Condict v. Grand Trunk Railway Company

54 N.Y. 500
CourtNew York Court of Appeals
DecidedSeptember 5, 1873
StatusPublished
Cited by37 cases

This text of 54 N.Y. 500 (Condict v. Grand Trunk Railway Company) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Condict v. Grand Trunk Railway Company, 54 N.Y. 500 (N.Y. 1873).

Opinion

Earl, C.

It is the duty of common carriers to transport property intrusted to them for carriage within a reasonable time, and they are responsible for damage caused by delays which are attributable to their fault or negligence. " ( Wibert v. The N. Y. & Erie R. R. Co., 12 N. Y., 245.) . That defendant could legally contract for carriage beyond the terminus of its road, is not disputed. (Quimby v. Vamderbilt, 17 N. Y., 306; Burtis v. The Buffalo & State-Line Railroad Co., 24 id., 269; Root v. The Great Western R. R. Co., 45 id., 524; Lamb v. Camden de Amboy R. R. & T. Co:, 46 id., 271.) In England it is held that a railroad company receiving goods marked for a particular place beyond its terminus, without expressly limiting its responsibility, undertakes prima facie to carry them to their destination, andisto be regarded as a carrier throughout the entire route. But in this and other States of the Union a different rule prevails. It is here held that, the receipt of goods marked for a place beyond the terminus of the carrier’s route does not import-a contract to carry them to their final destination. Such a contract will not be inferred from the simple address ' of the goods. There must be other facts arid circumstances sufficient to show a special contract. Here it was proved, by defendant’s general superintendent, that in its business it *503 contracted to carry goods to Chicago. From the terminus of its road, it used the Michigan Southern and the Michigan Central railroads, and its own line of steamers. These goods were addressed to the plaintiffs at Chicago, and the written agreement under which they were received by defendant specified that they were to be sent and delivered in Chicago for the tariff specified of sixty-four cents per 100 pounds for the whole distance. These facts, it seems to me, clearly show a special contract for the transportation of the goods to Chicago.

The next question to be determined is whether the delay in forwarding the goods from Sarnia was occasioned by any fault or neglect of the defendant. The defendant was a railroad carrier, and we must infer from all the facts in the case that its ordinaiy and usual mode of transportation to Chicago was by railroad. It seems that it had made some arrangement as to freight and the division thereof with the other roads, and that this arrangement had become unsatisfactory to those roads, and that, about two weeks before these goods were delivered to the defendant, those roads had refused to take any more goods from the defendant without an increase of the freight. This the defendant refused to accede to, and hence no goods were taken by them from the defendant. This state of things was known to the defendant when it made the contract for the carriage of plaintiffs’ goods. It knew that those roads would not take property from it for transportation at the old rates, and it also knew that it had inadequate facilities for transportation by water; and yet without giving the consignors notice of the difficulties, and knowing all the facts, it made the contract to carry to Chicago at sixty-four cents per 100 pounds. The goods reached the terminus of its road at Sarnia on the tenth day of November, and were consumed by fire in its depot on the sixteenth day of the same month. The goods were delayed from the tenth to the sixteenth because the defendant would not accede to the demand of the other roads as to the price to be charged for the carriage of freight. But there is no proof that the *504 demands made by those roads were unreasonable, or that they insisted upon charging more than a fair compensation. They refused to take the goods simply because the defendant refused to pay what they insisted upon as a proper charge. How can this circumstance discharge the defendant from its responsibility under its contract ? Knowing the obstacles to be encountered, it had agreed to carry the goods. It was not impossible for it to do so. The burden of the increased charge fell upon it, and in the fulfillment of its contract with the plaintiffs it should have borne that burden. A carrier cannot excuse his delay in forwarding goods on account simply of an increased expense, which is not unforeseen nor entirely unreasonable. Neither has the defendant excused its delay by showing that it forwarded goods from Sarnia by water as fast as its facilities enabled it to. If, under its contract, with the plaintiffs, it had the right. to transport the goods by water rather than by rail, it was bound to have adequate facilities for doing so. Its facilities for water transportation were so inadequate that no goods which had arrived at any time during ten days before the fun were transported in that way. Under such circumstances the defendant, with a knowledge of all the facts, could not make a contract for the transportation with reasonable .dispatch, and refuse the facilities for railroad transportation, rely upon the inadequate facilities for water transportation, and then claim immunity for the damage occasioned by the delay.

The defendant claims, however, that it is shielded from liability for the damage claimed by the fifth condition annexed to the contract, which provides that the responsibilities of the company will be considered to terminate when the goods have arrived at the place to be reached upon its railroad. This provision clearly had reference only to cases where the defendant had contracted to carry only to the terminus of its road, and could not apply where, as in this case, it had expressly contracted to carry beyond such terminus.

I, therefore, conclude that the defendant is responsible for the delay; and the only other question to be considered is, *505 whether the loss by fire was "in such sense a consequence of the delay as to impose any liability upon the defendant. There was a clause in the conditions annexed to the contract, that the defendant should not be responsible for damage occasioned by fire. There was a similar clause in the contract in the case of Lamb v. Camden & Amboy R. R. & T. Co. (46 N. Y., 271), and it was held' that such clause did not exonerate the carrier from a loss occasioned by fire, in case the fire resulted from its own negligence. So in this case, if the loss can be attributed to the fault or negligence of the defendant, it must be held liable. But it is claimed that the delay on the part of the defendant in the transportation of the goods, which exposed them to the fire, was the remote and not the proximate cause of the loss, and hence that the defendant cannot be held liable for the loss without violating the maxim causa próxima non remota spectatur. But the law is otherwise settled in this State. In Michaels v. New York Central Railroad Company (30 N. Y., 564), the defendant received at Albany, from the Hudson River Railroad Company, a box of goods to be transported to Rochester and delivered to the owners. Instead of forwarding the box immediately, it detained the same in its freight-house at Albany, to await the rendering of a bill for back charges by the Hudson River Railroad Company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wiener v. Compagnie Generale Transatlantique
61 F.2d 893 (Second Circuit, 1932)
The Malcolm Baxter, Jr.
277 U.S. 323 (Supreme Court, 1928)
Frawley v. Atchison, Topeka & Santa Fe Railroad
299 S.W. 93 (Missouri Court of Appeals, 1927)
Barnet v. . N.Y.C. H.R.R.R. Co.
118 N.E. 625 (New York Court of Appeals, 1918)
Barnet v. New York Central & Hudson River Railroad
222 N.Y. 195 (New York Court of Appeals, 1918)
Lord & Bushnell Co. v. Texas & New Orleans Railroad
134 S.W. 111 (Missouri Court of Appeals, 1911)
Gardiner v. New York Central & Hudson River Railroad
139 A.D. 17 (Appellate Division of the Supreme Court of New York, 1910)
Schwartz v. Panama Railroad Co.
103 P. 196 (California Supreme Court, 1909)
Allen & Gilbert-Ramaker Co. v. Canadian Pacific Railway Co.
84 P. 620 (Washington Supreme Court, 1906)
Hutchins v. . Pennsylvania R.R. Co.
73 N.E. 972 (New York Court of Appeals, 1905)
Bibb Broom Corn Co. v. Atchison, Topeka & Santa Fe Railway Co.
102 N.W. 709 (Supreme Court of Minnesota, 1905)
Lauterer v. Manhattan Ry. Co.
128 F. 540 (Second Circuit, 1904)
Tewes v. North German Lloyd Steamship Co.
42 Misc. 148 (New York Supreme Court, 1903)
Farnsworth v. New York Central & Hudson River Railroad
88 A.D. 320 (Appellate Division of the Supreme Court of New York, 1903)
Stillwater & Mechanicville Street Railway Co. v. Boston & Maine Railroad
72 A.D. 294 (Appellate Division of the Supreme Court of New York, 1902)
Hartley v. St. Louis, Keokuk & North Western Railroad
89 N.W. 88 (Supreme Court of Iowa, 1902)
Talcott v. . Wabash R.R. Co.
54 N.E. 1 (New York Court of Appeals, 1899)
Page v. Chicago, St. P. M. & O. Ry. Co.
64 N.W. 137 (South Dakota Supreme Court, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
54 N.Y. 500, Counsel Stack Legal Research, https://law.counselstack.com/opinion/condict-v-grand-trunk-railway-company-ny-1873.