Concrete Post-Tensioning v. Armco, Inc.

449 So. 2d 712, 1984 La. App. LEXIS 8571
CourtLouisiana Court of Appeal
DecidedApril 11, 1984
Docket83-584
StatusPublished
Cited by2 cases

This text of 449 So. 2d 712 (Concrete Post-Tensioning v. Armco, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Concrete Post-Tensioning v. Armco, Inc., 449 So. 2d 712, 1984 La. App. LEXIS 8571 (La. Ct. App. 1984).

Opinion

449 So.2d 712 (1984)

CONCRETE POST-TENSIONING, INC., Plaintiff-Appellant,
v.
ARMCO, INC., et al., Defendants-Appellees.

No. 83-584.

Court of Appeal of Louisiana, Third Circuit.

April 11, 1984.

*713 Porteus R. Burke, New Iberia, for plaintiff-appellant.

Sessions, Fishman, Rosenson, Boisfontaine & Nathan, Louis L. Galvis and Stephen Doody, New Orleans, Kenneth W. Cole, Lafayette, for defendants-appellees.

Before GUIDRY, FORET and CULPEPPER,[*] JJ.

GUIDRY, Judge.

On April 27, 1982, Concrete Post-Tensioning, Inc. (hereafter CPT) filed this suit asserting a claim for payment due and recognition of a laborer's lien and privilege under the Louisiana Private Works Act against Big D Contractors, Inc. (hereafter Big D) and Armco, Inc., Building Systems Division, (hereafter Armco). Armco answered by general denial, alternatively asserting a written waiver and release as a bar to plaintiff's claim against Armco and the enforcement of its lien and privilege. On the basis of this waiver and release, Armco filed a motion for summary judgment. After hearing, the trial judge granted the motion for summary judgment and dismissed Armco from the action. Plaintiff appeals.

The facts, as reflected by the record, are as follows. Armco was the general contractor on a construction project in New Iberia, Louisiana, known as the National Supply Company, New Iberia Center. As part of this project, Armco entered into a sub-contract with Big D to furnish all labor and materials to construct a foundation slab for a fabrication shop building which was to be erected. Big D thereafter entered into an oral agreement with CPT whereby CPT was to perform some of the construction work on this slab. Armco was not a party to this agreement. After completion of the work on the slab by Big D and CPT, Armco alleged that there were certain defects in the work which required correction. A dispute thereafter arose between Big D and CPT as to who was responsible for correcting the defects and the amount of money due by Big D to CPT for its services and materials. As a result of the dispute, Big D refused to pay CPT and CPT filed a lien against the aforesaid project. Thereafter, in accordance with the terms and conditions of the subcontract between Armco and Big D, Armco refused to make final payment to Big D until the dispute between Big D and CPT was settled and the lien was cancelled.

A series of meetings were then held in the offices of Armco, attended by L.J. Bishoff representing Armco; Dave Hall representing Big D; Leon Minvielle, III, counsel for Big D; and, Porteus R. Burke, counsel for CPT. On the basis of these negotiations, CPT and Big D entered into a written agreement. Under the terms of that agreement, the signatories, CPT and Big D, acknowledged their dispute and agreed to *714 mutually waive and release any and all liens against the project in consideration of the payment by Armco of the sum of $35,544.00 to Big D; payment by Big D of the sum of $26,071.00 to CPT; and, the deposit by Big D of the sum of $9,473.93 in a joint escrow account under the names of both appearers for corrective work. In the agreement, both appearers acknowledged and receipted for the payment by Armco. A copy of the agreement is annexed as Appendix I.

This agreement was executed on April 20, 1982 by CPT and Big D in return for which Big D delivered two checks to CPT's attorney, one in the amount of $26,071.00, and one in the amount of $9,473.93, the latter amount to be placed in escrow as aforestated. Receipt of payment in these amounts was acknowledged by CPT in the written agreement. On the same day, a representative of Big D then delivered to Armco the written agreement and obtained from Armco a check in the amount of $70,027.73, of which $35,544.00 was for the work on the slab. Big D negotiated Armco's check and actually received the sum of $70,027.73. On April 22, 1982, Big D issued a stop payment order on the two checks issued and delivered to CPT. Big D has not since made payment to CPT of the sums due CPT under the agreement. As a result, CPT refused to cancel its lien and filed this lawsuit.

The issue on appeal is whether the trial judge erred in granting defendant's motion for summary judgment. The trial judge granted the motion for summary judgment stating that there was no genuine issue of material fact and that Armco was entitled to judgment as a matter of law under the doctrine of equitable estoppel. We affirm.

In Industrial Sand and Abrasives, Inc. v. Louisville and Nashville Railroad Company, 427 So.2d 1152 at 1153 (La. 1983), the Supreme Court reiterated the following standards for reviewing a summary judgment:

"The sole purpose for the motion for summary judgment is to determine in advance of trial whether a genuine issue of material fact exists between the litigants. Miller v. East Ascension Tel. Co., 263 So.2d 360 (La.App. 1st Cir.), writs denied, 262 La. 1121, 266 So.2d 430 (1972); cf. Albatross Shipping Corp. v. Stewart, 326 F.2d 208 (5th Cir.1964); see also Kay v. Carter, 243 La. 1095, 150 So.2d 27 (1963); Comment, Development of Jurisprudence in Louisiana Relative to Summary Judgment Since 1960, 12 Loyola L.Rev. 128 (1965-66). The summary judgment procedure in Louisiana is set out, in La.C.C.P. art. 966 et seq. These provisions are based upon the Federal Rules of Civil Procedure and even though there has developed a substantial body of jurisprudence in the courts of this state regarding the motion for summary judgment, the prior jurisprudence of the federal courts pertaining to the proper use of this device remains helpful and persuasive. Roy & Roy v. Riddle, 187 So.2d 492 (La.App. 3rd Cir.), writs denied, 249 La. 724, 190 So.2d 236 (1966).
La.C.C.P. art. 966 provides that any party may move for a summary judgment at any time, and the mover is entitled to summary judgment in his favor "if the pleadings, depositions, answers to interrogatories, and admissions of file, together with the affidavits, if any, show that there is no genuine issue as to a material fact, and that the mover is entitled to judgment as a matter of law." Sanders v. Hercules Sheet Metal, Inc., 385 So.2d 772 (La.1980); cf. Fed. Rule Civ.Pro. 56. The burden is on the mover to show clearly that there is not a genuine issue of material fact in dispute, and any reasonable doubt as to the existence of a genuine issue of material fact must be resolved against the mover and in favor of trial on the merits. Thornhill v. Black, Sivalls & Bryson, 394 So.2d 1189 (La.1981); White v. Baker Manor Nursing Home, 400 So.2d 1168 (La.App. 1st Cir.), writs denied, 403 So.2d 68 (La.1982); cf. Erco Industries, Ltd. v. Seaboard Coast Line Railroad Co., 644 F.2d 424 (5th Cir.1981); Joplin v. Bias, 631 F.2d 1235 (5th Cir.1980).
*715 To satisfy this burden, the mover must meet a strict standard of showing that it is quite clear as to what is the truth and that there has been excluded any real doubt as to the existence of a genuine issue of material fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chalmers Corp. v. Carnell
479 So. 2d 990 (Louisiana Court of Appeal, 1985)
Green v. DeFelice
466 So. 2d 1373 (Louisiana Court of Appeal, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
449 So. 2d 712, 1984 La. App. LEXIS 8571, Counsel Stack Legal Research, https://law.counselstack.com/opinion/concrete-post-tensioning-v-armco-inc-lactapp-1984.