Concrete Materials Corporation, Inc. v. C.J. Mahan Construction Company

110 F.3d 63, 1997 U.S. App. LEXIS 11167, 1997 WL 151741
CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 28, 1997
Docket95-6657
StatusUnpublished
Cited by3 cases

This text of 110 F.3d 63 (Concrete Materials Corporation, Inc. v. C.J. Mahan Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Concrete Materials Corporation, Inc. v. C.J. Mahan Construction Company, 110 F.3d 63, 1997 U.S. App. LEXIS 11167, 1997 WL 151741 (6th Cir. 1997).

Opinion

110 F.3d 63

NOTICE: Sixth Circuit Rule 24(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Sixth Circuit.
CONCRETE MATERIALS CORPORATION, INC., Plaintiff-Appellee,
v.
C.J. MAHAN CONSTRUCTION COMPANY, Defendant-Appellant.

No. 95-6657.

United States Court of Appeals, Sixth Circuit.

March 28, 1997.

Before: LIVELY, MERRITT and DAUGHTREY, Circuit Judges.

PER CURIAM.

This appeal arises from a diversity action, based on contract, that resulted in a jury verdict in the plaintiff's favor. The defendant, now the appellant, contends that (1) the question of whether or not a contract existed between the parties should not have been submitted to the jury; (2) the district court erred in permitting the introduction of certain evidence concerning lost profits; (3) the court erred in excluding a defense witness; and (4) the award of pre-judgment interest was improperly calculated.

I. FACTUAL AND PROCEDURAL BACKGROUND

The relationship between the parties resulted from defendant C.J. Mahan Construction Company's successful bid on a $31 million bridge project on Interstate 75 in Kentucky and an offer by plaintiff Concrete Materials Corporation to provide the necessary concrete for the project. That written offer was made on October 21, 1993, and included the costs of the concrete and of the ice to cool it, as required by the state. It also provided for a 2 percent per month interest rate on overdue bills, for applicable sales taxes, and for hauling. Although no agreement was reached immediately, discussions continued between the two companies. After some negotiation, they came to an agreement as to the cost for the provision of the concrete itself for the project. This term of the agreement was documented in a letter from C. Jeffrey Mahan to Concrete Materials dated January 24, 1994.

Shortly thereafter, construction began and Concrete Materials provided the first load of concrete to Mahan Construction. A problem arose with the billing for this load. Concrete Materials included charges for the cost for ice set forth in the original quotation, $.18 per pound. Mahan Construction refused to pay this amount, claiming that this term was not included in their final agreement, threatening to terminate the business relationship unless the ice question could be settled, and refusing any further payments until the matter was resolved. This dispute continued for several months, Mahan Construction arguing that no agreement for ice had been made at all, and Concrete Materials arguing that their original quote held. In the end, no resolution was achieved, and Concrete Materials filed the present action in state court. It was removed to the United States District Court for the Eastern Division of Kentucky upon request of the defendant, Mahan Construction, due to the diversity of citizenship of the parties and to the fact that the amount in controversy was greater than $50,000.

In the district court below, a jury found that a contract had existed between Mahan Construction and Concrete Materials that included the quotations in the October offer, that Mahan Construction had breached the contract, and that Mahan Construction owed Concrete Materials a total of $307,734.43 in damages ($87,561.81 for work already done under the contract and owed on Mahan's open account with Concrete Materials, and $220,172.62 for breach of the contract). The court entered judgment in this amount against the defendant. After the trial, Concrete Materials made a motion for pre-judgment interest on the open account portion of the damages, which was granted, thereby increasing the total award to $342,747.63. This appeal followed.

II. DISCUSSION

A. Submission of the Contract Dispute to the Jury

Mahan Construction claims on appeal that the contract question in this case should not have been submitted to the jury, because there was no dispute as to the terms of the contract. Under Kentucky law, if the terms of a contract are unambiguous, there is no question of fact for the jury. Hunter v. Wehr Constructors, Inc., 875 S.W.2d 899, 901 (Ct.App.Ky.1993). Instead, the court should enforce the contract as a matter of law. Id. Whether or not a contract existed between the parties, however, is a question of fact for the jury. Id. We review de novo a trial court's determination of the absence or presence of ambiguity, because that determination presents a question of law. Id.; see also University Hills, Inc. v. Patton, 427 F.2d 1094, 1099 (6th Cir.1970).

Mahan Construction argues that the January 24, 1994, letter that it sent to Concrete Materials contained all the provisions of the contract and was clear on its face. Because this contract was unambiguous, the defendant contends, the trial judge erred as a matter of law in submitting the question to the jury at all. This argument ignores Concrete Materials's asserted interpretation of the factual situation: that its October offer was accepted by Mahan Construction, with changes made only to the price for the concrete itself and all other provisions remaining in place.

We conclude that Mahan Construction cannot prevail in its insistence that the contract provisions were unambiguous as a matter of law, because the plaintiff's interpretation of the situation is also plausible under the applicable state law. In Kentucky, it is possible for a contract to be formed "in any manner sufficient to show agreement ... even though the moment of its making is undetermined," Ky.Rev.Stat.Ann. § 355.2-204 (Michie 1996), and for additional terms to be submitted as part of the acceptance of an offer. Id. § 355.2-207. Concrete Materials has offered evidence sufficient to support a jury finding that the January letter from Mahan was an acceptance of the earlier offer and that it did not contain terms about the ice because those terms had been previously determined by the communications from Concrete Materials to Mahan in October and remained unchanged.1 Because the existence of a contract was ambiguous, and the terms thereof were certainly ambiguous, the district court properly submitted the factual determination on this issue to the jury.

B. Evidence of Lost Profits

Prior to trial, the parties in this action engaged in discovery. Concrete Materials submitted initial disclosures, as required by Fed.R.Civ.P. 26, including their computation of the damages they claimed. Additionally, the plaintiff submitted responses to the defendant's Interrogatories and Requests for Documents. Although some of these responses could arguably be considered incomplete, and one response included an objection to producing certain documents, the defendant made no effort to gain more information through a motion to compel or a court order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Pfizer Inc.
265 F.R.D. 278 (M.D. Tennessee, 2010)
Heyward v. Wilkinson
27 F. App'x 539 (Sixth Circuit, 2001)
Fitz, Inc. v. Ralph Wilson Plastics Co.
174 F.R.D. 587 (D. New Jersey, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
110 F.3d 63, 1997 U.S. App. LEXIS 11167, 1997 WL 151741, Counsel Stack Legal Research, https://law.counselstack.com/opinion/concrete-materials-corporation-inc-v-cj-mahan-construction-company-ca6-1997.