Coney Island Resorts, Inc. v. Giuliani
This text of 11 F. App'x 11 (Coney Island Resorts, Inc. v. Giuliani) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
SUMMARY ORDER
UPON DUE CONSIDERATION, it is ORDERED, ADJUDGED, AND DECREED that the judgment of the district court be and it hereby is AFFIRMED.
[12]*12I. BACKGROUND
Between 1984 and 1998, the City of New York (the “City”) and Coney Island Resorts, Inc., (“CIR”) engaged in lengthy negotiations aimed at developing Steeplechase Park in Brooklyn into an amusement park. Although a draft ground lease governing the development was negotiated, CIR’s inability to secure adequate financing for the project remained a sticking point throughout the negotiations, with the City refusing to enter into the lease before CIR acquired satisfactory financing. In view of this difficulty, the City granted CIR several extensions on City-imposed deadlines for delivery of the lease. The first two extensions the City granted CIR contained -express language reflecting the City’s longstanding insistence that CIR procure financing, and stated that:
The procurement of financing by CIR in form and amount satisfactory to the City remains [in the second extension letter, “continues to remain”] as one of the conditions to execution and delivery of [the negotiated] ground lease.
Coney Island Resorts, Inc. v. Giuliani, 103 F.Supp.2d 645, 649 (E.D.N.Y.2000).
The last three extensions, however, did not expressly condition entry into the lease upon CIR’s procuring financing. Instead, these three extensions, and in particular the final extension, stated only that:
i. “As [a] condition to this extension, Coney Island Resorts (“CIR”) shall make a payment to the Economic Development Corporation (“EDC”) [of a specified amount by a specified deadline]”; and
ii. “in the event either CIR has failed to make the required payment within five business days of [a specified date] or has not executed or deliveved the Ground Lease by [a specified date], CIR shall have no authority, right, designation or interest of any kind with respect to [the land at issue].”
CIR now claims that the final extension letter created a contract under which the City agreed to enter into the ground lease provided only that CIR performed the acts specifically identified in that letter, i.e., paid the extension fee and delivered a signed copy of the ground lease to the City by the requisite dates. And CIR, although it did not procure financing, did make the extension payment and did deliver a signed copy of the lease to the City before the expiry of the final extension. Nevertheless, in 1999, the City abandoned the amusement park project and instead, and without CIR’s participation, constructed a baseball stadium. CIR claims that in doing so, the City deprived it of its contractual right to the lease, in violation of the Due Process, Contract, Takings, and Equal Protection Clauses, and also the Fourth Amendment, of the federal Constitution.1
The district court granted summary judgment in favor of the City. It did so principally by reading the financing condition into the final extension letter on the grounds that, under New York law, the formal and talismanic use of language is not required in contract drafting and that contracts should be read to reflect the clear intent of the parties that make them. See Coney Island Resorts, Inc., 103 F.Supp.2d at 654-55 (citing Archibald v. Panagoulopoulos, 233 N.Y. 478, 488-89, 135 N.E. 857 (1922); Wood v. Lucy, Lady Duff-Gordon, 222 N.Y. 88, 91, 118 N.E. 214 (1917)). The district court determined that no rational juror could reach any conclusion other than that the parties to the final extension letter intended to maintain [13]*13rather than abandon the financing condition that had so plainly dominated their earlier negotiations. Accordingly, the district court decided that CIR, which had not procured financing, enjoyed no contractual rights to the lease.
With the contract question decided in this way, the district court quickly dismissed the remainder of CIR’s claims. Thus, the district court reasoned that because CIR had no right to enter into the ground lease, it had neither a property right to which its Due Process claim might attach nor a contract right to which its Contract Clause claim might apply. Id. at 655. Finally, the district court decided that CIR’s remaining assertions — -involving claims (a) that the City’s actions constituted a regulatory taking of certain land CIR owned adjacent to Steeplechase Park,2 and (b) that the City ultimately rejected CIR’s development proposal because CIR’s president Horace Bullard is an African American, thereby violating CIR’s rights under the Equal Protection Clause of the Fourteenth Amendment— were straightforwardly meritless.
CIR now appeals.
II. DISCUSSION
We affirm the decision below for substantially the reasons given by the district court. In particular, we agree that CIR’s procurement of acceptable financing for the amusement park remained a condition to execution of the ground lease even under the final extension agreement and therefore that CIR, which never arranged financing, had no contractual right to enter into the lease.3
We find unpersuasive CIR’s main objection to this conclusion — that to read the financing-condition into the final extension agreement between the City and CIR violates the parol evidence rule since the condition did not appear in the writing memorializing that agreement. The New York State law of contracts has indeed adopted the parol evidence rule. See Cruden v. Bank of New York, 957 F.2d 961, 976 (2d Cir.1992). But even though, as a general matter, that rule forbids reference to oral agreements or other external evidence that vary the terms of an unambiguous writing, the rule “does not, however, apply where the written contract was not intended to embody the entire agreement between the parties,” Fogelson v. Rackfay Constr. Co., 300 N.Y. 334, 338, 90 N.E.2d 881 (1950). Thus “[i]n a case where the contract is existing and valid but incomplete, parol evidence is admissible to complete the writing provided that all the particulars, upon inspection, plainly are not present and the parol evidence sought to be introduced is not contradictory of the written agreement,” Smith v. Slocum, 71 A.D.2d 1058, 420 N.Y.S.2d 814, 814-15 (4th Dep’t 1979). Indeed, in Lady Duff-Gordon itself Judge Cardozo famously added a term to the contact there construed — involving a promise by one party to use [14]*14reasonable efforts to promote the other party’s products — that was not expressly contained in the writing.
The case at bar is plainly of the same sort: the final extension agreement nowhere states that it is fully integrated. Instead, it plainly reflects only a partial agreement to be interpreted against the backdrop of a long-term, ongoing negotiation and contractual relationship. The district court correctly determined that in light of this ongoing relationship, no rational juror could conclude anything other than that the City and CIR intended, in the final extension agreement, to maintain the financing condition.
III. CONCLUSION
We have reviewed all CIR’s remaining claims and find them to be without merit.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
11 F. App'x 11, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coney-island-resorts-inc-v-giuliani-ca2-2001.