Concra v. International Fidelity Insurance

860 F. Supp. 13, 1994 U.S. Dist. LEXIS 11233, 1994 WL 423443
CourtDistrict Court, N.D. New York
DecidedAugust 9, 1994
Docket6:92-cv-01198
StatusPublished
Cited by1 cases

This text of 860 F. Supp. 13 (Concra v. International Fidelity Insurance) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Concra v. International Fidelity Insurance, 860 F. Supp. 13, 1994 U.S. Dist. LEXIS 11233, 1994 WL 423443 (N.D.N.Y. 1994).

Opinion

MEMORANDUM-DECISION and ORDER

HURD, United States Magistrate Judge.

I. INTRODUCTION.

Defendant International Fidelity Insurance Company (“IFIC”) moves for partial summary judgment on its counterclaim against plaintiff for the undisbursed balance of the subject construction contract, and to strike plaintiffs damage claims as being unsupported by objective evidence. Plaintiff, Anthony R. Concra, cross-moves for an order awarding him loss of rental income and other alleged monetary losses caused by IFIC’s alleged contract default.

II. FACTS.

This action arises out of a performance bond issued by IFIC as surety; Capitol Valley Contractors, Inc. (“Capitol Valley”) as principal; and plaintiff as an obligee. In November 1989, plaintiff contracted with Capitol Valley to construct a two story building in Hudson, New York. Plaintiff, who leases property from the City of Hudson Industrial Development Agency, received his funding for the project through defendant Hudson City Savings Bank. On or around November 2, 1989, IFIC issued performance and payment bonds on behalf of Capitol Valley to assure Capitol Valley’s performance of the construction contract. Pursuant to an agreement dated February 15,1990, between plaintiff and Morris Associates, the predecessor-in-interest to defendant Crawford & Associates, Morris agreed to act as project engineer in connection with the construction project.

Capitol Valley commenced construction in March 1990, but defaulted on the project’s construction in December 1990. 1 By agreement entitled Surety Takeover Agreement dated May 9, 1991, IFIC undertook the completion of the construction contract. IFIC then retained Sam Greco Construction to complete the construction, and upon certification by the project engineer, the project was allegedly completed on August 15, 1991. Plaintiff currently sublets occupancy of the building to the Columbia County Department of Social Services. On December 2, 1991, IFIC requested payment in full. Plaintiff refused payment because there were several mechanic’s liens against the property. IFIC removed all liens against the property by the end of September 1992. No payment on the contract balance has been paid.

Plaintiff alleges that payment is not forthcoming because of alleged substantial defects *15 in the project’s construction. Specifically, plaintiff alleges that IFIC failed to secure completion of the project, and left a building which did not conform to the contract plans and specifications, was not built in accordance with the New York Building Code, and contains substantial defects.

III. SUMMARY JUDGMENT.

A motion for summary judgment may be granted only when the moving party carries its burden of showing the absence of a genuine issue of material fact. Fed.R.Civ.P. 56; Goldman, Antonetti Ferraiuoli, Axtmayer & Hertell, Partnership v. Medfit Int'l Inc., 982 F.2d 686, 689 (1st Cir.1993); Thompson v. Gjivoje, 896 F.2d 716, 720 (2d Cir.1990) (citations omitted). “Ambiguities or inferences to be drawn from the facts must be viewed in a light most favorable to the party opposing the summary judgment motion.” Project Release v. Prevost, 722 F.2d 960, 968 (2d Cir.1983). In other words, a motion for summary judgment pursuant to Fed.R.Civ.P. 56 shall be granted only “when the pleadings, evidence obtained through discovery, and affidavits show that there is no genuine issue as to any material fact, and that the moving party is entitled to summary judgment as a matter of law.” Lang v. Retirement Living Pub. Co., 949 F.2d 576, 580 (2d Cir.1991). Therefore, “summary judgment will not lie if the dispute about a material fact is ‘genuine,’ that is, if the evidence is such that a reasonable jury could return a verdict for the non-moving party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986).

IV. DISCUSSION.

A. IFIC’s Claim of Entitlement to the Contract Balance:

IFIC claims that it is entitled to the balance of the adjusted contract balance, that is, $507,488.00 less $100,000 as retainage for any alleged defects pursuant to the Addendum to the Takeover Agreement. The Addendum provides in relevant part:

(a)In sixty (60) days Concra shall pay directly to [IFIC] an amount equal to eighty percent (80%) of the value of work completed after the December 25, 1990 requisition and approved by Morris Associates or their successor with a cap on said payment of two hundred thousand dollars ($200,000)....
(b) In the event Concra fails to pay 80% of the amount approved by Morris Associates or its successor as set forth in sub-paragraph (a), within ten (10) days of approval of the requisition, the parties agree that [IFIC’s] bond will be terminated and the surety discharged of any further liability thereon, unless such failure is cured within three (3) business days of notification to Concra and the bank of such failure.
(c) The balance of the adjusted contract balance less $100,000 to be held as retain-age shall be paid to International Fidelity upon issuance of a certificate of occupancy and the County Department of Social Services’ agreement to take possession of the building.

(Concra Aff. Ex. C, Addendum ¶ 1); (Rosen Aff. Ex. C, Addendum ¶ 1)

IFIC claims that they are entitled to the contract balance because both condition precedents under the Addendum have been met, i.e., (1) that a certificate of occupancy was issued; and °(2) that the Columbia County Department of Social Services took occupancy of the building. It is IFIC’s contention that the Addendum’s language is clear, and is not subject to conflicting interpretations. As to plaintiffs claim of defects, IFIC argues that the Addendum provides for the withholding of $100,000 in the event of any defects. In the alternative, IFIC contends that if the court were to rule that the contract language, and not the Addendum, controls, the building has been substantially complete.

The court concludes that it is the Addendum to the contract which controls the resolution of the dispute between the parties. 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
860 F. Supp. 13, 1994 U.S. Dist. LEXIS 11233, 1994 WL 423443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/concra-v-international-fidelity-insurance-nynd-1994.