Congressional Hotel Corp. v. Mervis Diamond Corp.

28 A.3d 75, 200 Md. App. 489, 2011 Md. App. LEXIS 109
CourtCourt of Special Appeals of Maryland
DecidedSeptember 2, 2011
Docket1980, September Term, 2009
StatusPublished
Cited by13 cases

This text of 28 A.3d 75 (Congressional Hotel Corp. v. Mervis Diamond Corp.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Congressional Hotel Corp. v. Mervis Diamond Corp., 28 A.3d 75, 200 Md. App. 489, 2011 Md. App. LEXIS 109 (Md. Ct. App. 2011).

Opinion

KRAUSER, C.J.

Congressional Hotel Corporation (“CHC”) appeals from an order of the Circuit Court for Montgomery County, awarding attorneys’ fees and costs to Mervis Diamond Corporation (“Mervis”), pursuant to a provision of the parties’ lease agreement (the “Lease”), for two bench trials and the first of two previous appeals, 1 resulting from CHC’s breach of the parties’ lease. The circuit court erred, CHC contends, by including, in that award, attorneys’ fees and costs relating to Mervis’s motion to reconsider, filed in this Court, following the first appeal and attorneys’ fees and costs relating to the second trial when it was, according to CHC, Mervis’s “errors and misconduct” that created the need for that trial. We disagree and affirm.

Background

This is the third time that this case has been before us. In outlining the factual basis of this appeal, we need proceed no further than to recite the facts and circumstances, as set out in our opinion in CHC’s first appeal, Congressional Hotel Corp. v. Mervis Diamond Corp., No. 1848, Sept. Term 2006 (filed December 12, 2007) (“Congressional /”), as we did in our opinion in CHC’s second appeal, Congressional Hotel Corp. v. Mervis Diamond Corp., No. 1075, Sept. Term 2009, slip op. at 5 (filed June 17, 2010) (“Congressional II ”). They are:

On July 6, 2004, Mervis and CHC executed the Lease for approximately 3,282 square feet of retail space (the “Premises”). The Premises are attached to a Ramada Inn Hotel in the Congressional Village shopping center in Rockville.
*493 Under Section 1.02(.j) of the Lease, Mervis was required to take possession of the Premises “five (5) days after Tenant’s receipt of Landlord’s notice to Tenant that the Premises [are] ready for Tenant’s use and that Landlord has completed the work listed on Exhibit B (the ‘Landlord’s Work’).” It is estimated, in Section 1.01(q) of the Lease, that CHC would deliver Notice of Possession by February 1, 2005.
... Prior to performing the Landlord’s Work, CHC was required to obtain a building permit from the City of Rockville.
Section 2.04 of the Lease describes certain rights of CHC and Mervis related to CHC’s failure to deliver Notice of Possession by the Estimated Delivery Date of February 1, 2005....
Beginning in 2002, Congressional Village was being converted from a strip retail shopping center with surface parking into a mixed-use residential and commercial center with two elevated parking garages (Garages 1 & 2)....
The City of Rockville requested a plan ... for the development and construction of Congressional Village to ensure that adequate parking was maintained.... [The City] informed the involved parties that adequate parking would have to be maintained in order to obtain occupancy permits.
Garage 2, which was scheduled to be completed by mid-February of 2005, would provide retail parking for the retail tenants of Congressional Village and the Ramada Inn, including the Premises. During construction, Ronald Cohen[, a principal in CHC,] made a decision to delay the construction of Garage 2 and, instead, commence construction of [a building] in Congressional Village, which two of Congressional Village’s largest and most prominent tenants were to occupy. [The City] approved the deviation.
In December of 2004, when it was clear that ... Garage 2 [would not be completed] by mid-February, 2005, CHC *494 began to explore the possibility of razing the Ramada Inn and constructing high-rise condominiums in its place. At a meeting in January of 2005, CHC informed Mervis that it wished to terminate the Lease and, instead, build condominiums at Congressional Village. CHC presented Mervis with architectural renderings of the project and offered Mervis the opportunity to purchase retail space. Mervis declined the offer and insisted on CHC’s adherence to the Lease. CHC tried a second time, in the same month, to terminate the Lease. Mervis rejected that proposal as well.
On the Estimated Delivery Date of February 1, 2005, CHC had not yet obtained the required building permit from the City of Rockville to commence the Landlord’s Work. It received the permit on February 15, 2005, after Mervis and CHC had finalized the terms of the Landlord’s work.
On February 18, 2005, counsel for Mervis sent a letter to CHC, asking when CHC planned to commence the Landlord’s Work. CHC asked Mervis to meet and discuss its concerns, but Mervis declined. On March 1, 2005, counsel for Mervis sent a second letter, demanding information about CHC’s plans to commence the Landlord’s Work. When it did not hear from CHC, Mervis filed this action in the circuit court fifteen days later.
Mervis alleged that CHC had breached the Lease and requested specific performance and lost profit damages. Mervis also sought a preliminary injunction to prevent CHC from altering or razing the Premises.

Congressional I, No. 1848, Sept. Term 2006, slip op. at 3-10 (footnotes omitted).

The first trial of this matter, a bench trial, began on June 12, 2006, and ended, six days later, on June 16, 2006. The circuit court, on September 29, 2006, issued a memorandum opinion and order (the “2006 Lost-Profits Judgment”), finding that CHC had breached the Lease “in early-March, 2005”; *495 ordering specific performance of the Lease, as Mervis requested; and awarding $2,164,500, representing lost profits from March 15, 2005, to September 29, 2006, together with, as yet, undetermined attorneys’ fees and costs.

CHC thereafter noted its first appeal (Congressional I). While CHC’s appeal was pending, Mervis moved, in accordance with the court’s award of unspecified attorneys’ fees and costs, for an award of fees and costs for the first trial, reserving the right to petition for an additional award “should there be further litigation.” On December 19, 2006, the circuit court entered an order awarding Mervis $298,979.98 in attorneys’ fees and costs, consisting of fees and costs incurred up to and including the first trial (the “2006 Fee Award”).

Following that award, we issued our unreported opinion in Congressional I, vacating the 2006 Lost-Profits Judgment and holding that the circuit court had erred in calculating Mervis’s lost profits, by starting from the date that the “Landlord’s Work” was to have commenced, because it was “the failure to complete the Landlord’s Work, not the failure to commence that work, that constitute^] the breach.” Congressional I, No. 1848, Sept. Term 2006, slip op. at 18 (emphasis in original). Accordingly, we remanded the case for the circuit court to determine when that work should have been completed, leaving it to that court to determine “[w]hether a ‘mini-trial’ to determine such issues [was] necessary.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Maryland, 2026
Untitled Case
D. Maryland, 2026
Abanda v. OurBloc LLC
D. Maryland, 2025
Sugarloaf Alliance v. Frederick Cnty.
Court of Special Appeals of Maryland, 2025
Leatherbury v. Zohdi
D. Maryland, 2022
Wei v. Xu
D. Maryland, 2022
Estate of Castruccio v. Castruccio
233 A.3d 175 (Court of Special Appeals of Maryland, 2020)
Giant of Maryland, LLC v. Taylor
109 A.3d 142 (Court of Special Appeals of Maryland, 2015)
Ochse v. Henry
88 A.3d 773 (Court of Special Appeals of Maryland, 2014)
Carroll Independent Fuel Co. v. Washington Real Estate Investment Trust
32 A.3d 128 (Court of Special Appeals of Maryland, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
28 A.3d 75, 200 Md. App. 489, 2011 Md. App. LEXIS 109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/congressional-hotel-corp-v-mervis-diamond-corp-mdctspecapp-2011.