Conklin v. R. P. & J. H. Staats Co.

161 F. 897, 88 C.C.A. 593, 1908 U.S. App. LEXIS 4403
Court of Appeals for the Third Circuit·Decided May 18, 1908·No. No. 24·Published·Cited by 5 cases

Opinion

BUFFINGTON, Circuit Judge.

In the court below the appellants, Conklin and others, filed a libel against the R. P. & J. IT. Staats Company, a corporation, to recover damages to their scow Sarah. On final hearing the court dismissed the libel. Its opinion is reported in 155 Fed. 818, where the facts are fully stated. Thereupon the libelant took this appeal.

The Staats Company was engaged in rebuilding piers of the North German Company at Hoboken, which had been destroyed by fire. It was a large undertaking, and took six years, from 1900 onward, for its completion. The fire destroyed the superstructure and left the stumps of piles standing. Such piles as showed above water were removed by the Staats Company, but the dredging and removal of the stumps below low water was done by a third company. The piers were relocated and were being constructed by the Staats Company at the time of the injury complained of. In such reconstruction they had been for some time furnished by the libelant with scow loads of broken stone. On December 13, 1901, the Staats Company wrote libelant as follows:

“Confirming our conversation to-day with reference to the delivery to us of several scow loads of broken stone for use in our work at Hoboken during [898] the winter, we understand that you will send us five scow loads of such stone, containing about 3,000 cubic yards in all, and will deliver the same alongside the North German Lloyd docks at Hoboken within the next few days, allowing them to remain there during the winter months; also that we may use the stone from these scows as occasion requires, without charge for demurrage to us until such time as a scow is taken from the lot for our use, and demur-rage shall only accrue on that scow after sufficient time has elapsed in which to unload the scow at a minimum rate of 75 yards per day (Sundas's and holidays excepted). The scows while lying in the slip to be solely at your risk, and you will provide such men as may be needed to look after them, and when a scow shall have been unloaded by us you will remove it from the premises.”

In accordance therewith the Sarah, with four other scows laden with stone, was towed to the north side of pier No. 2 on December 29, 1901, where she lay until January 3, 1902, when the Staats Company desired her space to bring in a barge of other material, and requested the tug of the North German Lloyd Company, which did the towing for all parties, to remove her. During this interval the scows were treated as undelivered, for two of them were removed by libelants and others substituted for them without consulting the Staats Company, and there was no proof to show that in requesting the removal of the Sarah the Staats Company directed at what point she should be moored, or accepted her in any such way as under the foregoing letter thereafter subjected itself to demurrage. The tug moved the scow to the south side of pier No. 1, where she was tied by the scow’s crew. The tide was then ebbing rapidly, aided by a strong westerly wind, which had been blowing for two days, and which caused the tide at the time of the accident to drop from 18 to 24 inches lower than usual. Pier No. 1 was then being constructed by the Staats Company. On its south side and at some distance therefrom there was piling extending parallel to the pier and through an opening in which the scow, as well as other craft, were warped to moor along the pier. What followed is stated in this extract from the opinion of the court below:

“The scow was moored on the south side of pier 1, breast off five feet, and was tied with two breast and two spring lines. The tide was ebbing rapidly, aided by a strong westerly wind, which had been blowing for two days, and which had caused the tide at the time of the accident to fall from 18 inches to 2 feet lower than usual. After the scow had laid at her mooring about three-quarters of an hour, she began to list away from the pier. Her captain sounded the water around her with a 16-foot pole, to see if the water were shallow; but he found no bottom. He then went down into the hold and heard water beginning to trickle slowly in. While he waited on the scow a pile broke through her bottom, and she careened over gradually to the port side. He then went up the pier to look for help, and when he came back, a l'ew minutes later, the scow lay bottom up, with one corner on the pier and the other in the water. He tried to ease up the lines to see if she would slide off, but she did not. AVhile she lay there, the watchman says he saw a jagged hole in her bottom, 16 or 17 inches wide by about 2 feet in length, the hole was about one-third of her length from the bow, and about 2 feet from her starboard side, which had lain next to the pier. Subsequent examination of the scow at a dry dock, to which she was taken for repairs, showed that the injury to her was in ail probability caused by her bottom coming in contact with a sunken pile, which, owing to the weight of her load, was forced through and rammed up in her hold as far as it could go, about 9 feet, and then, when the scow capsized by the spilling of its load, was broken off, and a piece thereof, about 8 feet in length, left in her hold in a reclining' posi[899] tion between the stanchions and cross-pieces. The portion of the pile found in the scow was a little less than Is) inches in diameter, about 9 feet long, and was in good condition, although it had a few barnacles on it. At one end appeared what is called a ‘battered break,’ as though a heavy weight had rested on it. This break had an old appearance, vrliUe at the other end was a new and longer break. It is apparent from the evidence that the accident happened by reason of the fact that the scow had been moored over a hidden pile: but how or when the pile came there is-not disclosed.”

Free access — add to your briefcase to read the full text and ask questions with AI

Conklin v. R. P. & J. H. Staats Co., 161 F. 897, 88 C.C.A. 593, 1908 U.S. App. LEXIS 4403 (3d Cir. 1908).

161 F. 897 (Conklin v. R. P. & J. H. Staats Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Connecticut Fire Ins. v. Smith & Richards Lumber Co.
28 F. Supp. 770 (D. New Jersey, 1939)
Arundel Sand & Gravel Co. v. United States
66 Ct. Cl. 90 (Court of Claims, 1928)
Neville v. Morrison Coal & Coke Co.
211 A.D. 282 (Appellate Division of the Supreme Court of New York, 1925)
Kenny v. Balbach Smelting & Refining Co.
6 F.2d 671 (S.D. New York, 1923)