, p. 452.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sullo Investments, LLC c. Moreau
Connecticut Appellate Court, 2014
Poeppel v. Lester
2013 S.D. 17 (South Dakota Supreme Court, 2013)
Atelier Constantin Popescu, LLC v. JC Corp.
49 A.3d 1003 (Connecticut Appellate Court, 2012)
Heaven v. Timber Hill, LLC
900 A.2d 560 (Connecticut Appellate Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
870 A.2d 1178, 88 Conn. App. 741, 2005 Conn. App. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conn-acoustics-inc-v-xhema-construction-inc-connappct-2005.